§63.7341. What reports must I submit and when? — Inbound Citations
40 C.F.R. § 63.7341
Statutory Authority
Cited by 27 regulations in release Current.
Citations to 40 U.S.C. § 63.7341 as a whole
-
(c) Report opacity exceedances in any HNR HRSG bypass or HNR waste heat stacks in the quarterly semiannual compliance report required by § 63.7341.
-
You must report each instance in which you did not meet each emission limitation in this subpart that applies to you. This includes periods of startup, shutdown, and malfunction. You must also report each instance in which you did not meet each work practice standard or operation and maintenance requirement in this subpart that applies to you. These instances are deviations from the emission limitations (including operating limits), work practice standards, and operation and maintenance requirements in this subpart. These deviations must be reported according to the requirements in § 63.7341.
Citations to §63.7341(a)(1)
-
(a) Unless the Administrator has approved a different schedule, you must submit quarterly compliance reports for battery stacks and semiannual compliance reports for all other affected sources to your permitting authority according to the requirements in paragraphs (a)(1) through (4) of this section.(1) The first quarterly compliance report for battery stacks must cover the period beginning on the compliance date that is specified for your affected source in § 63.7283 and ending on the last date of the third calendar month. Each subsequent compliance report must cover the next calendar quarter.(2) The first semiannual compliance report must cover the period beginning on the compliance date that is specified for your affected source in § 63.7283 and ending on June 30 or December 31, whichever date comes first after the compliance date that is specified for your affected source. Each subsequent compliance report must cover the semiannual reporting period from January 1 through June 30 or the semiannual reporting period from July 1 through December 31.(3) All quarterly compliance reports for battery stacks must be postmarked or delivered no later than one calendar month following the end of the quarterly reporting period. All semiannual compliance reports must be postmarked or delivered no later than July 31 or January 31, whichever date is the first date following the end of the semiannual reporting period.(4) For each affected source that is subject to permitting regulations pursuant to 40 CFR part 70 or 40 CFR part 71, and if the permitting authority has established dates for submitting semiannual reports pursuant to 40 CFR 70.6(a)(3)(iii)(A) or 40 CFR 71.6(a)(3)(iii)(A), you may submit the first and subsequent compliance reports according to the dates the permitting authority has established instead of according to the dates in paragraphs (a)(1) through (4) of this section.
Citations to §63.7341(a)(2)
-
(a) Unless the Administrator has approved a different schedule, you must submit quarterly compliance reports for battery stacks and semiannual compliance reports for all other affected sources to your permitting authority according to the requirements in paragraphs (a)(1) through (4) of this section.(1) The first quarterly compliance report for battery stacks must cover the period beginning on the compliance date that is specified for your affected source in § 63.7283 and ending on the last date of the third calendar month. Each subsequent compliance report must cover the next calendar quarter.(2) The first semiannual compliance report must cover the period beginning on the compliance date that is specified for your affected source in § 63.7283 and ending on June 30 or December 31, whichever date comes first after the compliance date that is specified for your affected source. Each subsequent compliance report must cover the semiannual reporting period from January 1 through June 30 or the semiannual reporting period from July 1 through December 31.(3) All quarterly compliance reports for battery stacks must be postmarked or delivered no later than one calendar month following the end of the quarterly reporting period. All semiannual compliance reports must be postmarked or delivered no later than July 31 or January 31, whichever date is the first date following the end of the semiannual reporting period.(4) For each affected source that is subject to permitting regulations pursuant to 40 CFR part 70 or 40 CFR part 71, and if the permitting authority has established dates for submitting semiannual reports pursuant to 40 CFR 70.6(a)(3)(iii)(A) or 40 CFR 71.6(a)(3)(iii)(A), you may submit the first and subsequent compliance reports according to the dates the permitting authority has established instead of according to the dates in paragraphs (a)(1) through (4) of this section.
