§137.330. What happens if the Self-Governance Tribe and the Secretary cannot develop a mutually agreeable construction project agreement?

42 C.F.R. § 137.330

The Self-Governance Tribe may submit a final construction project proposal to the Secretary. No later than 30 days after the Secretary receives the final construction project proposal, or within a longer time agreed to by the Self-Governance Tribe in writing, the Secretary shall review and make a determination to approve or reject the construction project proposal in whole or in part.
Notes, amendments, and revision history

Authority

Authority: 25 U.S.C. 458 et seq.

Source

Source: 67 FR 35342, May 17, 2002, unless otherwise noted.

§137.332. On what basis may the Secretary reject a final construction project proposal?

42 C.F.R. § 137.332

(a)
The only basis for rejection of project activities in a final construction project proposal are—
(1)
The amount of funds proposed in the final construction project proposal exceeds the applicable funding level for the construction project as determined under sections 508(c) [25 U.S.C. 458aaa-7(c)] and 106 of the Act [25 U.S.C. 450j-1].
(2)
The final construction project proposal does not meet the minimum content requirements for construction project agreements set forth in section 501(a)(2) of the Act [25 U.S.C. 458aaa(a)(2)]; and
(3)
The final construction project proposal on its face clearly demonstrates that the construction project cannot be completed as proposed.
(b)
For construction programs proposed to be included in a construction project agreement, the Secretary may also reject that portion of the proposal that proposes to assume an inherently Federal function that cannot legally be delegated to the Self-Governance Tribe.
Notes, amendments, and revision history

Authority

Authority: 25 U.S.C. 458 et seq.

Source

Source: 67 FR 35342, May 17, 2002, unless otherwise noted.

§137.333. What procedures must the Secretary follow if the Secretary rejects a final construction project proposal, in whole or in part?

42 C.F.R. § 137.333

Whenever the Secretary rejects a final construction project proposal in whole or in part, the Secretary must:
(a)
Send the Self-Governance Tribe a timely written notice of rejection that shall set forth specific finding(s) that clearly demonstrates, or that is supported by controlling legal authority supporting the rejection;
(b)
Within 20 days, provide all documents relied on in making the rejection decision to the Self-Governance Tribe;
(c)
Provide assistance to the Self-Governance Tribe to overcome any objections stated in the written notice of rejection;
(d)
Provide the Self-Governance Tribe with a hearing on the record with the right to engage in full discovery relevant to any issue raised in the matter and the opportunity for appeal of the decision to reject the final construction contract proposal, under the regulations set forth in subpart P of this part, except that the Self-Governance Tribe may, in lieu of filing an appeal, initiate an action in Federal district court and proceed directly under sections 511 [25 U.S.C. 458aaa-10] and 110(a) of the Act [25 U.S.C. 450m-1(a)]. With respect to any hearing or appeal or civil action conducted pursuant to this section, the Secretary shall have the burden of demonstrating by clear and convincing evidence the validity of the grounds for rejecting the final construction project proposal (or portion thereof); and
(e)
Provide the Self-Governance Tribe with the option of entering into the severable portions of a final proposed construction project agreement (including a lesser funding amount) that the Secretary did not reject, subject to any additional alterations necessary to conform the construction project agreement to the severed provisions. Exercising this option does not affect the Self-Governance Tribe's right to appeal the portion of the final construction project proposal that was rejected by the Secretary.
Notes, amendments, and revision history

Authority

Authority: 25 U.S.C. 458 et seq.

Source

Source: 67 FR 35342, May 17, 2002, unless otherwise noted.

§137.334. What happens if the Secretary fails to notify the Self-Governance Tribe of a decision to approve or reject a final construction project proposal within the time period allowed?

42 C.F.R. § 137.334

If the Secretary fails to notify the Self-Governance Tribe of the decision to approve or reject within 30 days (or a longer period if agreed to by the Self-Governance Tribe in writing), then the proposal will be deemed approved by the Secretary.