§63.43. Maximum achievable control technology (MACT) determinations for constructed and reconstructed major sources. — Inbound Citations
40 C.F.R. § 63.43
Statutory Authority
Cited by 17 regulations in release Current.
Citations to 40 C.F.R. § 63.43 as a whole
-
(4) If you propose to construct or reconstruct a major source of HAPs such that you are subject to a case-by-case MACT determination under section 112(g)(2) of the Act, you may elect to have this determination approved under the provisions of this program (other options for such determinations include a title V permit action or a Notice of MACT Approval under § 63.43 of this chapter). If you elect this option, you still must comply with the requirements of § 63.43 of this chapter that apply to all case-by-case MACT determinations.
-
(a) The requirements of §§ 63.40 through 63.44 of this subpart carry out section 112(g)(2)(B) of the 1990 Amendments.
-
(a) Each permitting authority shall review its existing programs, procedures, and criteria for preconstruction review for conformity to the requirements established by §§ 63.40 through 63.44, shall make any additions and revisions to its existing programs, procedures, and criteria that the permitting authority deems necessary to properly effectuate §§ 63.40 through 63.44, and shall adopt a program to implement section 112(g) with respect to construction or reconstruction of major sources of HAP. As part of the adoption by the permitting authority of a program to implement section 112(g) with respect to construction or reconstruction of major sources of HAP, the chief executive officer of the permitting authority shall certify that the program satisfies all applicable requirements established by §§ 63.40 through 63.44, and shall specify an effective date for that program which is not later than June 29, 1998. Prior to the specified effective date, the permitting authority shall publish a notice stating that the permitting authority has adopted a program to implement section 112(g) with respect to construction or reconstruction of major sources of HAP and stating the effective date, and shall provide a written description of the program to the Administrator through the appropriate EPA Regional Office. Nothing in this section shall be construed either:(1) To require that any owner or operator of a stationary source comply with any requirement adopted by the permitting authority which is not intended to implement section 112(g) with respect to construction or reconstruction of major sources of HAP; or(2) To preclude the permitting authority from enforcing any requirements not intended to implement section 112(g) with respect to construction or reconstruction of major sources of HAP under any other provision of applicable law.
-
(a) If the Administrator promulgates an emission standard under section 112(d) or section 112(h) of the Act or the permitting authority issues a determination under section 112(j) of the Act that is applicable to a stationary source or group of sources which would be deemed to be a constructed or reconstructed major source under this subpart before the date that the owner or operator has obtained a final and legally effective MACT determination under any of the review options available pursuant to § 63.43, the owner or operator of the source(s) shall comply with the promulgated standard or determination rather than any MACT determination under section 112(g) by the permitting authority, and the owner or operator shall comply with the promulgated standard by the compliance date in the promulgated standard.
Citations to §63.43(e)(2)(i)
-
(i) The information described in paragraphs (e)(2)(i) through (e)(2)(x) of this section; and
Citations to §63.43(e)(2)(ii)
-
(i) The information described in paragraphs (e)(2)(i) through (e)(2)(x) of this section; and
Citations to §63.43(e)(2)(iii)
-
(i) The information described in paragraphs (e)(2)(i) through (e)(2)(x) of this section; and
Citations to §63.43(e)(2)(iv)
-
(i) The information described in paragraphs (e)(2)(i) through (e)(2)(x) of this section; and
Citations to §63.43(e)(2)(ix)
-
(i) The information described in paragraphs (e)(2)(i) through (e)(2)(x) of this section; and
Citations to §63.43(e)(2)(v)
-
(i) The information described in paragraphs (e)(2)(i) through (e)(2)(x) of this section; and
Citations to §63.43(e)(2)(vi)
-
(i) The information described in paragraphs (e)(2)(i) through (e)(2)(x) of this section; and
Citations to §63.43(e)(2)(vii)
-
(i) The information described in paragraphs (e)(2)(i) through (e)(2)(x) of this section; and
Citations to §63.43(e)(2)(viii)
-
(i) The information described in paragraphs (e)(2)(i) through (e)(2)(x) of this section; and
Citations to §63.43(e)(2)(x)
-
(i) The information described in paragraphs (e)(2)(i) through (e)(2)(x) of this section; and
Citations to §63.43(f)
-
(i) Apply for and obtain a Notice of MACT Approval according to the procedures outlined in paragraphs (f) through (h) of this section; or
Citations to §63.43(g)
-
(i) Apply for and obtain a Notice of MACT Approval according to the procedures outlined in paragraphs (f) through (h) of this section; or
Citations to §63.43(h)
-
(i) Apply for and obtain a Notice of MACT Approval according to the procedures outlined in paragraphs (f) through (h) of this section; or