  • (2) On or after May 8, 2027, any gasoline facility which receives gasoline by pipeline, ship, barge, or cargo tank and subsequently loads all or a portion of the gasoline into gasoline cargo tanks for transport to bulk gasoline plants or gasoline dispensing facilities and has a gasoline throughput greater than 20,000 gallons per day (75,700 liters per day). Gasoline throughput shall be the maximum calculated design throughput for the facility as may be limited by compliance with an enforceable condition under Federal, State, or local law and discoverable by the Administrator and any other person.
    Controlled loading rack, for the purposes of § 63.420, means a loading rack equipped with vapor collection and processing systems that reduce displaced vapor emissions to no more than 80 milligrams of total organic compounds per liter of gasoline loaded, as measured using the test methods and procedures in § 60.503 (a) through (c) of this chapter.
    Equipment means each valve, pump, pressure relief device, sampling connection system, open-ended valve or line, and flange or other connector in the gasoline liquid transfer and vapor collection systems. This definition also includes the entire vapor processing system except the exhaust port(s) or stack(s).
    Flare means a thermal combustion device using an open or shrouded flame (without full enclosure) such that the pollutants are not emitted through a conveyance suitable to conduct a performance test.
    Gasoline means any petroleum distillate or petroleum distillate/alcohol blend having a Reid vapor pressure of 4.0 pounds per square inch (27.6 kilopascals) or greater, which is used as a fuel for internal combustion engines.
    Gasoline cargo tank means a delivery tank truck or railcar which is loading gasoline or which has loaded gasoline on the immediately previous load.
    In gasoline service means that a piece of equipment is used in a system that transfers gasoline or gasoline vapors.
    Limitation(s) on potential to emit means limitation(s) limiting a source's potential to emit as defined in § 63.2 of subpart A of this part.
    Operating parameter value means a value for an operating or emission parameter of the vapor processing system (e.g., temperature) which, if maintained continuously by itself or in combination with one or more other operating parameter values, determines that an owner or operator has complied with the applicable emission standard. The operating parameter value is determined using the procedures outlined in § 63.425(b).
    Oxygenated gasoline means the same as defined in 40 CFR 80.2.
    Pipeline breakout station means:
  • (1) The owner or operator shall design and operate the vapor processing system, vapor collection system, and liquid loading equipment to prevent gauge pressure in the railcar gasoline cargo tank from exceeding the applicable test limits in § 63.425(e) and (i) during product loading. This level is not to be exceeded when measured by the procedures specified in § 60.503(d) of this chapter during any performance test or performance evaluation conducted under § 63.425(b) or (c).
  • (b) Each owner or operator of a bulk gasoline terminal subject to the provisions in § 63.422(b)(1) shall operate the vapor processing system in a manner not to exceed the operating parameter value for the parameter described in paragraphs (a)(1) and (2) of this section, or to go below the operating parameter value for the parameter described in paragraph (a)(3) of this section, and established using the procedures in § 63.425(b). In cases where an alternative parameter pursuant to paragraph (a)(5) of this section is approved, each owner or operator shall operate the vapor processing system in a manner not to exceed or not to go below, as appropriate, the alternative operating parameter value. Operation of the vapor processing system in a manner exceeding or going below the operating parameter value, as specified above, shall constitute a violation of the emission standard in § 63.422(b)(1).
  • (i) All data and calculations, engineering assessments, and manufacturer's recommendations used in determining the operating parameter value under § 63.425(b); and
  • (a) Except as provided in paragraphs (b) through (d) of this section, each owner or operator of a Group 1 gasoline loading rack classified under Standard Industrial Classification code 2911 located within a contiguous area and under common control with a petroleum refinery shall comply with subpart R of this part, §§ 63.421, 63.422(a) through (c) and (e), 63.425(a) through (c) and (e) through (i), 63.427(a) and (b), and 63.428(b), (c), (g)(1), (h)(1) through (3), and (k).

Citations to §63.425(b)(3)

  • (i) Each exceedance or failure to maintain, as appropriate, the monitored operating parameter value determined under § 63.425(b)(3). The report shall include the monitoring data for the days on which exceedances or failures to maintain have occurred, and a description and timing of the steps taken to repair or perform maintenance on the vapor collection and processing systems or the CMS.

Citations to §63.425(c)

Citations to §63.425(c)(2)(i)

  • (2) The first performance test or performance evaluation of the continuous emissions monitoring system (CEMS) shall be conducted within 180 days of the date affected source begins compliance with the requirements in § 63.422(b)(2). A previously conducted performance test may be used to satisfy this requirement if the conditions in paragraphs (c)(2)(i) through (v) of this section are met. Prior to conducting this performance test or evaluation, you must continue to meet the monitoring and operating limits that apply based on the previously conducted performance test.
    (iii) The operating conditions, test methods, and test requirements (e.g., length of test) used for the previous performance test conform to the requirements in paragraph (c)(1) of this section.
    (iv) The temperature in the combustion zone was recorded during the performance test as specified in § 60.503a(c)(8)(i) of this chapter and can be used to establish the operating limit as specified in § 60.503a(c)(8)(ii) through (iv) of this chapter.
    (v) The performance test demonstrates compliance with the emission limit specified in § 63.422(b)(2).

Citations to §63.425(c)(2)(ii)

  • (2) The first performance test or performance evaluation of the continuous emissions monitoring system (CEMS) shall be conducted within 180 days of the date affected source begins compliance with the requirements in § 63.422(b)(2). A previously conducted performance test may be used to satisfy this requirement if the conditions in paragraphs (c)(2)(i) through (v) of this section are met. Prior to conducting this performance test or evaluation, you must continue to meet the monitoring and operating limits that apply based on the previously conducted performance test.
    (iii) The operating conditions, test methods, and test requirements (e.g., length of test) used for the previous performance test conform to the requirements in paragraph (c)(1) of this section.
    (iv) The temperature in the combustion zone was recorded during the performance test as specified in § 60.503a(c)(8)(i) of this chapter and can be used to establish the operating limit as specified in § 60.503a(c)(8)(ii) through (iv) of this chapter.
    (v) The performance test demonstrates compliance with the emission limit specified in § 63.422(b)(2).

