§97.22. Information requirements for NO X Budget permit applications. — Inbound Citations
40 C.F.R. § 97.22
Statutory Authority
Cited by 7 regulations in release Current.
Citations to 40 C.F.R. § 97.22 as a whole
-
(a) The NOX authorized account representative of any NOX Budget source required to have a federally enforceable permit shall submit to the permitting authority a complete NOX Budget permit application under § 97.22 by the applicable deadline in paragraph (b) of this section.
-
(a) Each NOX Budget permit will contain, in a format prescribed by the permitting authority, all elements required for a complete NOX Budget permit application under § 97.22.
-
(i) A unit exempt under this section and located at a source that is required, or but for this exemption would be required, to have a title V operating permit shall not resume operation unless the NOX authorized account representative of the source submits a complete NOX Budget permit application under § 97.22 for the unit not less than 18 months (or such lesser time provided by the permitting authority) before the later of May 31, 2004 or the date on which the unit resumes operation.
-
-
(1) A complete NOX Budget permit application under § 97.22;
-
(a) Each NOX Budget opt-in permit will contain all elements required for a complete NOX Budget opt-in permit application under § 97.22.
Citations to §97.22(d)(2)
-
(3) A nitrogen oxides emission rate (or NOX-diluent) monitoring system, consisting of a NOX pollutant concentration monitor, a diluent gas (CO2 or O2) monitor, and an automated DAHS. A NOX concentration monitoring system provides a permanent, continuous record of: NOX concentration in units of parts per million (ppm), diluent gas concentration in units of percent O2 or CO2 (percent O2 or CO2), and NOX emission rate in units of pounds per million British thermal units (lb/mmBtu); and