Citations to §63.7341(a)(3)
-
(a) Unless the Administrator has approved a different schedule, you must submit quarterly compliance reports for battery stacks and semiannual compliance reports for all other affected sources to your permitting authority according to the requirements in paragraphs (a)(1) through (4) of this section.(1) The first quarterly compliance report for battery stacks must cover the period beginning on the compliance date that is specified for your affected source in § 63.7283 and ending on the last date of the third calendar month. Each subsequent compliance report must cover the next calendar quarter.(2) The first semiannual compliance report must cover the period beginning on the compliance date that is specified for your affected source in § 63.7283 and ending on June 30 or December 31, whichever date comes first after the compliance date that is specified for your affected source. Each subsequent compliance report must cover the semiannual reporting period from January 1 through June 30 or the semiannual reporting period from July 1 through December 31.(3) All quarterly compliance reports for battery stacks must be postmarked or delivered no later than one calendar month following the end of the quarterly reporting period. All semiannual compliance reports must be postmarked or delivered no later than July 31 or January 31, whichever date is the first date following the end of the semiannual reporting period.(4) For each affected source that is subject to permitting regulations pursuant to 40 CFR part 70 or 40 CFR part 71, and if the permitting authority has established dates for submitting semiannual reports pursuant to 40 CFR 70.6(a)(3)(iii)(A) or 40 CFR 71.6(a)(3)(iii)(A), you may submit the first and subsequent compliance reports according to the dates the permitting authority has established instead of according to the dates in paragraphs (a)(1) through (4) of this section.
Citations to §63.7341(a)(4)
-
(a) Unless the Administrator has approved a different schedule, you must submit quarterly compliance reports for battery stacks and semiannual compliance reports for all other affected sources to your permitting authority according to the requirements in paragraphs (a)(1) through (4) of this section.(1) The first quarterly compliance report for battery stacks must cover the period beginning on the compliance date that is specified for your affected source in § 63.7283 and ending on the last date of the third calendar month. Each subsequent compliance report must cover the next calendar quarter.(2) The first semiannual compliance report must cover the period beginning on the compliance date that is specified for your affected source in § 63.7283 and ending on June 30 or December 31, whichever date comes first after the compliance date that is specified for your affected source. Each subsequent compliance report must cover the semiannual reporting period from January 1 through June 30 or the semiannual reporting period from July 1 through December 31.(3) All quarterly compliance reports for battery stacks must be postmarked or delivered no later than one calendar month following the end of the quarterly reporting period. All semiannual compliance reports must be postmarked or delivered no later than July 31 or January 31, whichever date is the first date following the end of the semiannual reporting period.(4) For each affected source that is subject to permitting regulations pursuant to 40 CFR part 70 or 40 CFR part 71, and if the permitting authority has established dates for submitting semiannual reports pursuant to 40 CFR 70.6(a)(3)(iii)(A) or 40 CFR 71.6(a)(3)(iii)(A), you may submit the first and subsequent compliance reports according to the dates the permitting authority has established instead of according to the dates in paragraphs (a)(1) through (4) of this section.
Citations to §63.7341(c)(1)
-
(b) Each quarterly report must provide information on compliance with the emission limitations for battery stacks in § 63.7296. The reports must include the information in paragraphs (c)(1) through (3), and as applicable, paragraphs (c)(4) through (8) of this section.
Citations to §63.7341(c)(2)
-
(b) Each quarterly report must provide information on compliance with the emission limitations for battery stacks in § 63.7296. The reports must include the information in paragraphs (c)(1) through (3), and as applicable, paragraphs (c)(4) through (8) of this section.
Citations to §63.7341(c)(3)
-
(b) Each quarterly report must provide information on compliance with the emission limitations for battery stacks in § 63.7296. The reports must include the information in paragraphs (c)(1) through (3), and as applicable, paragraphs (c)(4) through (8) of this section.