Citations to §63.425(c)(2)(iii)

  • (2) The first performance test or performance evaluation of the continuous emissions monitoring system (CEMS) shall be conducted within 180 days of the date affected source begins compliance with the requirements in § 63.422(b)(2). A previously conducted performance test may be used to satisfy this requirement if the conditions in paragraphs (c)(2)(i) through (v) of this section are met. Prior to conducting this performance test or evaluation, you must continue to meet the monitoring and operating limits that apply based on the previously conducted performance test.
    (iii) The operating conditions, test methods, and test requirements (e.g., length of test) used for the previous performance test conform to the requirements in paragraph (c)(1) of this section.
    (iv) The temperature in the combustion zone was recorded during the performance test as specified in § 60.503a(c)(8)(i) of this chapter and can be used to establish the operating limit as specified in § 60.503a(c)(8)(ii) through (iv) of this chapter.
    (v) The performance test demonstrates compliance with the emission limit specified in § 63.422(b)(2).

Citations to §63.425(c)(2)(iv)

  • (2) The first performance test or performance evaluation of the continuous emissions monitoring system (CEMS) shall be conducted within 180 days of the date affected source begins compliance with the requirements in § 63.422(b)(2). A previously conducted performance test may be used to satisfy this requirement if the conditions in paragraphs (c)(2)(i) through (v) of this section are met. Prior to conducting this performance test or evaluation, you must continue to meet the monitoring and operating limits that apply based on the previously conducted performance test.
    (iii) The operating conditions, test methods, and test requirements (e.g., length of test) used for the previous performance test conform to the requirements in paragraph (c)(1) of this section.
    (iv) The temperature in the combustion zone was recorded during the performance test as specified in § 60.503a(c)(8)(i) of this chapter and can be used to establish the operating limit as specified in § 60.503a(c)(8)(ii) through (iv) of this chapter.
    (v) The performance test demonstrates compliance with the emission limit specified in § 63.422(b)(2).

Citations to §63.425(c)(2)(v)

  • (2) The first performance test or performance evaluation of the continuous emissions monitoring system (CEMS) shall be conducted within 180 days of the date affected source begins compliance with the requirements in § 63.422(b)(2). A previously conducted performance test may be used to satisfy this requirement if the conditions in paragraphs (c)(2)(i) through (v) of this section are met. Prior to conducting this performance test or evaluation, you must continue to meet the monitoring and operating limits that apply based on the previously conducted performance test.
    (iii) The operating conditions, test methods, and test requirements (e.g., length of test) used for the previous performance test conform to the requirements in paragraph (c)(1) of this section.
    (iv) The temperature in the combustion zone was recorded during the performance test as specified in § 60.503a(c)(8)(i) of this chapter and can be used to establish the operating limit as specified in § 60.503a(c)(8)(ii) through (iv) of this chapter.
    (v) The performance test demonstrates compliance with the emission limit specified in § 63.422(b)(2).

Citations to §63.425(c)(v)

  • (2) The first performance test or performance evaluation of the continuous emissions monitoring system (CEMS) shall be conducted within 180 days of the date affected source begins compliance with the requirements in § 63.422(b)(2). A previously conducted performance test may be used to satisfy this requirement if the conditions in paragraphs (c)(2)(i) through (v) of this section are met. Prior to conducting this performance test or evaluation, you must continue to meet the monitoring and operating limits that apply based on the previously conducted performance test.
    (iii) The operating conditions, test methods, and test requirements (e.g., length of test) used for the previous performance test conform to the requirements in paragraph (c)(1) of this section.
    (iv) The temperature in the combustion zone was recorded during the performance test as specified in § 60.503a(c)(8)(i) of this chapter and can be used to establish the operating limit as specified in § 60.503a(c)(8)(ii) through (iv) of this chapter.
    (v) The performance test demonstrates compliance with the emission limit specified in § 63.422(b)(2).

Citations to §63.425(d)

Citations to §63.425(e)

