(b) You must demonstrate initial compliance with each compliance option, operating requirement, and work practice requirement that applies to you according to Tables 5 and 6 to this subpart and according to §§ 63.2260 through 63.2269 of this subpart.
Citations to §63.2269(a)
-
If you operate a dry rotary dryer, you must demonstrate that your dryer processes furnish with an inlet moisture content of less than or equal to 30 percent (by weight, dry basis) and operates with a dryer inlet temperature of less than or equal to 600 °F. You must designate and clearly identify each dry rotary dryer. You must record the inlet furnish moisture content (dry basis) and inlet dryer operating temperature according to §§ 63.2269(a), (b), and (c) and 63.2270 for a minimum of 30 calendar days. You must submit the highest recorded 24-hour average inlet furnish moisture content and the highest recorded 24-hour average dryer inlet temperature with your Notification of Compliance Status. In addition, you must submit with the Notification of Compliance Status a signed statement by a responsible official that certifies with truth, accuracy, and completeness that the dry rotary dryer will dry furnish with a maximum inlet moisture content less than or equal to 30 percent (by weight, dry basis) and will operate with a maximum inlet temperature of less than or equal to 600 °F in the future.
-
If you operate a veneer redryer, you must record the inlet moisture content of the veneer processed in the redryer according to §§ 63.2269(a) and (c) and 63.2270 for a minimum of 30 calendar days. You must designate and clearly identify each veneer redryer. You must submit the highest recorded 24-hour average inlet veneer moisture content with your Notification of Compliance Status to show that your veneer redryer processes veneer with an inlet moisture content of less than or equal to 25 percent (by weight, dry basis). In addition, submit with the Notification of Compliance Status a signed statement by a responsible official that certifies with truth, accuracy, and completeness that the veneer redryer will dry veneer with a moisture content less than 25 percent (by weight, dry basis) in the future.
Citations to §63.2269(a)(1)
-
(a) You must install, operate, and maintain each continuous parameter monitoring system (CPMS) according to paragraphs (a)(1) through (3) of this section.(1) The CPMS must be capable of completing a minimum of one cycle of operation (sampling, analyzing, and recording) for each successive 15-minute period.(2) At all times, you must maintain the monitoring equipment including, but not limited to, maintaining necessary parts for routine repairs of the monitoring equipment.
Citations to §63.2269(a)(2)
-
(a) You must install, operate, and maintain each continuous parameter monitoring system (CPMS) according to paragraphs (a)(1) through (3) of this section.(1) The CPMS must be capable of completing a minimum of one cycle of operation (sampling, analyzing, and recording) for each successive 15-minute period.(2) At all times, you must maintain the monitoring equipment including, but not limited to, maintaining necessary parts for routine repairs of the monitoring equipment.
Citations to §63.2269(a)(3)
-
(a) You must install, operate, and maintain each continuous parameter monitoring system (CPMS) according to paragraphs (a)(1) through (3) of this section.(1) The CPMS must be capable of completing a minimum of one cycle of operation (sampling, analyzing, and recording) for each successive 15-minute period.(2) At all times, you must maintain the monitoring equipment including, but not limited to, maintaining necessary parts for routine repairs of the monitoring equipment.
Citations to §63.2269(b)
-
If you operate a dry rotary dryer, you must demonstrate that your dryer processes furnish with an inlet moisture content of less than or equal to 30 percent (by weight, dry basis) and operates with a dryer inlet temperature of less than or equal to 600 °F. You must designate and clearly identify each dry rotary dryer. You must record the inlet furnish moisture content (dry basis) and inlet dryer operating temperature according to §§ 63.2269(a), (b), and (c) and 63.2270 for a minimum of 30 calendar days. You must submit the highest recorded 24-hour average inlet furnish moisture content and the highest recorded 24-hour average dryer inlet temperature with your Notification of Compliance Status. In addition, you must submit with the Notification of Compliance Status a signed statement by a responsible official that certifies with truth, accuracy, and completeness that the dry rotary dryer will dry furnish with a maximum inlet moisture content less than or equal to 30 percent (by weight, dry basis) and will operate with a maximum inlet temperature of less than or equal to 600 °F in the future.
