§98.66. Data reporting requirements.

40 C.F.R. § 98.66

In addition to the information required by § 98.3(c), you must report the following information at the facility level:
(a)
[Reserved]
(b)
Type of smelter technology used.
(c)
The following PFC-specific information on an annual basis—
(1)
Perfluoromethane emissions and perfluoroethane emissions from anode effects in all prebake and all Søderberg electrolysis cells combined.
(2)
Anode effect minutes per cell-day (AE-mins/cell-day), anode effect frequency (AE/cell-day), anode effect duration (minutes). (Or anode effect overvoltage factor ((kg CF4/metric ton Al)/(mV/cell day)), potline overvoltage (mV/cell day), current efficiency (%)).
(3)
Smelter-specific slope coefficients (or overvoltage emission factors) and the last date when the smelter-specific slope coefficients (or overvoltage emission factors) were measured.
(d)
Method used to measure the frequency and duration of anode effects (or overvoltage).
(e)
The following CO<I>2</I>-specific information for prebake cells—
(1)
Annual anode consumption if using the method in § 98.63(g).
(2)
Annual CO<I>2</I> emissions from the smelter.
(f)
The following CO<I>2</I>-specific information for Søderberg cells—
(1)
Annual paste consumption if using the method in § 98.63(g).
(2)
Annual CO<I>2</I> emissions from the smelter.
(g)
[Reserved]
(h)
Exact data elements required will vary depending on smelter technology (e.g., point-feed prebake or Søderberg) and process control technology (e.g., Pechiney or other).
Notes, amendments, and revision history

Amendments

[74 FR 56374, Oct. 30, 2009, as amended at 75 FR 79156, Dec. 17, 2010; 79 FR 63784, Oct. 24, 2014; 81 FR 89253, Dec. 9, 2016]

Authority

Authority: 42 U.S.C. 7401-7671q.

Source

Source: 74 FR 56374, Oct. 30, 2009, unless otherwise noted.

Amendments

[74 FR 56374, Oct. 30, 2009, as amended at 75 FR 79156, Dec. 17, 2010; 79 FR 63784, Oct. 24, 2014; 81 FR 89253, Dec. 9, 2016]