§75.61. Notifications. — Inbound Citations

40 C.F.R. § 75.61

Cited by 30 regulations in release Current.

Citations to 40 U.S.C. § 75.61 as a whole

  • (1) The owner or operator shall maintain and operate CEMS for SO2, NO or NOX, a diluent and, for Units 4 and 5 only, COMS, in accordance with 40 CFR 60.8 and 60.13, and appendix B of 40 CFR part 60. Within six (6) months of promulgation of this section, the owner or operator shall install CEMS and COMS software which complies with the requirements of this section. The owner or operator of the Plant may petition the Regional Administrator for extension of the six (6) month period for good cause shown. Completion of 40 CFR part 75 monitor certification requirements shall be deemed to satisfy the requirements under 40 CFR 60.8 and 60.13 and appendix B of part 60. The owner or operator shall comply with the quality assurance procedures for CEMS found in 40 CFR part 75, and all reports required thereunder shall be submitted to the Regional Administrator. The owner or operator shall provide the Regional Administrator notice in accordance with 40 CFR 75.61.
  • (b) You must prepare and submit notifications specified in § 75.61 of this chapter, as applicable, to your affected EGUs.
  • (b) You must prepare and submit notifications specified in 40 CFR 75.61, as applicable, to your affected EGUs.
  • (2) The designated representative shall provide initial certification testing notification, recertification testing notification, and routine periodic quality-assurance testing, as specified in § 75.61. Initial certification testing notification, recertification testing notification, or periodic quality assurance testing notification is not required for an excepted monitoring system under appendix D to this part.
  • (d) The owner or operator or the designated representative shall submit a written notice of the dates of relative accuracy testing as specified in § 75.61.
  • (b) No owner or operator of an affected unit shall operate the unit without complying with the requirements of §§ 75.2 through 75.75 and appendices A through G to this part.
  • (b) The designated representative shall submit all reports and petitions (except as provided in § 75.61) as follows:
    (1) The designated representative shall submit initial certification applications according to § 75.63.
    (2) The designated representative shall submit recertification applications according to § 75.63.
    (3) The designated representative shall submit monitoring plans according to § 75.62.
    (4) The designated representative shall submit electronic quarterly reports according to § 75.64.
    (5) The designated representative shall submit petitions, correspondence, application forms, designated representative signature, and petition-related test results in hardcopy to the Administrator. Additional petition requirements are specified in §§ 75.66 and 75.67.
    (6) If requested in writing (or by electronic mail) by the applicable EPA Regional Office, appropriate State, and/or appropriate local air pollution control agency, the designated representative shall submit a hardcopy RATA report within 45 days after completing a required semiannual or annual RATA according to section 2.3.1 of appendix B to this part, or within 15 days of receiving the request, whichever is later. The designated representative shall report the hardcopy information required by § 75.59(a)(9) to the applicable EPA Regional Office, appropriate State, and/or appropriate local air pollution control agency that requested the RATA report.
    (7) If requested in writing (or by electronic mail) by the applicable EPA Regional Office, appropriate State, and/or appropriate local air pollution control agency, the designated representative shall submit a hardcopy report within 45 days after completing a required periodic retest according to section 2.2 of appendix E to this part, or within 15 days of receiving the request, whichever is later. The designated representative shall report the hardcopy information required by § 75.59(b)(5) to the applicable EPA Regional Office, appropriate State, and/or appropriate local air pollution control agency that requested the hardcopy report.
  • (iii) The designated representative submits notification of the date of certification testing of a replacement monitoring system in accordance with § 75.61.
  • (5) The designated representative for an affected unit shall submit written notice to the permitting authority according to the provisions in § 75.61 for each affected unit or group of units monitored at a common stack and each non-affected unit under § 75.72(b)(2)(ii).
  • The CAIR designated representative for a CAIR NOX unit shall submit written notice to the permitting authority and the Administrator in accordance with § 75.61 of this chapter.
  • The CAIR designated representative for a CAIR SO2 unit shall submit written notice to the permitting authority and the Administrator in accordance with § 75.61 of this chapter.
  • The CAIR designated representative for a CAIR NOX Ozone Season unit shall submit written notice to the permitting authority and the Administrator in accordance with § 75.61 of this chapter.
  • The NOX authorized account representative for a NOX Budget unit shall submit written notice to the permitting authority and the Administrator in accordance with § 75.61 of this chapter, except that if the unit is not subject to an Acid Rain emissions limitation, the notification is only required to be sent to the permitting authority.
  • The designated representative of a CSAPR NOX Ozone Season Group 3 unit shall submit written notice to the Administrator in accordance with § 75.61 of this chapter.
  • The CAIR designated representative for a CAIR NOX unit shall submit written notice to the Administrator in accordance with § 75.61 of this chapter.
  • The CAIR designated representative for a CAIR SO2 unit shall submit written notice to the Administrator in accordance with § 75.61 of this chapter. § 97.274 Recordkeeping and reporting.
  • The CAIR designated representative for a CAIR NOX Ozone Season unit shall submit written notice to the Administrator in accordance with § 75.61 of this chapter.
  • The designated representative of a CSAPR NOX Annual unit shall submit written notice to the Administrator in accordance with § 75.61 of this chapter.
  • The designated representative of a CSAPR NOX Ozone Season Group 1 unit shall submit written notice to the Administrator in accordance with § 75.61 of this chapter.
  • The designated representative of a CSAPR SO2 Group 1 unit shall submit written notice to the Administrator in accordance with § 75.61 of this chapter.
  • (a) The NOX authorized account representative for a NOX Budget unit shall submit written notice to the Administrator, the appropriate EPA Regional Office, and the permitting authority in accordance with § 75.61 of this chapter.
  • The designated representative of a CSAPR SO2 Group 2 unit shall submit written notice to the Administrator in accordance with § 75.61 of this chapter.
  • The designated representative of a CSAPR NOX Ozone Season Group 2 unit shall submit written notice to the Administrator in accordance with § 75.61 of this chapter.
  • The designated representative of a Texas SO2 Trading Program unit shall submit written notice to the Administrator in accordance with § 75.61 of this chapter.