Citations to §63.2269(b)(1)
-
(b) For each temperature monitoring device, you must meet the requirements in paragraphs (a) and (b)(1) through (6) of this section.(2) Use a temperature sensor with a minimum accuracy of 4 °F or 0.75 percent of the temperature value, whichever is larger.(3) If a chart recorder is used, it must have a sensitivity with minor divisions not more than 20 °F.(4) Validate the temperature sensor's reading at least semiannually using the requirements of paragraph (b)(4)(i), (ii), (iii), (iv), or (v) of this section:(i) Compare measured readings to a National Institute of Standards and Technology (NIST) traceable temperature measurement device or simulate a typical operating temperature using a NIST traceable temperature simulation device. When the temperature measurement device method is used, the sensor of the NIST traceable calibrated device must be placed as close as practicable to the process sensor, and both devices must be subjected to the same environmental conditions. The accuracy of the temperature measured must be 2.5 percent of the temperature measured by the NIST traceable device or 5 °F, whichever is greater.(iii) Request thermocouple manufacturer to certify or re-certify electromotive force (electrical properties) of the thermocouple.(v) Permanently install a redundant temperature sensor as close as practicable to the process temperature sensor. The sensors must yield a reading within 30 °F of each other for thermal oxidizers and catalytic oxidizers; within 5 °F of each other for biofilters; and within 20 °F of each other for dry rotary dryers.(5) Conduct validation checks using the procedures in paragraph (b)(4) of this section any time the sensor exceeds the manufacturer's specified maximum operating temperature range or install a new temperature sensor.(6) At least quarterly, inspect all components for integrity and all electrical connections for continuity, oxidation, and galvanic corrosion.
Citations to §63.2269(b)(2)
-
(b) For each temperature monitoring device, you must meet the requirements in paragraphs (a) and (b)(1) through (6) of this section.(2) Use a temperature sensor with a minimum accuracy of 4 °F or 0.75 percent of the temperature value, whichever is larger.(3) If a chart recorder is used, it must have a sensitivity with minor divisions not more than 20 °F.(4) Validate the temperature sensor's reading at least semiannually using the requirements of paragraph (b)(4)(i), (ii), (iii), (iv), or (v) of this section:(i) Compare measured readings to a National Institute of Standards and Technology (NIST) traceable temperature measurement device or simulate a typical operating temperature using a NIST traceable temperature simulation device. When the temperature measurement device method is used, the sensor of the NIST traceable calibrated device must be placed as close as practicable to the process sensor, and both devices must be subjected to the same environmental conditions. The accuracy of the temperature measured must be 2.5 percent of the temperature measured by the NIST traceable device or 5 °F, whichever is greater.(iii) Request thermocouple manufacturer to certify or re-certify electromotive force (electrical properties) of the thermocouple.(v) Permanently install a redundant temperature sensor as close as practicable to the process temperature sensor. The sensors must yield a reading within 30 °F of each other for thermal oxidizers and catalytic oxidizers; within 5 °F of each other for biofilters; and within 20 °F of each other for dry rotary dryers.(5) Conduct validation checks using the procedures in paragraph (b)(4) of this section any time the sensor exceeds the manufacturer's specified maximum operating temperature range or install a new temperature sensor.(6) At least quarterly, inspect all components for integrity and all electrical connections for continuity, oxidation, and galvanic corrosion.
