§63.7330. What are my monitoring requirements? — Inbound Citations
40 C.F.R. § 63.7330
Statutory Authority
Cited by 13 regulations in release Current.
Citations to 40 U.S.C. § 63.7330 as a whole
-
(b) For each CPMS required in § 63.7330, you must develop and make available for inspection upon request by the permitting authority a site-specific monitoring plan that addresses the requirements in paragraphs (b)(1) through (6) of this section.(1) Installation of the CPMS sampling probe or other interface at a measurement location relative to each affected process unit such that the measurement is representative of control of the exhaust emissions (e.g., on or downstream of the last control device);(2) Performance and equipment specifications for the sample interface, the parametric signal analyzer, and the data collection and reduction system;(3) Performance evaluation procedures and acceptance criteria (e.g., calibrations);(4) Ongoing operation and maintenance procedures in accordance with the general requirements of § 63.8(c)(1)(ii), (3), (4)(ii), (7), and (8);(5) Ongoing data quality assurance procedures in accordance with the general requirements of §§ 63.8(d)(1) and (2) and 63.7342(b)(3); and(6) Ongoing recordkeeping and reporting procedures in accordance the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (2)(i).
Citations to §63.7330(a)(1)
-
(a) For each baghouse applied to pushing emissions from a coke oven battery, you must at all times monitor the relative change in particulate matter loadings using a bag leak detection system according to the requirements in § 63.7331(a) and conduct inspections at their specified frequency according to the requirements in paragraphs (a)(1) through (8) of this section.(1) Monitor the pressure drop across each baghouse cell each day to ensure pressure drop is within the normal operating range identified in the manual;(2) Confirm that dust is being removed from hoppers through weekly visual inspections or equivalent means of ensuring the proper functioning of removal mechanisms;(3) Check the compressed air supply for pulse-jet baghouses each day;(4) Monitor cleaning cycles to ensure proper operation using an appropriate methodology;(5) Check bag cleaning mechanisms for proper functioning through monthly visual inspection or equivalent means;(6) Make monthly visual checks of bag tension on reverse air and shaker-type baghouses to ensure that bags are not kinked (kneed or bent) or laying on their sides. You do not have to make this check for shaker-type baghouses using self-tensioning (spring-loaded) devices;(7) Confirm the physical integrity of the baghouse through quarterly visual inspections of the baghouse interior for air leaks; and(8) Inspect fans for wear, material buildup, and corrosion through quarterly visual inspections, vibration detectors, or equivalent means.
Citations to §63.7330(a)(2)
-
(a) For each baghouse applied to pushing emissions from a coke oven battery, you must at all times monitor the relative change in particulate matter loadings using a bag leak detection system according to the requirements in § 63.7331(a) and conduct inspections at their specified frequency according to the requirements in paragraphs (a)(1) through (8) of this section.(1) Monitor the pressure drop across each baghouse cell each day to ensure pressure drop is within the normal operating range identified in the manual;(2) Confirm that dust is being removed from hoppers through weekly visual inspections or equivalent means of ensuring the proper functioning of removal mechanisms;(3) Check the compressed air supply for pulse-jet baghouses each day;(4) Monitor cleaning cycles to ensure proper operation using an appropriate methodology;(5) Check bag cleaning mechanisms for proper functioning through monthly visual inspection or equivalent means;(6) Make monthly visual checks of bag tension on reverse air and shaker-type baghouses to ensure that bags are not kinked (kneed or bent) or laying on their sides. You do not have to make this check for shaker-type baghouses using self-tensioning (spring-loaded) devices;(7) Confirm the physical integrity of the baghouse through quarterly visual inspections of the baghouse interior for air leaks; and(8) Inspect fans for wear, material buildup, and corrosion through quarterly visual inspections, vibration detectors, or equivalent means.
