§93.114. Criteria and procedures: Currently conforming transportation plan and TIP.

40 C.F.R. § 93.114

There must be a currently conforming transportation plan and currently conforming TIP at the time of project approval, or a project must meet the requirements in § 93.104(f) during the 12-month lapse grace period.
(a)
Only one conforming transportation plan or TIP may exist in an area at any time; conformity determinations of a previous transportation plan or TIP expire once the current plan or TIP is found to conform by DOT. The conformity determination on a transportation plan or TIP will also lapse if conformity is not determined according to the frequency requirements specified in § 93.104.
(b)
This criterion is not required to be satisfied at the time of project approval for a TCM specifically included in the applicable implementation plan, provided that all other relevant criteria of this subpart are satisfied.
Notes, amendments, and revision history

Amendments

[62 FR 43801, Aug. 15, 1997, as amended at 73 FR 4440, Jan. 24, 2008]

Source

Source: 62 FR 43801, Aug. 15, 1997, unless otherwise noted.

Authority

Authority: 42 U.S.C. 7401-7671q.