Citations to §63.2269(b)(3)
-
(b) For each temperature monitoring device, you must meet the requirements in paragraphs (a) and (b)(1) through (6) of this section.(2) Use a temperature sensor with a minimum accuracy of 4 °F or 0.75 percent of the temperature value, whichever is larger.(3) If a chart recorder is used, it must have a sensitivity with minor divisions not more than 20 °F.(4) Validate the temperature sensor's reading at least semiannually using the requirements of paragraph (b)(4)(i), (ii), (iii), (iv), or (v) of this section:(i) Compare measured readings to a National Institute of Standards and Technology (NIST) traceable temperature measurement device or simulate a typical operating temperature using a NIST traceable temperature simulation device. When the temperature measurement device method is used, the sensor of the NIST traceable calibrated device must be placed as close as practicable to the process sensor, and both devices must be subjected to the same environmental conditions. The accuracy of the temperature measured must be 2.5 percent of the temperature measured by the NIST traceable device or 5 °F, whichever is greater.(iii) Request thermocouple manufacturer to certify or re-certify electromotive force (electrical properties) of the thermocouple.(v) Permanently install a redundant temperature sensor as close as practicable to the process temperature sensor. The sensors must yield a reading within 30 °F of each other for thermal oxidizers and catalytic oxidizers; within 5 °F of each other for biofilters; and within 20 °F of each other for dry rotary dryers.(5) Conduct validation checks using the procedures in paragraph (b)(4) of this section any time the sensor exceeds the manufacturer's specified maximum operating temperature range or install a new temperature sensor.(6) At least quarterly, inspect all components for integrity and all electrical connections for continuity, oxidation, and galvanic corrosion.
Citations to §63.2269(b)(4)
-
(b) For each temperature monitoring device, you must meet the requirements in paragraphs (a) and (b)(1) through (6) of this section.(2) Use a temperature sensor with a minimum accuracy of 4 °F or 0.75 percent of the temperature value, whichever is larger.(3) If a chart recorder is used, it must have a sensitivity with minor divisions not more than 20 °F.(4) Validate the temperature sensor's reading at least semiannually using the requirements of paragraph (b)(4)(i), (ii), (iii), (iv), or (v) of this section:(i) Compare measured readings to a National Institute of Standards and Technology (NIST) traceable temperature measurement device or simulate a typical operating temperature using a NIST traceable temperature simulation device. When the temperature measurement device method is used, the sensor of the NIST traceable calibrated device must be placed as close as practicable to the process sensor, and both devices must be subjected to the same environmental conditions. The accuracy of the temperature measured must be 2.5 percent of the temperature measured by the NIST traceable device or 5 °F, whichever is greater.(iii) Request thermocouple manufacturer to certify or re-certify electromotive force (electrical properties) of the thermocouple.(v) Permanently install a redundant temperature sensor as close as practicable to the process temperature sensor. The sensors must yield a reading within 30 °F of each other for thermal oxidizers and catalytic oxidizers; within 5 °F of each other for biofilters; and within 20 °F of each other for dry rotary dryers.(5) Conduct validation checks using the procedures in paragraph (b)(4) of this section any time the sensor exceeds the manufacturer's specified maximum operating temperature range or install a new temperature sensor.(6) At least quarterly, inspect all components for integrity and all electrical connections for continuity, oxidation, and galvanic corrosion.
Citations to §63.2269(b)(5)
-
(b) For each temperature monitoring device, you must meet the requirements in paragraphs (a) and (b)(1) through (6) of this section.(2) Use a temperature sensor with a minimum accuracy of 4 °F or 0.75 percent of the temperature value, whichever is larger.(3) If a chart recorder is used, it must have a sensitivity with minor divisions not more than 20 °F.(4) Validate the temperature sensor's reading at least semiannually using the requirements of paragraph (b)(4)(i), (ii), (iii), (iv), or (v) of this section:(i) Compare measured readings to a National Institute of Standards and Technology (NIST) traceable temperature measurement device or simulate a typical operating temperature using a NIST traceable temperature simulation device. When the temperature measurement device method is used, the sensor of the NIST traceable calibrated device must be placed as close as practicable to the process sensor, and both devices must be subjected to the same environmental conditions. The accuracy of the temperature measured must be 2.5 percent of the temperature measured by the NIST traceable device or 5 °F, whichever is greater.(iii) Request thermocouple manufacturer to certify or re-certify electromotive force (electrical properties) of the thermocouple.(v) Permanently install a redundant temperature sensor as close as practicable to the process temperature sensor. The sensors must yield a reading within 30 °F of each other for thermal oxidizers and catalytic oxidizers; within 5 °F of each other for biofilters; and within 20 °F of each other for dry rotary dryers.(5) Conduct validation checks using the procedures in paragraph (b)(4) of this section any time the sensor exceeds the manufacturer's specified maximum operating temperature range or install a new temperature sensor.(6) At least quarterly, inspect all components for integrity and all electrical connections for continuity, oxidation, and galvanic corrosion.