Citations to §63.7341(c)(4)
-
(b) Each quarterly report must provide information on compliance with the emission limitations for battery stacks in § 63.7296. The reports must include the information in paragraphs (c)(1) through (3), and as applicable, paragraphs (c)(4) through (8) of this section.
Citations to §63.7341(c)(5)
-
(b) Each quarterly report must provide information on compliance with the emission limitations for battery stacks in § 63.7296. The reports must include the information in paragraphs (c)(1) through (3), and as applicable, paragraphs (c)(4) through (8) of this section.
Citations to §63.7341(c)(6)
-
(b) Each quarterly report must provide information on compliance with the emission limitations for battery stacks in § 63.7296. The reports must include the information in paragraphs (c)(1) through (3), and as applicable, paragraphs (c)(4) through (8) of this section.
Citations to §63.7341(c)(7)
-
(b) Each quarterly report must provide information on compliance with the emission limitations for battery stacks in § 63.7296. The reports must include the information in paragraphs (c)(1) through (3), and as applicable, paragraphs (c)(4) through (8) of this section.
Citations to §63.7341(c)(8)
-
(b) Each quarterly report must provide information on compliance with the emission limitations for battery stacks in § 63.7296. The reports must include the information in paragraphs (c)(1) through (3), and as applicable, paragraphs (c)(4) through (8) of this section.
Citations to §63.7341(c)(8)(i)
-
(8) For each deviation from an emission limitation occurring at an affected source where you are using a continuous monitoring system (including COMS, CEMS, or CPMS) to comply with the emission limitation in this subpart, you must include the information in paragraphs (c)(4) and (8)(i) through (xii) of this section. This includes periods of startup, shutdown, and malfunction.(ii) The start date, start time, and duration in hours that each continuous monitoring system (including COMS, CEMS, or CPMS) was inoperative, except for zero (low-level) and high-level checks.(iii) The start date, start time, and duration in hours that each continuous monitoring system (including COMS, CEMS, or CPMS) was out-of-control, including the information in § 63.8(c)(8).(iv) The date and time that each deviation started and stopped, the duration in hours, and whether each deviation occurred during a period of startup, shutdown, or malfunction or during another period.(v) A summary of the total duration in hours of the deviation during the reporting period and the total duration as a percent of the total source operating time during that reporting period.(vi) A breakdown of the total duration in hours of the deviations during the reporting period into those that are due to startup, shutdown, control equipment problems, process problems, other known causes, and other unknown causes.(vii) A summary of the total duration in hours of continuous monitoring system downtime during the reporting period and the total duration of continuous monitoring system downtime as a percent of the total source operating time during the reporting period.(xii) A description of any changes in continuous monitoring systems, processes, or controls since the last reporting period.
Citations to §63.7341(c)(8)(ii)
-
(8) For each deviation from an emission limitation occurring at an affected source where you are using a continuous monitoring system (including COMS, CEMS, or CPMS) to comply with the emission limitation in this subpart, you must include the information in paragraphs (c)(4) and (8)(i) through (xii) of this section. This includes periods of startup, shutdown, and malfunction.(ii) The start date, start time, and duration in hours that each continuous monitoring system (including COMS, CEMS, or CPMS) was inoperative, except for zero (low-level) and high-level checks.(iii) The start date, start time, and duration in hours that each continuous monitoring system (including COMS, CEMS, or CPMS) was out-of-control, including the information in § 63.8(c)(8).(iv) The date and time that each deviation started and stopped, the duration in hours, and whether each deviation occurred during a period of startup, shutdown, or malfunction or during another period.(v) A summary of the total duration in hours of the deviation during the reporting period and the total duration as a percent of the total source operating time during that reporting period.(vi) A breakdown of the total duration in hours of the deviations during the reporting period into those that are due to startup, shutdown, control equipment problems, process problems, other known causes, and other unknown causes.(vii) A summary of the total duration in hours of continuous monitoring system downtime during the reporting period and the total duration of continuous monitoring system downtime as a percent of the total source operating time during the reporting period.(xii) A description of any changes in continuous monitoring systems, processes, or controls since the last reporting period.
