§63.8243. What equations and procedures must I use to demonstrate continuous compliance? — Inbound Citations

40 C.F.R. § 63.8243

Cited by 5 regulations in release Current.

Citations to 40 U.S.C. § 63.8243 as a whole

  • (1) For all by-product hydrogen streams and all end box ventilation system vents, if applicable, you must demonstrate continuous compliance with the applicable mercury emission limit by reducing the mercury emissions data to 52-week averages using Equation 1 of § 63.8243 and maintaining the 52-week average mercury emissions no higher than the applicable mercury emissions limit in § 63.8190(a)(2). To obtain the data to calculate these 52-week averages, you must monitor in accordance with paragraph (a)(1)(i) or (ii) of this section.
    (i) You must collect mercury emissions data according to § 63.8244(a), representing at least 75 percent of the 15-minute periods in each operating day of the 52-week compliance period (with data recorded during monitoring malfunctions, associated repairs, and required quality assurance or control activities not counting toward the 75 percent requirement);
    (ii) You must conduct at least three test runs per week to collect mercury emissions samples according to § 63.8244(b)(1) and (2)(i) and, if your final control device is not a nonregenerable carbon adsorber, you must collect data for monitoring values according to § 63.8244(b)(2)(ii) through (v).

Citations to §63.8243(a)

  • (i) During any consecutive 52-week period, you must not discharge to the atmosphere total mercury emissions in excess of the applicable limit in paragraph (a)(2)(i)(A) or (B) of this section calculated using the procedures in § 63.8243(a).
    (A) 0.076 grams of mercury per megagram of chlorine produced (1.5 × 10−4 pounds of mercury per ton of chlorine produced) from all by-product hydrogen streams and all end box ventilation system vents when both types of emission points are present.
    (B) 0.033 grams of mercury per megagram of chlorine produced (6.59 × 10−5 pounds of mercury per ton of chlorine produced) from all by-product hydrogen streams when end box ventilation systems are not present.

Citations to §63.8243(a)(1)

  • (a) For each consecutive 52-week period, you must determine the g Hg/Mg Cl2 produced from all by-product hydrogen streams and all end box ventilation system vents, if applicable, at a mercury cell chlor-alkali production facility using the procedures in paragraphs (a)(1) through (3) of this section. You must begin collecting data on the compliance date that is specified in § 63.8186 for your affected source and calculate your first 52-week average mercury emission rate at the end of the 52nd week after the compliance date.
    (1) Each week, you must determine the weekly mercury emission rate in grams per week for each by-product hydrogen stream and for each end box ventilation system vent, if applicable, using one of the monitoring options in paragraph (a)(1)(i) or (ii) of this section.
    (i) Continuous mercury monitoring according to §§ 63.8242 and 63.8244(a).
    (ii) Periodic monitoring according to § 63.8244(b).
    (2) Each week, you must determine the chlorine production and keep records of the production rate as required under § 63.8256(b)(6).
    (3) Beginning 52 weeks after the compliance date specified in § 63.8186 for your affected source, you must calculate the 52-week average mercury emission rate from all by-product hydrogen steam and all end box ventilation system vents, if applicable, using Equation 1 of this section as follows:

Citations to §63.8243(a)(2)

  • (a) For each consecutive 52-week period, you must determine the g Hg/Mg Cl2 produced from all by-product hydrogen streams and all end box ventilation system vents, if applicable, at a mercury cell chlor-alkali production facility using the procedures in paragraphs (a)(1) through (3) of this section. You must begin collecting data on the compliance date that is specified in § 63.8186 for your affected source and calculate your first 52-week average mercury emission rate at the end of the 52nd week after the compliance date.
    (1) Each week, you must determine the weekly mercury emission rate in grams per week for each by-product hydrogen stream and for each end box ventilation system vent, if applicable, using one of the monitoring options in paragraph (a)(1)(i) or (ii) of this section.
    (i) Continuous mercury monitoring according to §§ 63.8242 and 63.8244(a).
    (ii) Periodic monitoring according to § 63.8244(b).
    (2) Each week, you must determine the chlorine production and keep records of the production rate as required under § 63.8256(b)(6).
    (3) Beginning 52 weeks after the compliance date specified in § 63.8186 for your affected source, you must calculate the 52-week average mercury emission rate from all by-product hydrogen steam and all end box ventilation system vents, if applicable, using Equation 1 of this section as follows:

Citations to §63.8243(a)(3)

  • (a) For each consecutive 52-week period, you must determine the g Hg/Mg Cl2 produced from all by-product hydrogen streams and all end box ventilation system vents, if applicable, at a mercury cell chlor-alkali production facility using the procedures in paragraphs (a)(1) through (3) of this section. You must begin collecting data on the compliance date that is specified in § 63.8186 for your affected source and calculate your first 52-week average mercury emission rate at the end of the 52nd week after the compliance date.
    (1) Each week, you must determine the weekly mercury emission rate in grams per week for each by-product hydrogen stream and for each end box ventilation system vent, if applicable, using one of the monitoring options in paragraph (a)(1)(i) or (ii) of this section.
    (i) Continuous mercury monitoring according to §§ 63.8242 and 63.8244(a).
    (ii) Periodic monitoring according to § 63.8244(b).
    (2) Each week, you must determine the chlorine production and keep records of the production rate as required under § 63.8256(b)(6).
    (3) Beginning 52 weeks after the compliance date specified in § 63.8186 for your affected source, you must calculate the 52-week average mercury emission rate from all by-product hydrogen steam and all end box ventilation system vents, if applicable, using Equation 1 of this section as follows: