§63.424. Standards: Equipment leaks. — Inbound Citations

40 C.F.R. § 63.424

Cited by 17 regulations in release Current.

Citations to 40 C.F.R. § 63.424 as a whole

  • (1) A bulk gasoline terminal that is not subject to the control requirements of 40 CFR part 63, subpart R (§§ 63.422, 63.423, and 63.424) or 40 CFR part 63, subpart CC (§§ 63.646, 63.648, 63.649, and 63.650).
  • (f) Each owner or operator complying with the provisions of § 63.424 shall keep records of the information in paragraphs (f)(1) and (2) of this section.
    (1) Each owner or operator complying with the provisions of § 63.424(b) shall record the following information in the logbook for each leak that is detected:
    (i) The equipment type and identification number;
    (ii) The nature of the leak (i.e., vapor or liquid) and the method of detection (i.e., sight, sound, or smell);
    (iii) The date the leak was detected and the date of each attempt to repair the leak;
    (iv) Repair methods applied in each attempt to repair the leak;
    (v) “Repair delayed” and the reason for the delay if the leak is not repaired within 15 calendar days after discovery of the leak;
    (vi) The expected date of successful repair of the leak if the leak is not repaired within 15 days; and
    (2) Each owner or operator complying with the provisions of § 63.424(c) or § 60.503a(a)(2) of this chapter shall keep records of the following information:
    (ii) For each leak inspection conducted under § 63.424(c) or § 60.503a(a)(2) of this chapter, keep the following records:
    (A) An indication if the leak inspection was conducted under § 63.424(c) or § 60.503a(a)(2) of this chapter.
    (iii) For leak inspections conducted with Method 21 of appendix A-7 to part 60 of this chapter, keep the following additional records:
    (iv) For leak inspections conducted with OGI, keep the records specified in section 12 of appendix K to part 60 of this chapter.
    (v) For each leak that is detected during a leak inspection or by audio/visual/olfactory methods during normal duties, record the following information:
    (B) The date the leak was detected, the name of the person who found the leak, nature of the leak (i.e., vapor or liquid) and the method of detection (i.e., audio/visual/olfactory, Method 21 of appendix A-7 to part 60 of this chapter, or OGI).
    (C) The date of each attempt to repair the leak and the repair methods applied in each attempt to repair the leak.
    (D) The date of successful repair of the leak, the method of monitoring used to confirm the repair, and if Method 21 of appendix A-7 to part 60 of this chapter is used to confirm the repair, the maximum instrument reading measured by Method 21 of appendix A-7 to part 60. If OGI is used to confirm the repair, keep video footage of the repair confirmation.
    (E) For each repair delayed beyond 15 calendar days after discovery of the leak, record “Repair delayed”, the reason for the delay, and the expected date of successful repair. The owner or operator (or designate) whose decision it was that repair could not be carried out in the 15-calendar day timeframe must sign the record.
    (F) For each leak that is not repairable, the maximum instrument reading measured by Method 21 of appendix A-7 to part 60 of this chapter at the time the leak is determined to be not repairable, a video captured by the OGI camera showing that emissions are still visible, or a signed record that the leak is still detectable via audio/visual/olfactory methods.
  • (1) Approval of alternatives to the requirements in §§ 63.420, 63.422 through 63.423, and 63.424. Any owner or operator requesting to use an alternative means of emission limitation for storage vessels covered by § 63.423 must follow the procedures in § 63.426.

Citations to §63.424(a)

Citations to §63.424(b)

  • (1) Each owner or operator complying with the provisions of § 63.424(b) shall record the following information in the logbook for each leak that is detected:
    (i) The equipment type and identification number;
    (ii) The nature of the leak (i.e., vapor or liquid) and the method of detection (i.e., sight, sound, or smell);
    (iii) The date the leak was detected and the date of each attempt to repair the leak;
    (iv) Repair methods applied in each attempt to repair the leak;
    (v) “Repair delayed” and the reason for the delay if the leak is not repaired within 15 calendar days after discovery of the leak;
    (vi) The expected date of successful repair of the leak if the leak is not repaired within 15 days; and

Citations to §63.424(b)(1)

Citations to §63.424(b)(2)

Citations to §63.424(b)(3)

Citations to §63.424(b)(4)

  • (1) Each owner or operator subject to the provisions of § 63.424 shall report to the Administrator a description of the types, identification numbers, and locations of all equipment in gasoline service. For facilities electing to implement an instrument program under § 63.424(b)(4), the report shall contain a full description of the program.
    (i) In the case of an existing source or a new source that has an initial startup date before December 14, 1994, the report shall be submitted with the notification of compliance status required under § 63.9(h), unless an extension of compliance is granted under § 63.6(i). If an extension of compliance is granted, the report shall be submitted on a date scheduled by the Administrator.
    (ii) In the case of new sources that did not have an initial startup date before December 14, 1994, the report shall be submitted with the application for approval of construction, as described in § 63.5(d).

Citations to §63.424(c)

  • (2) Each owner or operator complying with the provisions of § 63.424(c) or § 60.503a(a)(2) of this chapter shall keep records of the following information:
    (ii) For each leak inspection conducted under § 63.424(c) or § 60.503a(a)(2) of this chapter, keep the following records:
    (A) An indication if the leak inspection was conducted under § 63.424(c) or § 60.503a(a)(2) of this chapter.
    (iii) For leak inspections conducted with Method 21 of appendix A-7 to part 60 of this chapter, keep the following additional records:
    (iv) For leak inspections conducted with OGI, keep the records specified in section 12 of appendix K to part 60 of this chapter.
    (v) For each leak that is detected during a leak inspection or by audio/visual/olfactory methods during normal duties, record the following information:
    (B) The date the leak was detected, the name of the person who found the leak, nature of the leak (i.e., vapor or liquid) and the method of detection (i.e., audio/visual/olfactory, Method 21 of appendix A-7 to part 60 of this chapter, or OGI).
    (C) The date of each attempt to repair the leak and the repair methods applied in each attempt to repair the leak.
    (D) The date of successful repair of the leak, the method of monitoring used to confirm the repair, and if Method 21 of appendix A-7 to part 60 of this chapter is used to confirm the repair, the maximum instrument reading measured by Method 21 of appendix A-7 to part 60. If OGI is used to confirm the repair, keep video footage of the repair confirmation.
    (E) For each repair delayed beyond 15 calendar days after discovery of the leak, record “Repair delayed”, the reason for the delay, and the expected date of successful repair. The owner or operator (or designate) whose decision it was that repair could not be carried out in the 15-calendar day timeframe must sign the record.
    (F) For each leak that is not repairable, the maximum instrument reading measured by Method 21 of appendix A-7 to part 60 of this chapter at the time the leak is determined to be not repairable, a video captured by the OGI camera showing that emissions are still visible, or a signed record that the leak is still detectable via audio/visual/olfactory methods.

Citations to §63.424(c)(1)

  • (c) Comply with the requirements in § 60.502a(j) of this chapter except as provided in paragraphs (c)(1) through (3) of this section.
    (1) The frequency for optical gas imaging (OGI) monitoring shall be semiannually rather than quarterly as specified in § 60.502a(j)(1)(i).
    (2) The frequency for Method 21 monitoring of pumps and valves shall be semiannually rather than quarterly as specified in § 60.502a(j)(1)(ii)(A) and (B).
    (3) The frequency of monitoring of pressure relief devices shall be semiannually and within 5 calendar days after each pressure release rather than quarterly and within 5 calendar days after each pressure release as specified in § 60.502a(j)(4)(i).

Citations to §63.424(c)(2)

  • (c) Comply with the requirements in § 60.502a(j) of this chapter except as provided in paragraphs (c)(1) through (3) of this section.
    (1) The frequency for optical gas imaging (OGI) monitoring shall be semiannually rather than quarterly as specified in § 60.502a(j)(1)(i).
    (2) The frequency for Method 21 monitoring of pumps and valves shall be semiannually rather than quarterly as specified in § 60.502a(j)(1)(ii)(A) and (B).
    (3) The frequency of monitoring of pressure relief devices shall be semiannually and within 5 calendar days after each pressure release rather than quarterly and within 5 calendar days after each pressure release as specified in § 60.502a(j)(4)(i).