  • (ii) No later than the dates specified in § 63.11083, the maximum allowable pressure and vacuum changes (Δ p, Δ v) for all affected gasoline cargo tanks is provided in column 3 of table 2 in § 63.425(e). The requirements in paragraph (g)(1)(i) of this section do not apply when demonstrating compliance with this paragraph (g)(1)(ii).
  • (2) On or after May 8, 2027, any gasoline facility which receives gasoline by pipeline, ship, barge, or cargo tank and subsequently loads all or a portion of the gasoline into gasoline cargo tanks for transport to bulk gasoline plants or gasoline dispensing facilities and has a gasoline throughput greater than 20,000 gallons per day (75,700 liters per day). Gasoline throughput shall be the maximum calculated design throughput for the facility as may be limited by compliance with an enforceable condition under Federal, State, or local law and discoverable by the Administrator and any other person.
    Controlled loading rack, for the purposes of § 63.420, means a loading rack equipped with vapor collection and processing systems that reduce displaced vapor emissions to no more than 80 milligrams of total organic compounds per liter of gasoline loaded, as measured using the test methods and procedures in § 60.503 (a) through (c) of this chapter.
    Equipment means each valve, pump, pressure relief device, sampling connection system, open-ended valve or line, and flange or other connector in the gasoline liquid transfer and vapor collection systems. This definition also includes the entire vapor processing system except the exhaust port(s) or stack(s).
    Flare means a thermal combustion device using an open or shrouded flame (without full enclosure) such that the pollutants are not emitted through a conveyance suitable to conduct a performance test.
    Gasoline means any petroleum distillate or petroleum distillate/alcohol blend having a Reid vapor pressure of 4.0 pounds per square inch (27.6 kilopascals) or greater, which is used as a fuel for internal combustion engines.
    Gasoline cargo tank means a delivery tank truck or railcar which is loading gasoline or which has loaded gasoline on the immediately previous load.
    In gasoline service means that a piece of equipment is used in a system that transfers gasoline or gasoline vapors.
    Limitation(s) on potential to emit means limitation(s) limiting a source's potential to emit as defined in § 63.2 of subpart A of this part.
    Operating parameter value means a value for an operating or emission parameter of the vapor processing system (e.g., temperature) which, if maintained continuously by itself or in combination with one or more other operating parameter values, determines that an owner or operator has complied with the applicable emission standard. The operating parameter value is determined using the procedures outlined in § 63.425(b).
    Oxygenated gasoline means the same as defined in 40 CFR 80.2.
    Pipeline breakout station means:
  • (1) The tank truck or railcar gasoline cargo tank has been repaired, retested, and subsequently passed either the annual certification test described in § 63.425(e) or the railcar bubble test described in § 63.425(i); or
  • (1) Annual certification testing performed under § 63.425(e) and railcar bubble leak testing performed under § 63.425(i); and
  • (a) Except as provided in paragraphs (b) through (d) of this section, each owner or operator of a Group 1 gasoline loading rack classified under Standard Industrial Classification code 2911 located within a contiguous area and under common control with a petroleum refinery shall comply with subpart R of this part, §§ 63.421, 63.422(a) through (c) and (e), 63.425(a) through (c) and (e) through (i), 63.427(a) and (b), and 63.428(b), (c), (g)(1), (h)(1) through (3), and (k).
  • (c) A cargo tank used to transport a petroleum distillate fuel that is equipped with vapor recovery equipment may be leakage tested in accordance with 40 CFR 63.425(e). To satisfy the leakage test requirements of this paragraph, the test specified in 40 CFR 63.425(e)(1) must be conducted using air. The hydrostatic test alternative permitted under Appendix A to 40 CFR Part 60 (“Method 27—Determination of Vapor Tightness of Gasoline Delivery Tank Using Pressure-Vacuum Test”) may not be used to satisfy the leakage test requirements of this paragraph. A cargo tank tested in accordance with 40 CFR 63.425(e) may be marked as specified in § 180.415 of this subchapter.
  • (2) Cargo tanks used to transport petroleum distillate fuels that are equipped with vapor collection equipment may be leak tested in accordance with the Environmental Protection Agency's “Method 27—Determination of Vapor Tightness of Gasoline Delivery Tank Using Pressure-Vacuum Test,” as set forth in Appendix A to 40 CFR part 60. Test methods and procedures and maximum allowable pressure and vacuum changes are in 40 CFR 63.425(e). The hydrostatic test alternative, using liquid in Environmental Protection Agency's “Method 27—Determination of Vapor Tightness of Gasoline Delivery Tank Using Pressure-Vacuum Test,” may not be used to satisfy the leak testing requirements of this paragraph. The test must be conducted using air.

Citations to §63.425(e)(1)

Citations to §63.425(e)(2)

Citations to §63.425(f)

  • (2) On or after May 8, 2027, any gasoline facility which receives gasoline by pipeline, ship, barge, or cargo tank and subsequently loads all or a portion of the gasoline into gasoline cargo tanks for transport to bulk gasoline plants or gasoline dispensing facilities and has a gasoline throughput greater than 20,000 gallons per day (75,700 liters per day). Gasoline throughput shall be the maximum calculated design throughput for the facility as may be limited by compliance with an enforceable condition under Federal, State, or local law and discoverable by the Administrator and any other person.
    Controlled loading rack, for the purposes of § 63.420, means a loading rack equipped with vapor collection and processing systems that reduce displaced vapor emissions to no more than 80 milligrams of total organic compounds per liter of gasoline loaded, as measured using the test methods and procedures in § 60.503 (a) through (c) of this chapter.
    Equipment means each valve, pump, pressure relief device, sampling connection system, open-ended valve or line, and flange or other connector in the gasoline liquid transfer and vapor collection systems. This definition also includes the entire vapor processing system except the exhaust port(s) or stack(s).
    Flare means a thermal combustion device using an open or shrouded flame (without full enclosure) such that the pollutants are not emitted through a conveyance suitable to conduct a performance test.
    Gasoline means any petroleum distillate or petroleum distillate/alcohol blend having a Reid vapor pressure of 4.0 pounds per square inch (27.6 kilopascals) or greater, which is used as a fuel for internal combustion engines.
    Gasoline cargo tank means a delivery tank truck or railcar which is loading gasoline or which has loaded gasoline on the immediately previous load.
    In gasoline service means that a piece of equipment is used in a system that transfers gasoline or gasoline vapors.
    Limitation(s) on potential to emit means limitation(s) limiting a source's potential to emit as defined in § 63.2 of subpart A of this part.
    Operating parameter value means a value for an operating or emission parameter of the vapor processing system (e.g., temperature) which, if maintained continuously by itself or in combination with one or more other operating parameter values, determines that an owner or operator has complied with the applicable emission standard. The operating parameter value is determined using the procedures outlined in § 63.425(b).
    Oxygenated gasoline means the same as defined in 40 CFR 80.2.
    Pipeline breakout station means:
  • (c) Each owner or operator of a bulk gasoline terminal subject to the provisions of this subpart shall discontinue loading any cargo tank that fails vapor tightness according to the test requirements in § 63.425(f), (g), and (h) until vapor tightness documentation for that gasoline cargo tank is obtained which documents that:
    (1) The tank truck or railcar gasoline cargo tank has been repaired, retested, and subsequently passed either the annual certification test described in § 63.425(e) or the railcar bubble test described in § 63.425(i); or
    (2) For each gasoline cargo tank failing the test in § 63.425(f) at the facility, the cargo tank meets the test requirements in either § 63.425(g) or (h); or
    (3) For each gasoline cargo tank failing the test in § 63.425(g) at the facility, the cargo tank meets the test requirements in § 63.425(h).
  • (2) Continuous performance testing performed at any time at that facility under § 63.425(f), (g), and (h).
  • (a) Except as provided in paragraphs (b) through (d) of this section, each owner or operator of a Group 1 gasoline loading rack classified under Standard Industrial Classification code 2911 located within a contiguous area and under common control with a petroleum refinery shall comply with subpart R of this part, §§ 63.421, 63.422(a) through (c) and (e), 63.425(a) through (c) and (e) through (i), 63.427(a) and (b), and 63.428(b), (c), (g)(1), (h)(1) through (3), and (k).