Citations to §63.2269(b)(6)
-
(b) For each temperature monitoring device, you must meet the requirements in paragraphs (a) and (b)(1) through (6) of this section.(2) Use a temperature sensor with a minimum accuracy of 4 °F or 0.75 percent of the temperature value, whichever is larger.(3) If a chart recorder is used, it must have a sensitivity with minor divisions not more than 20 °F.(4) Validate the temperature sensor's reading at least semiannually using the requirements of paragraph (b)(4)(i), (ii), (iii), (iv), or (v) of this section:(i) Compare measured readings to a National Institute of Standards and Technology (NIST) traceable temperature measurement device or simulate a typical operating temperature using a NIST traceable temperature simulation device. When the temperature measurement device method is used, the sensor of the NIST traceable calibrated device must be placed as close as practicable to the process sensor, and both devices must be subjected to the same environmental conditions. The accuracy of the temperature measured must be 2.5 percent of the temperature measured by the NIST traceable device or 5 °F, whichever is greater.(iii) Request thermocouple manufacturer to certify or re-certify electromotive force (electrical properties) of the thermocouple.(v) Permanently install a redundant temperature sensor as close as practicable to the process temperature sensor. The sensors must yield a reading within 30 °F of each other for thermal oxidizers and catalytic oxidizers; within 5 °F of each other for biofilters; and within 20 °F of each other for dry rotary dryers.(5) Conduct validation checks using the procedures in paragraph (b)(4) of this section any time the sensor exceeds the manufacturer's specified maximum operating temperature range or install a new temperature sensor.(6) At least quarterly, inspect all components for integrity and all electrical connections for continuity, oxidation, and galvanic corrosion.
Citations to §63.2269(c)
-
If you operate a dry rotary dryer, you must demonstrate that your dryer processes furnish with an inlet moisture content of less than or equal to 30 percent (by weight, dry basis) and operates with a dryer inlet temperature of less than or equal to 600 °F. You must designate and clearly identify each dry rotary dryer. You must record the inlet furnish moisture content (dry basis) and inlet dryer operating temperature according to §§ 63.2269(a), (b), and (c) and 63.2270 for a minimum of 30 calendar days. You must submit the highest recorded 24-hour average inlet furnish moisture content and the highest recorded 24-hour average dryer inlet temperature with your Notification of Compliance Status. In addition, you must submit with the Notification of Compliance Status a signed statement by a responsible official that certifies with truth, accuracy, and completeness that the dry rotary dryer will dry furnish with a maximum inlet moisture content less than or equal to 30 percent (by weight, dry basis) and will operate with a maximum inlet temperature of less than or equal to 600 °F in the future.
-
If you operate a veneer redryer, you must record the inlet moisture content of the veneer processed in the redryer according to §§ 63.2269(a) and (c) and 63.2270 for a minimum of 30 calendar days. You must designate and clearly identify each veneer redryer. You must submit the highest recorded 24-hour average inlet veneer moisture content with your Notification of Compliance Status to show that your veneer redryer processes veneer with an inlet moisture content of less than or equal to 25 percent (by weight, dry basis). In addition, submit with the Notification of Compliance Status a signed statement by a responsible official that certifies with truth, accuracy, and completeness that the veneer redryer will dry veneer with a moisture content less than 25 percent (by weight, dry basis) in the future.