Citations to §63.7330(a)(3)
-
(a) For each baghouse applied to pushing emissions from a coke oven battery, you must at all times monitor the relative change in particulate matter loadings using a bag leak detection system according to the requirements in § 63.7331(a) and conduct inspections at their specified frequency according to the requirements in paragraphs (a)(1) through (8) of this section.(1) Monitor the pressure drop across each baghouse cell each day to ensure pressure drop is within the normal operating range identified in the manual;(2) Confirm that dust is being removed from hoppers through weekly visual inspections or equivalent means of ensuring the proper functioning of removal mechanisms;(3) Check the compressed air supply for pulse-jet baghouses each day;(4) Monitor cleaning cycles to ensure proper operation using an appropriate methodology;(5) Check bag cleaning mechanisms for proper functioning through monthly visual inspection or equivalent means;(6) Make monthly visual checks of bag tension on reverse air and shaker-type baghouses to ensure that bags are not kinked (kneed or bent) or laying on their sides. You do not have to make this check for shaker-type baghouses using self-tensioning (spring-loaded) devices;(7) Confirm the physical integrity of the baghouse through quarterly visual inspections of the baghouse interior for air leaks; and(8) Inspect fans for wear, material buildup, and corrosion through quarterly visual inspections, vibration detectors, or equivalent means.
Citations to §63.7330(a)(4)
-
(a) For each baghouse applied to pushing emissions from a coke oven battery, you must at all times monitor the relative change in particulate matter loadings using a bag leak detection system according to the requirements in § 63.7331(a) and conduct inspections at their specified frequency according to the requirements in paragraphs (a)(1) through (8) of this section.(1) Monitor the pressure drop across each baghouse cell each day to ensure pressure drop is within the normal operating range identified in the manual;(2) Confirm that dust is being removed from hoppers through weekly visual inspections or equivalent means of ensuring the proper functioning of removal mechanisms;(3) Check the compressed air supply for pulse-jet baghouses each day;(4) Monitor cleaning cycles to ensure proper operation using an appropriate methodology;(5) Check bag cleaning mechanisms for proper functioning through monthly visual inspection or equivalent means;(6) Make monthly visual checks of bag tension on reverse air and shaker-type baghouses to ensure that bags are not kinked (kneed or bent) or laying on their sides. You do not have to make this check for shaker-type baghouses using self-tensioning (spring-loaded) devices;(7) Confirm the physical integrity of the baghouse through quarterly visual inspections of the baghouse interior for air leaks; and(8) Inspect fans for wear, material buildup, and corrosion through quarterly visual inspections, vibration detectors, or equivalent means.
Citations to §63.7330(a)(5)
-
(a) For each baghouse applied to pushing emissions from a coke oven battery, you must at all times monitor the relative change in particulate matter loadings using a bag leak detection system according to the requirements in § 63.7331(a) and conduct inspections at their specified frequency according to the requirements in paragraphs (a)(1) through (8) of this section.(1) Monitor the pressure drop across each baghouse cell each day to ensure pressure drop is within the normal operating range identified in the manual;(2) Confirm that dust is being removed from hoppers through weekly visual inspections or equivalent means of ensuring the proper functioning of removal mechanisms;(3) Check the compressed air supply for pulse-jet baghouses each day;(4) Monitor cleaning cycles to ensure proper operation using an appropriate methodology;(5) Check bag cleaning mechanisms for proper functioning through monthly visual inspection or equivalent means;(6) Make monthly visual checks of bag tension on reverse air and shaker-type baghouses to ensure that bags are not kinked (kneed or bent) or laying on their sides. You do not have to make this check for shaker-type baghouses using self-tensioning (spring-loaded) devices;(7) Confirm the physical integrity of the baghouse through quarterly visual inspections of the baghouse interior for air leaks; and(8) Inspect fans for wear, material buildup, and corrosion through quarterly visual inspections, vibration detectors, or equivalent means.
Citations to §63.7330(a)(6)
-
(a) For each baghouse applied to pushing emissions from a coke oven battery, you must at all times monitor the relative change in particulate matter loadings using a bag leak detection system according to the requirements in § 63.7331(a) and conduct inspections at their specified frequency according to the requirements in paragraphs (a)(1) through (8) of this section.(1) Monitor the pressure drop across each baghouse cell each day to ensure pressure drop is within the normal operating range identified in the manual;(2) Confirm that dust is being removed from hoppers through weekly visual inspections or equivalent means of ensuring the proper functioning of removal mechanisms;(3) Check the compressed air supply for pulse-jet baghouses each day;(4) Monitor cleaning cycles to ensure proper operation using an appropriate methodology;(5) Check bag cleaning mechanisms for proper functioning through monthly visual inspection or equivalent means;(6) Make monthly visual checks of bag tension on reverse air and shaker-type baghouses to ensure that bags are not kinked (kneed or bent) or laying on their sides. You do not have to make this check for shaker-type baghouses using self-tensioning (spring-loaded) devices;(7) Confirm the physical integrity of the baghouse through quarterly visual inspections of the baghouse interior for air leaks; and(8) Inspect fans for wear, material buildup, and corrosion through quarterly visual inspections, vibration detectors, or equivalent means.