Citations to §63.425(g)

  • (2) On or after May 8, 2027, any gasoline facility which receives gasoline by pipeline, ship, barge, or cargo tank and subsequently loads all or a portion of the gasoline into gasoline cargo tanks for transport to bulk gasoline plants or gasoline dispensing facilities and has a gasoline throughput greater than 20,000 gallons per day (75,700 liters per day). Gasoline throughput shall be the maximum calculated design throughput for the facility as may be limited by compliance with an enforceable condition under Federal, State, or local law and discoverable by the Administrator and any other person.
    Controlled loading rack, for the purposes of § 63.420, means a loading rack equipped with vapor collection and processing systems that reduce displaced vapor emissions to no more than 80 milligrams of total organic compounds per liter of gasoline loaded, as measured using the test methods and procedures in § 60.503 (a) through (c) of this chapter.
    Equipment means each valve, pump, pressure relief device, sampling connection system, open-ended valve or line, and flange or other connector in the gasoline liquid transfer and vapor collection systems. This definition also includes the entire vapor processing system except the exhaust port(s) or stack(s).
    Flare means a thermal combustion device using an open or shrouded flame (without full enclosure) such that the pollutants are not emitted through a conveyance suitable to conduct a performance test.
    Gasoline means any petroleum distillate or petroleum distillate/alcohol blend having a Reid vapor pressure of 4.0 pounds per square inch (27.6 kilopascals) or greater, which is used as a fuel for internal combustion engines.
    Gasoline cargo tank means a delivery tank truck or railcar which is loading gasoline or which has loaded gasoline on the immediately previous load.
    In gasoline service means that a piece of equipment is used in a system that transfers gasoline or gasoline vapors.
    Limitation(s) on potential to emit means limitation(s) limiting a source's potential to emit as defined in § 63.2 of subpart A of this part.
    Operating parameter value means a value for an operating or emission parameter of the vapor processing system (e.g., temperature) which, if maintained continuously by itself or in combination with one or more other operating parameter values, determines that an owner or operator has complied with the applicable emission standard. The operating parameter value is determined using the procedures outlined in § 63.425(b).
    Oxygenated gasoline means the same as defined in 40 CFR 80.2.
    Pipeline breakout station means:
  • (c) Each owner or operator of a bulk gasoline terminal subject to the provisions of this subpart shall discontinue loading any cargo tank that fails vapor tightness according to the test requirements in § 63.425(f), (g), and (h) until vapor tightness documentation for that gasoline cargo tank is obtained which documents that:
    (1) The tank truck or railcar gasoline cargo tank has been repaired, retested, and subsequently passed either the annual certification test described in § 63.425(e) or the railcar bubble test described in § 63.425(i); or
    (2) For each gasoline cargo tank failing the test in § 63.425(f) at the facility, the cargo tank meets the test requirements in either § 63.425(g) or (h); or
    (3) For each gasoline cargo tank failing the test in § 63.425(g) at the facility, the cargo tank meets the test requirements in § 63.425(h).
  • (2) Continuous performance testing performed at any time at that facility under § 63.425(f), (g), and (h).
  • (a) Except as provided in paragraphs (b) through (d) of this section, each owner or operator of a Group 1 gasoline loading rack classified under Standard Industrial Classification code 2911 located within a contiguous area and under common control with a petroleum refinery shall comply with subpart R of this part, §§ 63.421, 63.422(a) through (c) and (e), 63.425(a) through (c) and (e) through (i), 63.427(a) and (b), and 63.428(b), (c), (g)(1), (h)(1) through (3), and (k).

Citations to §63.425(h)