Citations to §63.7341(c)(8)(iii)
-
(8) For each deviation from an emission limitation occurring at an affected source where you are using a continuous monitoring system (including COMS, CEMS, or CPMS) to comply with the emission limitation in this subpart, you must include the information in paragraphs (c)(4) and (8)(i) through (xii) of this section. This includes periods of startup, shutdown, and malfunction.(ii) The start date, start time, and duration in hours that each continuous monitoring system (including COMS, CEMS, or CPMS) was inoperative, except for zero (low-level) and high-level checks.(iii) The start date, start time, and duration in hours that each continuous monitoring system (including COMS, CEMS, or CPMS) was out-of-control, including the information in § 63.8(c)(8).(iv) The date and time that each deviation started and stopped, the duration in hours, and whether each deviation occurred during a period of startup, shutdown, or malfunction or during another period.(v) A summary of the total duration in hours of the deviation during the reporting period and the total duration as a percent of the total source operating time during that reporting period.(vi) A breakdown of the total duration in hours of the deviations during the reporting period into those that are due to startup, shutdown, control equipment problems, process problems, other known causes, and other unknown causes.(vii) A summary of the total duration in hours of continuous monitoring system downtime during the reporting period and the total duration of continuous monitoring system downtime as a percent of the total source operating time during the reporting period.(xii) A description of any changes in continuous monitoring systems, processes, or controls since the last reporting period.
Citations to §63.7341(c)(8)(iv)
-
(8) For each deviation from an emission limitation occurring at an affected source where you are using a continuous monitoring system (including COMS, CEMS, or CPMS) to comply with the emission limitation in this subpart, you must include the information in paragraphs (c)(4) and (8)(i) through (xii) of this section. This includes periods of startup, shutdown, and malfunction.(ii) The start date, start time, and duration in hours that each continuous monitoring system (including COMS, CEMS, or CPMS) was inoperative, except for zero (low-level) and high-level checks.(iii) The start date, start time, and duration in hours that each continuous monitoring system (including COMS, CEMS, or CPMS) was out-of-control, including the information in § 63.8(c)(8).(iv) The date and time that each deviation started and stopped, the duration in hours, and whether each deviation occurred during a period of startup, shutdown, or malfunction or during another period.(v) A summary of the total duration in hours of the deviation during the reporting period and the total duration as a percent of the total source operating time during that reporting period.(vi) A breakdown of the total duration in hours of the deviations during the reporting period into those that are due to startup, shutdown, control equipment problems, process problems, other known causes, and other unknown causes.(vii) A summary of the total duration in hours of continuous monitoring system downtime during the reporting period and the total duration of continuous monitoring system downtime as a percent of the total source operating time during the reporting period.(xii) A description of any changes in continuous monitoring systems, processes, or controls since the last reporting period.
Citations to §63.7341(c)(8)(ix)
-
(8) For each deviation from an emission limitation occurring at an affected source where you are using a continuous monitoring system (including COMS, CEMS, or CPMS) to comply with the emission limitation in this subpart, you must include the information in paragraphs (c)(4) and (8)(i) through (xii) of this section. This includes periods of startup, shutdown, and malfunction.(ii) The start date, start time, and duration in hours that each continuous monitoring system (including COMS, CEMS, or CPMS) was inoperative, except for zero (low-level) and high-level checks.(iii) The start date, start time, and duration in hours that each continuous monitoring system (including COMS, CEMS, or CPMS) was out-of-control, including the information in § 63.8(c)(8).(iv) The date and time that each deviation started and stopped, the duration in hours, and whether each deviation occurred during a period of startup, shutdown, or malfunction or during another period.(v) A summary of the total duration in hours of the deviation during the reporting period and the total duration as a percent of the total source operating time during that reporting period.(vi) A breakdown of the total duration in hours of the deviations during the reporting period into those that are due to startup, shutdown, control equipment problems, process problems, other known causes, and other unknown causes.(vii) A summary of the total duration in hours of continuous monitoring system downtime during the reporting period and the total duration of continuous monitoring system downtime as a percent of the total source operating time during the reporting period.(xii) A description of any changes in continuous monitoring systems, processes, or controls since the last reporting period.