Citations to §63.7330(a)(7)
-
(a) For each baghouse applied to pushing emissions from a coke oven battery, you must at all times monitor the relative change in particulate matter loadings using a bag leak detection system according to the requirements in § 63.7331(a) and conduct inspections at their specified frequency according to the requirements in paragraphs (a)(1) through (8) of this section.(1) Monitor the pressure drop across each baghouse cell each day to ensure pressure drop is within the normal operating range identified in the manual;(2) Confirm that dust is being removed from hoppers through weekly visual inspections or equivalent means of ensuring the proper functioning of removal mechanisms;(3) Check the compressed air supply for pulse-jet baghouses each day;(4) Monitor cleaning cycles to ensure proper operation using an appropriate methodology;(5) Check bag cleaning mechanisms for proper functioning through monthly visual inspection or equivalent means;(6) Make monthly visual checks of bag tension on reverse air and shaker-type baghouses to ensure that bags are not kinked (kneed or bent) or laying on their sides. You do not have to make this check for shaker-type baghouses using self-tensioning (spring-loaded) devices;(7) Confirm the physical integrity of the baghouse through quarterly visual inspections of the baghouse interior for air leaks; and(8) Inspect fans for wear, material buildup, and corrosion through quarterly visual inspections, vibration detectors, or equivalent means.
Citations to §63.7330(a)(8)
-
(a) For each baghouse applied to pushing emissions from a coke oven battery, you must at all times monitor the relative change in particulate matter loadings using a bag leak detection system according to the requirements in § 63.7331(a) and conduct inspections at their specified frequency according to the requirements in paragraphs (a)(1) through (8) of this section.(1) Monitor the pressure drop across each baghouse cell each day to ensure pressure drop is within the normal operating range identified in the manual;(2) Confirm that dust is being removed from hoppers through weekly visual inspections or equivalent means of ensuring the proper functioning of removal mechanisms;(3) Check the compressed air supply for pulse-jet baghouses each day;(4) Monitor cleaning cycles to ensure proper operation using an appropriate methodology;(5) Check bag cleaning mechanisms for proper functioning through monthly visual inspection or equivalent means;(6) Make monthly visual checks of bag tension on reverse air and shaker-type baghouses to ensure that bags are not kinked (kneed or bent) or laying on their sides. You do not have to make this check for shaker-type baghouses using self-tensioning (spring-loaded) devices;(7) Confirm the physical integrity of the baghouse through quarterly visual inspections of the baghouse interior for air leaks; and(8) Inspect fans for wear, material buildup, and corrosion through quarterly visual inspections, vibration detectors, or equivalent means.
Citations to §63.7330(b)
-
(1) Using the continuous parameter monitoring systems (CPMS) required in § 63.7330(b), measure and record the pressure drop and scrubber water flow rate for each particulate matter test run during periods of pushing. A minimum of one pressure drop measurement and one scrubber water flow rate measurement must be obtained for each push.
Citations to §63.7330(c)
-
(1) Using the CPMS required in § 63.7330(c), measure and record the hot water pressure and temperature for each particulate matter test run during periods of pushing. A minimum of one pressure measurement and one temperature measurement must be made just prior to each push by monitoring the hot water holding tank on the mobile scrubber car.
Citations to §63.7330(e)
-
(1) Using the continuous opacity monitoring system (COMS) required in § 63.7330(e), measure and record the opacity of emissions from each battery stack for a 24-hour period.
Citations to §63.7330(f)
-
(1) Using the CPMS required in § 63.7330(f), measure and record the pressure drop for each particulate matter test run during periods of pushing. A minimum of one pressure drop measurement must be obtained for each push.