  • (2) On or after May 8, 2027, any gasoline facility which receives gasoline by pipeline, ship, barge, or cargo tank and subsequently loads all or a portion of the gasoline into gasoline cargo tanks for transport to bulk gasoline plants or gasoline dispensing facilities and has a gasoline throughput greater than 20,000 gallons per day (75,700 liters per day). Gasoline throughput shall be the maximum calculated design throughput for the facility as may be limited by compliance with an enforceable condition under Federal, State, or local law and discoverable by the Administrator and any other person.
    Controlled loading rack, for the purposes of § 63.420, means a loading rack equipped with vapor collection and processing systems that reduce displaced vapor emissions to no more than 80 milligrams of total organic compounds per liter of gasoline loaded, as measured using the test methods and procedures in § 60.503 (a) through (c) of this chapter.
    Equipment means each valve, pump, pressure relief device, sampling connection system, open-ended valve or line, and flange or other connector in the gasoline liquid transfer and vapor collection systems. This definition also includes the entire vapor processing system except the exhaust port(s) or stack(s).
    Flare means a thermal combustion device using an open or shrouded flame (without full enclosure) such that the pollutants are not emitted through a conveyance suitable to conduct a performance test.
    Gasoline means any petroleum distillate or petroleum distillate/alcohol blend having a Reid vapor pressure of 4.0 pounds per square inch (27.6 kilopascals) or greater, which is used as a fuel for internal combustion engines.
    Gasoline cargo tank means a delivery tank truck or railcar which is loading gasoline or which has loaded gasoline on the immediately previous load.
    In gasoline service means that a piece of equipment is used in a system that transfers gasoline or gasoline vapors.
    Limitation(s) on potential to emit means limitation(s) limiting a source's potential to emit as defined in § 63.2 of subpart A of this part.
    Operating parameter value means a value for an operating or emission parameter of the vapor processing system (e.g., temperature) which, if maintained continuously by itself or in combination with one or more other operating parameter values, determines that an owner or operator has complied with the applicable emission standard. The operating parameter value is determined using the procedures outlined in § 63.425(b).
    Oxygenated gasoline means the same as defined in 40 CFR 80.2.
    Pipeline breakout station means:
  • (c) Each owner or operator of a bulk gasoline terminal subject to the provisions of this subpart shall discontinue loading any cargo tank that fails vapor tightness according to the test requirements in § 63.425(f), (g), and (h) until vapor tightness documentation for that gasoline cargo tank is obtained which documents that:
    (1) The tank truck or railcar gasoline cargo tank has been repaired, retested, and subsequently passed either the annual certification test described in § 63.425(e) or the railcar bubble test described in § 63.425(i); or
    (2) For each gasoline cargo tank failing the test in § 63.425(f) at the facility, the cargo tank meets the test requirements in either § 63.425(g) or (h); or
    (3) For each gasoline cargo tank failing the test in § 63.425(g) at the facility, the cargo tank meets the test requirements in § 63.425(h).
  • (2) Continuous performance testing performed at any time at that facility under § 63.425(f), (g), and (h).
  • (a) Except as provided in paragraphs (b) through (d) of this section, each owner or operator of a Group 1 gasoline loading rack classified under Standard Industrial Classification code 2911 located within a contiguous area and under common control with a petroleum refinery shall comply with subpart R of this part, §§ 63.421, 63.422(a) through (c) and (e), 63.425(a) through (c) and (e) through (i), 63.427(a) and (b), and 63.428(b), (c), (g)(1), (h)(1) through (3), and (k).

Citations to §63.425(i)

Citations to §63.425(j)

Citations to §63.425(j)(1)

  • (j) Compliance with the vapor concentration below the LEL level for internal floating roof storage vessels at § 63.423(b)(2) shall be determined based on the procedures specified in paragraphs (j)(1) through (5) of this section. If tubing is necessary to obtain the measurements, the tubing must be non-crimping and made of Teflon or other inert material.
    (1) LEL monitoring must be conducted at least once every 12 months and at other times upon request by the Administrator. If the measurement cannot be performed due to wind speeds exceeding those specified in paragraph (j)(3)(iii) of this section, the measurement must be performed within 30 days of the previous attempt.
    (2) The calibration of the LEL meter must be checked per manufacturer specifications immediately before and after the measurements as specified in paragraphs (j)(2)(i) and (ii) of this section. If tubing will be used for the measurements, the tubing must be attached during calibration so that the calibration gas travels through the entire measurement system.
    (i) The calibration gas must contain a single hydrocarbon at a concentration corresponding to 50 percent of the LEL (e.g., 2.50 percent by volume when using methane as the calibration gas). The vendor must provide a Certificate of Analysis for the gas, and the certified concentration must be within ±2 percent (e.g., 2.45 percent—2.55 percent by volume when using methane as the calibration gas). The LEL span response must be between 49 percent and 51 percent. If the span check prior to the measurements does not meet this requirement, the LEL meter must be recalibrated or replaced. If the span check after the measurements does not meet this requirement, the LEL meter must be recalibrated or replaced, and the measurements must be repeated.
    (ii) Check the instrumental offset response using a certified compressed gas cylinder of zero air or an ambient environment that is free of organic compounds. The pre-measurement instrumental offset response must be 0 percent LEL. If the LEL meter does not meet this requirement, the LEL meter must be recalibrated or replaced.
    (i) Measurements of the vapors within the internal floating roof storage vessel must be collected no more than 3 feet above the internal floating roof.
    (ii) Measurements shall be taken for a minimum of 20 minutes, logging the measurements at least once every 15 seconds, or until one 5-minute average as determined according to paragraph (j)(5)(ii) of this section exceeds the level specified in § 63.423(b)(2).
    (iii) Measurements shall be taken when the wind speed at the top of the tank is 5 mph or less to the extent practicable, but in no case shall measurements be taken when the sustained wind speed at top of tank is greater than the annual average wind speed at the site or 15 mph, whichever is less.
    (iv) Measurements should be conducted when the internal floating roof is floating with limited product movement (limited filling or emptying of the tank).
    (4) To determine the actual vapor concentration within the storage vessel, the percent of the LEL “as the calibration gas” must be corrected according to one of the following procedures. Alternatively, if the LEL meter used has correction factors that can be selected from the meter's program, you may enable this feature to automatically apply one of the correction factors specified in paragraphs (j)(4)(i) and (ii) of this section.
    (i) Multiply the measurement by the published gasoline vapor correction factor for the specific LEL meter and calibration gas used.
    (ii) If there is no published correction factor for gasoline vapors for the specific LEL meter used, multiply the measurement by the published correction factor for butane as a surrogate for determining the LEL of gasoline vapors. The correction factor must correspond to the calibration gas used.
    (5) Use the calculation procedures in paragraphs (j)(5)(i) through (iii) of this section to determine compliance with the LEL level.
    (i) For each minute while measurements are being taken, determine the one-minute average reading as the arithmetic average of the corrected individual measurements (taken at least once every 15 seconds) during the minute.
    (ii) Starting with the end of the fifth minute of data, calculate a five-minute rolling average as the arithmetic average of the previous five one-minute readings determined under paragraph (j)(5)(i) of this section. Determine a new five-minute average reading for every subsequent one-minute reading.
    (iii) Each five-minute rolling average must meet the LEL level specified in § 63.423(b)(2).