Citations to §75.61(a)(1)

Citations to §75.61(a)(1)(i)

  • (2) The owner, operator, or designated representative shall submit notice of testing dates for recertification under this paragraph as specified in § 75.61(a)(1)(ii), unless all of the tests in paragraph (c) of this section are required for recertification, in which case the owner or operator shall provide notice in accordance with the notice provisions for initial certification testing in § 75.61(a)(1)(i).

Citations to §75.61(a)(1)(ii)

Citations to §75.61(a)(3)

  • (d) This paragraph (d) applies to affected units under the Acid Rain Program and to units subject to a State or Federal pollutant mass emissions reduction program that adopts the emission monitoring and reporting provisions of this part. In accordance with § 75.20, for an affected unit which, on the applicable compliance date, is either in long-term cold storage (as defined in § 72.2 of this chapter) or is shut down as the result of a planned outage or a forced outage, thereby preventing the required continuous monitoring system certification tests from being completed by the compliance date, the owner or operator shall provide notice of such unit storage or outage in accordance with § 75.61(a)(3) or § 75.61(a)(7), as applicable. For the planned and unplanned unit outages described in this paragraph (d), the owner or operator shall ensure that all of the continuous monitoring systems for SO2, NOX, CO2, opacity, and volumetric flow rate required under this part (or under the applicable State or Federal mass emissions reduction program) are installed and that all required certification tests are completed no later than 90 unit operating days or 180 calendar days (whichever occurs first) after the date that the unit recommences commercial operation, notice of which date shall be provided under § 75.61(a)(3) or § 75.61(a)(7), as applicable. The owner or operator shall determine and report SO2 concentration, NOX emission rate, CO2 concentration, and flow rate data (as applicable) for all unit operating hours after the applicable compliance date until all of the required certification tests are successfully completed, using either:
    (1) The maximum potential concentration of SO2 (as defined in section 2.1.1.1 of appendix A to this part), the maximum potential NOX emission rate, as defined in § 72.2 of this chapter, the maximum potential flow rate, as defined in section 2.1.4.1 of appendix A to this part, or the maximum potential CO2 concentration, as defined in section 2.1.3.1 of appendix A to this part; or
    (2) The conditional data validation provisions of § 75.20(b)(3); or
    (3) Reference methods under § 75.22(b); or
    (4) Another procedure approved by the Administrator pursuant to a petition under § 75.66.

Citations to §75.61(a)(7)

  • (3) The response of a continuous opacity monitoring system to an attenuation filter and the known value of the filter after a stated period of operation during which no unscheduled maintenance, repair, or adjustment took place.
    Calibration gas means:
  • (d) This paragraph (d) applies to affected units under the Acid Rain Program and to units subject to a State or Federal pollutant mass emissions reduction program that adopts the emission monitoring and reporting provisions of this part. In accordance with § 75.20, for an affected unit which, on the applicable compliance date, is either in long-term cold storage (as defined in § 72.2 of this chapter) or is shut down as the result of a planned outage or a forced outage, thereby preventing the required continuous monitoring system certification tests from being completed by the compliance date, the owner or operator shall provide notice of such unit storage or outage in accordance with § 75.61(a)(3) or § 75.61(a)(7), as applicable. For the planned and unplanned unit outages described in this paragraph (d), the owner or operator shall ensure that all of the continuous monitoring systems for SO2, NOX, CO2, opacity, and volumetric flow rate required under this part (or under the applicable State or Federal mass emissions reduction program) are installed and that all required certification tests are completed no later than 90 unit operating days or 180 calendar days (whichever occurs first) after the date that the unit recommences commercial operation, notice of which date shall be provided under § 75.61(a)(3) or § 75.61(a)(7), as applicable. The owner or operator shall determine and report SO2 concentration, NOX emission rate, CO2 concentration, and flow rate data (as applicable) for all unit operating hours after the applicable compliance date until all of the required certification tests are successfully completed, using either:
    (1) The maximum potential concentration of SO2 (as defined in section 2.1.1.1 of appendix A to this part), the maximum potential NOX emission rate, as defined in § 72.2 of this chapter, the maximum potential flow rate, as defined in section 2.1.4.1 of appendix A to this part, or the maximum potential CO2 concentration, as defined in section 2.1.3.1 of appendix A to this part; or
    (2) The conditional data validation provisions of § 75.20(b)(3); or
    (3) Reference methods under § 75.22(b); or
    (4) Another procedure approved by the Administrator pursuant to a petition under § 75.66.