Citations to §63.424(c)(3)

  • (c) Comply with the requirements in § 60.502a(j) of this chapter except as provided in paragraphs (c)(1) through (3) of this section.
    (1) The frequency for optical gas imaging (OGI) monitoring shall be semiannually rather than quarterly as specified in § 60.502a(j)(1)(i).
    (2) The frequency for Method 21 monitoring of pumps and valves shall be semiannually rather than quarterly as specified in § 60.502a(j)(1)(ii)(A) and (B).
    (3) The frequency of monitoring of pressure relief devices shall be semiannually and within 5 calendar days after each pressure release rather than quarterly and within 5 calendar days after each pressure release as specified in § 60.502a(j)(4)(i).

Citations to §63.424(e)

Citations to §63.424(e)(1)

  • (e) Compliance with the provisions of this section shall be achieved as expeditiously as practicable, but no later than the dates provided in paragraphs (e)(1) through (3) of this section.
    (1) For facilities that commenced construction on or before February 8, 1994, meet the requirements in paragraphs (b) and (d) of this section no later than December 15, 1997. Beginning no later than May 8, 2027, paragraph (b) of this section no longer applies and facilities shall meet the requirements in paragraphs (c) and (d) of this section no later than May 8, 2027.
    (2) For facilities that commenced construction after February 8, 1994, and on or before June 10, 2022, meet the requirements in paragraphs (b) and (d) of this section upon startup. Beginning no later than May 8, 2027, paragraph (b) of this section no longer applies and facilities shall meet the requirements in paragraphs (c) and (d) of this section no later than May 8, 2027.
    (3) For facilities that commenced construction after June 10, 2022, meet the requirements in paragraph (c) and (d) of this section upon startup or July 8, 2024, whichever is later.

Citations to §63.424(e)(2)

  • (e) Compliance with the provisions of this section shall be achieved as expeditiously as practicable, but no later than the dates provided in paragraphs (e)(1) through (3) of this section.
    (1) For facilities that commenced construction on or before February 8, 1994, meet the requirements in paragraphs (b) and (d) of this section no later than December 15, 1997. Beginning no later than May 8, 2027, paragraph (b) of this section no longer applies and facilities shall meet the requirements in paragraphs (c) and (d) of this section no later than May 8, 2027.
    (2) For facilities that commenced construction after February 8, 1994, and on or before June 10, 2022, meet the requirements in paragraphs (b) and (d) of this section upon startup. Beginning no later than May 8, 2027, paragraph (b) of this section no longer applies and facilities shall meet the requirements in paragraphs (c) and (d) of this section no later than May 8, 2027.
    (3) For facilities that commenced construction after June 10, 2022, meet the requirements in paragraph (c) and (d) of this section upon startup or July 8, 2024, whichever is later.

Citations to §63.424(e)(3)

  • (e) Compliance with the provisions of this section shall be achieved as expeditiously as practicable, but no later than the dates provided in paragraphs (e)(1) through (3) of this section.
    (1) For facilities that commenced construction on or before February 8, 1994, meet the requirements in paragraphs (b) and (d) of this section no later than December 15, 1997. Beginning no later than May 8, 2027, paragraph (b) of this section no longer applies and facilities shall meet the requirements in paragraphs (c) and (d) of this section no later than May 8, 2027.
    (2) For facilities that commenced construction after February 8, 1994, and on or before June 10, 2022, meet the requirements in paragraphs (b) and (d) of this section upon startup. Beginning no later than May 8, 2027, paragraph (b) of this section no longer applies and facilities shall meet the requirements in paragraphs (c) and (d) of this section no later than May 8, 2027.
    (3) For facilities that commenced construction after June 10, 2022, meet the requirements in paragraph (c) and (d) of this section upon startup or July 8, 2024, whichever is later.