Citations to §63.425(j)(2)

  • (j) Compliance with the vapor concentration below the LEL level for internal floating roof storage vessels at § 63.423(b)(2) shall be determined based on the procedures specified in paragraphs (j)(1) through (5) of this section. If tubing is necessary to obtain the measurements, the tubing must be non-crimping and made of Teflon or other inert material.
    (1) LEL monitoring must be conducted at least once every 12 months and at other times upon request by the Administrator. If the measurement cannot be performed due to wind speeds exceeding those specified in paragraph (j)(3)(iii) of this section, the measurement must be performed within 30 days of the previous attempt.
    (2) The calibration of the LEL meter must be checked per manufacturer specifications immediately before and after the measurements as specified in paragraphs (j)(2)(i) and (ii) of this section. If tubing will be used for the measurements, the tubing must be attached during calibration so that the calibration gas travels through the entire measurement system.
    (i) The calibration gas must contain a single hydrocarbon at a concentration corresponding to 50 percent of the LEL (e.g., 2.50 percent by volume when using methane as the calibration gas). The vendor must provide a Certificate of Analysis for the gas, and the certified concentration must be within ±2 percent (e.g., 2.45 percent—2.55 percent by volume when using methane as the calibration gas). The LEL span response must be between 49 percent and 51 percent. If the span check prior to the measurements does not meet this requirement, the LEL meter must be recalibrated or replaced. If the span check after the measurements does not meet this requirement, the LEL meter must be recalibrated or replaced, and the measurements must be repeated.
    (ii) Check the instrumental offset response using a certified compressed gas cylinder of zero air or an ambient environment that is free of organic compounds. The pre-measurement instrumental offset response must be 0 percent LEL. If the LEL meter does not meet this requirement, the LEL meter must be recalibrated or replaced.
    (i) Measurements of the vapors within the internal floating roof storage vessel must be collected no more than 3 feet above the internal floating roof.
    (ii) Measurements shall be taken for a minimum of 20 minutes, logging the measurements at least once every 15 seconds, or until one 5-minute average as determined according to paragraph (j)(5)(ii) of this section exceeds the level specified in § 63.423(b)(2).
    (iii) Measurements shall be taken when the wind speed at the top of the tank is 5 mph or less to the extent practicable, but in no case shall measurements be taken when the sustained wind speed at top of tank is greater than the annual average wind speed at the site or 15 mph, whichever is less.
    (iv) Measurements should be conducted when the internal floating roof is floating with limited product movement (limited filling or emptying of the tank).
    (4) To determine the actual vapor concentration within the storage vessel, the percent of the LEL “as the calibration gas” must be corrected according to one of the following procedures. Alternatively, if the LEL meter used has correction factors that can be selected from the meter's program, you may enable this feature to automatically apply one of the correction factors specified in paragraphs (j)(4)(i) and (ii) of this section.
    (i) Multiply the measurement by the published gasoline vapor correction factor for the specific LEL meter and calibration gas used.
    (ii) If there is no published correction factor for gasoline vapors for the specific LEL meter used, multiply the measurement by the published correction factor for butane as a surrogate for determining the LEL of gasoline vapors. The correction factor must correspond to the calibration gas used.
    (5) Use the calculation procedures in paragraphs (j)(5)(i) through (iii) of this section to determine compliance with the LEL level.
    (i) For each minute while measurements are being taken, determine the one-minute average reading as the arithmetic average of the corrected individual measurements (taken at least once every 15 seconds) during the minute.
    (ii) Starting with the end of the fifth minute of data, calculate a five-minute rolling average as the arithmetic average of the previous five one-minute readings determined under paragraph (j)(5)(i) of this section. Determine a new five-minute average reading for every subsequent one-minute reading.
    (iii) Each five-minute rolling average must meet the LEL level specified in § 63.423(b)(2).

Citations to §63.425(j)(3)