Citations to §63.7341(c)(8)(v)
-
(8) For each deviation from an emission limitation occurring at an affected source where you are using a continuous monitoring system (including COMS, CEMS, or CPMS) to comply with the emission limitation in this subpart, you must include the information in paragraphs (c)(4) and (8)(i) through (xii) of this section. This includes periods of startup, shutdown, and malfunction.(ii) The start date, start time, and duration in hours that each continuous monitoring system (including COMS, CEMS, or CPMS) was inoperative, except for zero (low-level) and high-level checks.(iii) The start date, start time, and duration in hours that each continuous monitoring system (including COMS, CEMS, or CPMS) was out-of-control, including the information in § 63.8(c)(8).(iv) The date and time that each deviation started and stopped, the duration in hours, and whether each deviation occurred during a period of startup, shutdown, or malfunction or during another period.(v) A summary of the total duration in hours of the deviation during the reporting period and the total duration as a percent of the total source operating time during that reporting period.(vi) A breakdown of the total duration in hours of the deviations during the reporting period into those that are due to startup, shutdown, control equipment problems, process problems, other known causes, and other unknown causes.(vii) A summary of the total duration in hours of continuous monitoring system downtime during the reporting period and the total duration of continuous monitoring system downtime as a percent of the total source operating time during the reporting period.(xii) A description of any changes in continuous monitoring systems, processes, or controls since the last reporting period.
Citations to §63.7341(c)(8)(vi)
-
(8) For each deviation from an emission limitation occurring at an affected source where you are using a continuous monitoring system (including COMS, CEMS, or CPMS) to comply with the emission limitation in this subpart, you must include the information in paragraphs (c)(4) and (8)(i) through (xii) of this section. This includes periods of startup, shutdown, and malfunction.(ii) The start date, start time, and duration in hours that each continuous monitoring system (including COMS, CEMS, or CPMS) was inoperative, except for zero (low-level) and high-level checks.(iii) The start date, start time, and duration in hours that each continuous monitoring system (including COMS, CEMS, or CPMS) was out-of-control, including the information in § 63.8(c)(8).(iv) The date and time that each deviation started and stopped, the duration in hours, and whether each deviation occurred during a period of startup, shutdown, or malfunction or during another period.(v) A summary of the total duration in hours of the deviation during the reporting period and the total duration as a percent of the total source operating time during that reporting period.(vi) A breakdown of the total duration in hours of the deviations during the reporting period into those that are due to startup, shutdown, control equipment problems, process problems, other known causes, and other unknown causes.(vii) A summary of the total duration in hours of continuous monitoring system downtime during the reporting period and the total duration of continuous monitoring system downtime as a percent of the total source operating time during the reporting period.(xii) A description of any changes in continuous monitoring systems, processes, or controls since the last reporting period.