  • (j) Compliance with the vapor concentration below the LEL level for internal floating roof storage vessels at § 63.423(b)(2) shall be determined based on the procedures specified in paragraphs (j)(1) through (5) of this section. If tubing is necessary to obtain the measurements, the tubing must be non-crimping and made of Teflon or other inert material.
    (1) LEL monitoring must be conducted at least once every 12 months and at other times upon request by the Administrator. If the measurement cannot be performed due to wind speeds exceeding those specified in paragraph (j)(3)(iii) of this section, the measurement must be performed within 30 days of the previous attempt.
    (2) The calibration of the LEL meter must be checked per manufacturer specifications immediately before and after the measurements as specified in paragraphs (j)(2)(i) and (ii) of this section. If tubing will be used for the measurements, the tubing must be attached during calibration so that the calibration gas travels through the entire measurement system.
    (i) The calibration gas must contain a single hydrocarbon at a concentration corresponding to 50 percent of the LEL (e.g., 2.50 percent by volume when using methane as the calibration gas). The vendor must provide a Certificate of Analysis for the gas, and the certified concentration must be within ±2 percent (e.g., 2.45 percent—2.55 percent by volume when using methane as the calibration gas). The LEL span response must be between 49 percent and 51 percent. If the span check prior to the measurements does not meet this requirement, the LEL meter must be recalibrated or replaced. If the span check after the measurements does not meet this requirement, the LEL meter must be recalibrated or replaced, and the measurements must be repeated.
    (ii) Check the instrumental offset response using a certified compressed gas cylinder of zero air or an ambient environment that is free of organic compounds. The pre-measurement instrumental offset response must be 0 percent LEL. If the LEL meter does not meet this requirement, the LEL meter must be recalibrated or replaced.
    (i) Measurements of the vapors within the internal floating roof storage vessel must be collected no more than 3 feet above the internal floating roof.
    (ii) Measurements shall be taken for a minimum of 20 minutes, logging the measurements at least once every 15 seconds, or until one 5-minute average as determined according to paragraph (j)(5)(ii) of this section exceeds the level specified in § 63.423(b)(2).
    (iii) Measurements shall be taken when the wind speed at the top of the tank is 5 mph or less to the extent practicable, but in no case shall measurements be taken when the sustained wind speed at top of tank is greater than the annual average wind speed at the site or 15 mph, whichever is less.
    (iv) Measurements should be conducted when the internal floating roof is floating with limited product movement (limited filling or emptying of the tank).
    (4) To determine the actual vapor concentration within the storage vessel, the percent of the LEL “as the calibration gas” must be corrected according to one of the following procedures. Alternatively, if the LEL meter used has correction factors that can be selected from the meter's program, you may enable this feature to automatically apply one of the correction factors specified in paragraphs (j)(4)(i) and (ii) of this section.
    (i) Multiply the measurement by the published gasoline vapor correction factor for the specific LEL meter and calibration gas used.
    (ii) If there is no published correction factor for gasoline vapors for the specific LEL meter used, multiply the measurement by the published correction factor for butane as a surrogate for determining the LEL of gasoline vapors. The correction factor must correspond to the calibration gas used.
    (5) Use the calculation procedures in paragraphs (j)(5)(i) through (iii) of this section to determine compliance with the LEL level.
    (i) For each minute while measurements are being taken, determine the one-minute average reading as the arithmetic average of the corrected individual measurements (taken at least once every 15 seconds) during the minute.
    (ii) Starting with the end of the fifth minute of data, calculate a five-minute rolling average as the arithmetic average of the previous five one-minute readings determined under paragraph (j)(5)(i) of this section. Determine a new five-minute average reading for every subsequent one-minute reading.
    (iii) Each five-minute rolling average must meet the LEL level specified in § 63.423(b)(2).

Citations to §63.425(j)(4)

  • (j) Compliance with the vapor concentration below the LEL level for internal floating roof storage vessels at § 63.423(b)(2) shall be determined based on the procedures specified in paragraphs (j)(1) through (5) of this section. If tubing is necessary to obtain the measurements, the tubing must be non-crimping and made of Teflon or other inert material.
    (1) LEL monitoring must be conducted at least once every 12 months and at other times upon request by the Administrator. If the measurement cannot be performed due to wind speeds exceeding those specified in paragraph (j)(3)(iii) of this section, the measurement must be performed within 30 days of the previous attempt.
    (2) The calibration of the LEL meter must be checked per manufacturer specifications immediately before and after the measurements as specified in paragraphs (j)(2)(i) and (ii) of this section. If tubing will be used for the measurements, the tubing must be attached during calibration so that the calibration gas travels through the entire measurement system.
    (i) The calibration gas must contain a single hydrocarbon at a concentration corresponding to 50 percent of the LEL (e.g., 2.50 percent by volume when using methane as the calibration gas). The vendor must provide a Certificate of Analysis for the gas, and the certified concentration must be within ±2 percent (e.g., 2.45 percent—2.55 percent by volume when using methane as the calibration gas). The LEL span response must be between 49 percent and 51 percent. If the span check prior to the measurements does not meet this requirement, the LEL meter must be recalibrated or replaced. If the span check after the measurements does not meet this requirement, the LEL meter must be recalibrated or replaced, and the measurements must be repeated.
    (ii) Check the instrumental offset response using a certified compressed gas cylinder of zero air or an ambient environment that is free of organic compounds. The pre-measurement instrumental offset response must be 0 percent LEL. If the LEL meter does not meet this requirement, the LEL meter must be recalibrated or replaced.
    (i) Measurements of the vapors within the internal floating roof storage vessel must be collected no more than 3 feet above the internal floating roof.
    (ii) Measurements shall be taken for a minimum of 20 minutes, logging the measurements at least once every 15 seconds, or until one 5-minute average as determined according to paragraph (j)(5)(ii) of this section exceeds the level specified in § 63.423(b)(2).
    (iii) Measurements shall be taken when the wind speed at the top of the tank is 5 mph or less to the extent practicable, but in no case shall measurements be taken when the sustained wind speed at top of tank is greater than the annual average wind speed at the site or 15 mph, whichever is less.
    (iv) Measurements should be conducted when the internal floating roof is floating with limited product movement (limited filling or emptying of the tank).
    (4) To determine the actual vapor concentration within the storage vessel, the percent of the LEL “as the calibration gas” must be corrected according to one of the following procedures. Alternatively, if the LEL meter used has correction factors that can be selected from the meter's program, you may enable this feature to automatically apply one of the correction factors specified in paragraphs (j)(4)(i) and (ii) of this section.
    (i) Multiply the measurement by the published gasoline vapor correction factor for the specific LEL meter and calibration gas used.
    (ii) If there is no published correction factor for gasoline vapors for the specific LEL meter used, multiply the measurement by the published correction factor for butane as a surrogate for determining the LEL of gasoline vapors. The correction factor must correspond to the calibration gas used.
    (5) Use the calculation procedures in paragraphs (j)(5)(i) through (iii) of this section to determine compliance with the LEL level.
    (i) For each minute while measurements are being taken, determine the one-minute average reading as the arithmetic average of the corrected individual measurements (taken at least once every 15 seconds) during the minute.
    (ii) Starting with the end of the fifth minute of data, calculate a five-minute rolling average as the arithmetic average of the previous five one-minute readings determined under paragraph (j)(5)(i) of this section. Determine a new five-minute average reading for every subsequent one-minute reading.
    (iii) Each five-minute rolling average must meet the LEL level specified in § 63.423(b)(2).

Citations to §63.425(j)(5)

  • (j) Compliance with the vapor concentration below the LEL level for internal floating roof storage vessels at § 63.423(b)(2) shall be determined based on the procedures specified in paragraphs (j)(1) through (5) of this section. If tubing is necessary to obtain the measurements, the tubing must be non-crimping and made of Teflon or other inert material.
    (1) LEL monitoring must be conducted at least once every 12 months and at other times upon request by the Administrator. If the measurement cannot be performed due to wind speeds exceeding those specified in paragraph (j)(3)(iii) of this section, the measurement must be performed within 30 days of the previous attempt.
    (2) The calibration of the LEL meter must be checked per manufacturer specifications immediately before and after the measurements as specified in paragraphs (j)(2)(i) and (ii) of this section. If tubing will be used for the measurements, the tubing must be attached during calibration so that the calibration gas travels through the entire measurement system.
    (i) The calibration gas must contain a single hydrocarbon at a concentration corresponding to 50 percent of the LEL (e.g., 2.50 percent by volume when using methane as the calibration gas). The vendor must provide a Certificate of Analysis for the gas, and the certified concentration must be within ±2 percent (e.g., 2.45 percent—2.55 percent by volume when using methane as the calibration gas). The LEL span response must be between 49 percent and 51 percent. If the span check prior to the measurements does not meet this requirement, the LEL meter must be recalibrated or replaced. If the span check after the measurements does not meet this requirement, the LEL meter must be recalibrated or replaced, and the measurements must be repeated.
    (ii) Check the instrumental offset response using a certified compressed gas cylinder of zero air or an ambient environment that is free of organic compounds. The pre-measurement instrumental offset response must be 0 percent LEL. If the LEL meter does not meet this requirement, the LEL meter must be recalibrated or replaced.
    (i) Measurements of the vapors within the internal floating roof storage vessel must be collected no more than 3 feet above the internal floating roof.
    (ii) Measurements shall be taken for a minimum of 20 minutes, logging the measurements at least once every 15 seconds, or until one 5-minute average as determined according to paragraph (j)(5)(ii) of this section exceeds the level specified in § 63.423(b)(2).
    (iii) Measurements shall be taken when the wind speed at the top of the tank is 5 mph or less to the extent practicable, but in no case shall measurements be taken when the sustained wind speed at top of tank is greater than the annual average wind speed at the site or 15 mph, whichever is less.
    (iv) Measurements should be conducted when the internal floating roof is floating with limited product movement (limited filling or emptying of the tank).
    (4) To determine the actual vapor concentration within the storage vessel, the percent of the LEL “as the calibration gas” must be corrected according to one of the following procedures. Alternatively, if the LEL meter used has correction factors that can be selected from the meter's program, you may enable this feature to automatically apply one of the correction factors specified in paragraphs (j)(4)(i) and (ii) of this section.
    (i) Multiply the measurement by the published gasoline vapor correction factor for the specific LEL meter and calibration gas used.
    (ii) If there is no published correction factor for gasoline vapors for the specific LEL meter used, multiply the measurement by the published correction factor for butane as a surrogate for determining the LEL of gasoline vapors. The correction factor must correspond to the calibration gas used.
    (5) Use the calculation procedures in paragraphs (j)(5)(i) through (iii) of this section to determine compliance with the LEL level.
    (i) For each minute while measurements are being taken, determine the one-minute average reading as the arithmetic average of the corrected individual measurements (taken at least once every 15 seconds) during the minute.
    (ii) Starting with the end of the fifth minute of data, calculate a five-minute rolling average as the arithmetic average of the previous five one-minute readings determined under paragraph (j)(5)(i) of this section. Determine a new five-minute average reading for every subsequent one-minute reading.
    (iii) Each five-minute rolling average must meet the LEL level specified in § 63.423(b)(2).

Citations to §63.425(j)(5)(i)

  • (5) Use the calculation procedures in paragraphs (j)(5)(i) through (iii) of this section to determine compliance with the LEL level.
    (i) For each minute while measurements are being taken, determine the one-minute average reading as the arithmetic average of the corrected individual measurements (taken at least once every 15 seconds) during the minute.
    (ii) Starting with the end of the fifth minute of data, calculate a five-minute rolling average as the arithmetic average of the previous five one-minute readings determined under paragraph (j)(5)(i) of this section. Determine a new five-minute average reading for every subsequent one-minute reading.
    (iii) Each five-minute rolling average must meet the LEL level specified in § 63.423(b)(2).

Citations to §63.425(j)(5)(ii)

  • (5) Use the calculation procedures in paragraphs (j)(5)(i) through (iii) of this section to determine compliance with the LEL level.
    (i) For each minute while measurements are being taken, determine the one-minute average reading as the arithmetic average of the corrected individual measurements (taken at least once every 15 seconds) during the minute.
    (ii) Starting with the end of the fifth minute of data, calculate a five-minute rolling average as the arithmetic average of the previous five one-minute readings determined under paragraph (j)(5)(i) of this section. Determine a new five-minute average reading for every subsequent one-minute reading.
    (iii) Each five-minute rolling average must meet the LEL level specified in § 63.423(b)(2).

Citations to §63.425(j)(5)(iii)

  • (5) Use the calculation procedures in paragraphs (j)(5)(i) through (iii) of this section to determine compliance with the LEL level.
    (i) For each minute while measurements are being taken, determine the one-minute average reading as the arithmetic average of the corrected individual measurements (taken at least once every 15 seconds) during the minute.
    (ii) Starting with the end of the fifth minute of data, calculate a five-minute rolling average as the arithmetic average of the previous five one-minute readings determined under paragraph (j)(5)(i) of this section. Determine a new five-minute average reading for every subsequent one-minute reading.
    (iii) Each five-minute rolling average must meet the LEL level specified in § 63.423(b)(2).