Citations to §63.7341(c)(8)(vii)
-
(8) For each deviation from an emission limitation occurring at an affected source where you are using a continuous monitoring system (including COMS, CEMS, or CPMS) to comply with the emission limitation in this subpart, you must include the information in paragraphs (c)(4) and (8)(i) through (xii) of this section. This includes periods of startup, shutdown, and malfunction.(ii) The start date, start time, and duration in hours that each continuous monitoring system (including COMS, CEMS, or CPMS) was inoperative, except for zero (low-level) and high-level checks.(iii) The start date, start time, and duration in hours that each continuous monitoring system (including COMS, CEMS, or CPMS) was out-of-control, including the information in § 63.8(c)(8).(iv) The date and time that each deviation started and stopped, the duration in hours, and whether each deviation occurred during a period of startup, shutdown, or malfunction or during another period.(v) A summary of the total duration in hours of the deviation during the reporting period and the total duration as a percent of the total source operating time during that reporting period.(vi) A breakdown of the total duration in hours of the deviations during the reporting period into those that are due to startup, shutdown, control equipment problems, process problems, other known causes, and other unknown causes.(vii) A summary of the total duration in hours of continuous monitoring system downtime during the reporting period and the total duration of continuous monitoring system downtime as a percent of the total source operating time during the reporting period.(xii) A description of any changes in continuous monitoring systems, processes, or controls since the last reporting period.
Citations to §63.7341(c)(8)(viii)
-
(8) For each deviation from an emission limitation occurring at an affected source where you are using a continuous monitoring system (including COMS, CEMS, or CPMS) to comply with the emission limitation in this subpart, you must include the information in paragraphs (c)(4) and (8)(i) through (xii) of this section. This includes periods of startup, shutdown, and malfunction.(ii) The start date, start time, and duration in hours that each continuous monitoring system (including COMS, CEMS, or CPMS) was inoperative, except for zero (low-level) and high-level checks.(iii) The start date, start time, and duration in hours that each continuous monitoring system (including COMS, CEMS, or CPMS) was out-of-control, including the information in § 63.8(c)(8).(iv) The date and time that each deviation started and stopped, the duration in hours, and whether each deviation occurred during a period of startup, shutdown, or malfunction or during another period.(v) A summary of the total duration in hours of the deviation during the reporting period and the total duration as a percent of the total source operating time during that reporting period.(vi) A breakdown of the total duration in hours of the deviations during the reporting period into those that are due to startup, shutdown, control equipment problems, process problems, other known causes, and other unknown causes.(vii) A summary of the total duration in hours of continuous monitoring system downtime during the reporting period and the total duration of continuous monitoring system downtime as a percent of the total source operating time during the reporting period.(xii) A description of any changes in continuous monitoring systems, processes, or controls since the last reporting period.
Citations to §63.7341(c)(8)(x)
-
(8) For each deviation from an emission limitation occurring at an affected source where you are using a continuous monitoring system (including COMS, CEMS, or CPMS) to comply with the emission limitation in this subpart, you must include the information in paragraphs (c)(4) and (8)(i) through (xii) of this section. This includes periods of startup, shutdown, and malfunction.(ii) The start date, start time, and duration in hours that each continuous monitoring system (including COMS, CEMS, or CPMS) was inoperative, except for zero (low-level) and high-level checks.(iii) The start date, start time, and duration in hours that each continuous monitoring system (including COMS, CEMS, or CPMS) was out-of-control, including the information in § 63.8(c)(8).(iv) The date and time that each deviation started and stopped, the duration in hours, and whether each deviation occurred during a period of startup, shutdown, or malfunction or during another period.(v) A summary of the total duration in hours of the deviation during the reporting period and the total duration as a percent of the total source operating time during that reporting period.(vi) A breakdown of the total duration in hours of the deviations during the reporting period into those that are due to startup, shutdown, control equipment problems, process problems, other known causes, and other unknown causes.(vii) A summary of the total duration in hours of continuous monitoring system downtime during the reporting period and the total duration of continuous monitoring system downtime as a percent of the total source operating time during the reporting period.(xii) A description of any changes in continuous monitoring systems, processes, or controls since the last reporting period.
Citations to §63.7341(c)(8)(xi)
-
(8) For each deviation from an emission limitation occurring at an affected source where you are using a continuous monitoring system (including COMS, CEMS, or CPMS) to comply with the emission limitation in this subpart, you must include the information in paragraphs (c)(4) and (8)(i) through (xii) of this section. This includes periods of startup, shutdown, and malfunction.(ii) The start date, start time, and duration in hours that each continuous monitoring system (including COMS, CEMS, or CPMS) was inoperative, except for zero (low-level) and high-level checks.(iii) The start date, start time, and duration in hours that each continuous monitoring system (including COMS, CEMS, or CPMS) was out-of-control, including the information in § 63.8(c)(8).(iv) The date and time that each deviation started and stopped, the duration in hours, and whether each deviation occurred during a period of startup, shutdown, or malfunction or during another period.(v) A summary of the total duration in hours of the deviation during the reporting period and the total duration as a percent of the total source operating time during that reporting period.(vi) A breakdown of the total duration in hours of the deviations during the reporting period into those that are due to startup, shutdown, control equipment problems, process problems, other known causes, and other unknown causes.(vii) A summary of the total duration in hours of continuous monitoring system downtime during the reporting period and the total duration of continuous monitoring system downtime as a percent of the total source operating time during the reporting period.(xii) A description of any changes in continuous monitoring systems, processes, or controls since the last reporting period.
Citations to §63.7341(c)(8)(xii)
-
(8) For each deviation from an emission limitation occurring at an affected source where you are using a continuous monitoring system (including COMS, CEMS, or CPMS) to comply with the emission limitation in this subpart, you must include the information in paragraphs (c)(4) and (8)(i) through (xii) of this section. This includes periods of startup, shutdown, and malfunction.(ii) The start date, start time, and duration in hours that each continuous monitoring system (including COMS, CEMS, or CPMS) was inoperative, except for zero (low-level) and high-level checks.(iii) The start date, start time, and duration in hours that each continuous monitoring system (including COMS, CEMS, or CPMS) was out-of-control, including the information in § 63.8(c)(8).(iv) The date and time that each deviation started and stopped, the duration in hours, and whether each deviation occurred during a period of startup, shutdown, or malfunction or during another period.(v) A summary of the total duration in hours of the deviation during the reporting period and the total duration as a percent of the total source operating time during that reporting period.(vi) A breakdown of the total duration in hours of the deviations during the reporting period into those that are due to startup, shutdown, control equipment problems, process problems, other known causes, and other unknown causes.(vii) A summary of the total duration in hours of continuous monitoring system downtime during the reporting period and the total duration of continuous monitoring system downtime as a percent of the total source operating time during the reporting period.(xii) A description of any changes in continuous monitoring systems, processes, or controls since the last reporting period.
Citations to §63.7341(c)(xii)
-
(8) For each deviation from an emission limitation occurring at an affected source where you are using a continuous monitoring system (including COMS, CEMS, or CPMS) to comply with the emission limitation in this subpart, you must include the information in paragraphs (c)(4) and (8)(i) through (xii) of this section. This includes periods of startup, shutdown, and malfunction.(ii) The start date, start time, and duration in hours that each continuous monitoring system (including COMS, CEMS, or CPMS) was inoperative, except for zero (low-level) and high-level checks.(iii) The start date, start time, and duration in hours that each continuous monitoring system (including COMS, CEMS, or CPMS) was out-of-control, including the information in § 63.8(c)(8).(iv) The date and time that each deviation started and stopped, the duration in hours, and whether each deviation occurred during a period of startup, shutdown, or malfunction or during another period.(v) A summary of the total duration in hours of the deviation during the reporting period and the total duration as a percent of the total source operating time during that reporting period.(vi) A breakdown of the total duration in hours of the deviations during the reporting period into those that are due to startup, shutdown, control equipment problems, process problems, other known causes, and other unknown causes.(vii) A summary of the total duration in hours of continuous monitoring system downtime during the reporting period and the total duration of continuous monitoring system downtime as a percent of the total source operating time during the reporting period.(xii) A description of any changes in continuous monitoring systems, processes, or controls since the last reporting period.