Citations to §63.2269(c)(1)
-
(c) For each furnish or veneer moisture meter, you must meet the requirements in paragraphs (a)(1) through (3) and (c)(1) through (5) of this section. This paragraph (c) does not apply for lumber moisture monitoring (covered in paragraphs (n) and (o) of this section) to show compliance with the lumber kilns standards in § 63.2241(e).(1) For dry rotary dryers, use a continuous moisture monitor with a minimum accuracy of 1 percent (dry basis) moisture or better in the 25 to 35 percent (dry basis) moisture content range. For veneer redryers, use a continuous moisture monitor with a minimum accuracy of 3 percent (dry basis) moisture or better in the 15 to 25 percent (dry basis) moisture content range. Alternatively, you may use a continuous moisture monitor with a minimum accuracy of 5 percent (dry basis) moisture or better for dry rotary dryers used to dry furnish with less than 25 percent (dry basis) moisture or for veneer redryers used to redry veneer with less than 20 percent (dry basis) moisture.(2) Locate the moisture monitor in a position that provides a representative measure of furnish or veneer moisture.(3) Calibrate the moisture monitor based on the procedures specified by the moisture monitor manufacturer at least once per semiannual compliance period (or more frequently if recommended by the moisture monitor manufacturer).(4) At least quarterly, inspect all components of the moisture monitor for integrity and all electrical connections for continuity.
Citations to §63.2269(c)(2)
-
(c) For each furnish or veneer moisture meter, you must meet the requirements in paragraphs (a)(1) through (3) and (c)(1) through (5) of this section. This paragraph (c) does not apply for lumber moisture monitoring (covered in paragraphs (n) and (o) of this section) to show compliance with the lumber kilns standards in § 63.2241(e).(1) For dry rotary dryers, use a continuous moisture monitor with a minimum accuracy of 1 percent (dry basis) moisture or better in the 25 to 35 percent (dry basis) moisture content range. For veneer redryers, use a continuous moisture monitor with a minimum accuracy of 3 percent (dry basis) moisture or better in the 15 to 25 percent (dry basis) moisture content range. Alternatively, you may use a continuous moisture monitor with a minimum accuracy of 5 percent (dry basis) moisture or better for dry rotary dryers used to dry furnish with less than 25 percent (dry basis) moisture or for veneer redryers used to redry veneer with less than 20 percent (dry basis) moisture.(2) Locate the moisture monitor in a position that provides a representative measure of furnish or veneer moisture.(3) Calibrate the moisture monitor based on the procedures specified by the moisture monitor manufacturer at least once per semiannual compliance period (or more frequently if recommended by the moisture monitor manufacturer).(4) At least quarterly, inspect all components of the moisture monitor for integrity and all electrical connections for continuity.
Citations to §63.2269(c)(3)
-
(c) For each furnish or veneer moisture meter, you must meet the requirements in paragraphs (a)(1) through (3) and (c)(1) through (5) of this section. This paragraph (c) does not apply for lumber moisture monitoring (covered in paragraphs (n) and (o) of this section) to show compliance with the lumber kilns standards in § 63.2241(e).(1) For dry rotary dryers, use a continuous moisture monitor with a minimum accuracy of 1 percent (dry basis) moisture or better in the 25 to 35 percent (dry basis) moisture content range. For veneer redryers, use a continuous moisture monitor with a minimum accuracy of 3 percent (dry basis) moisture or better in the 15 to 25 percent (dry basis) moisture content range. Alternatively, you may use a continuous moisture monitor with a minimum accuracy of 5 percent (dry basis) moisture or better for dry rotary dryers used to dry furnish with less than 25 percent (dry basis) moisture or for veneer redryers used to redry veneer with less than 20 percent (dry basis) moisture.(2) Locate the moisture monitor in a position that provides a representative measure of furnish or veneer moisture.(3) Calibrate the moisture monitor based on the procedures specified by the moisture monitor manufacturer at least once per semiannual compliance period (or more frequently if recommended by the moisture monitor manufacturer).(4) At least quarterly, inspect all components of the moisture monitor for integrity and all electrical connections for continuity.
Citations to §63.2269(c)(4)
-
(c) For each furnish or veneer moisture meter, you must meet the requirements in paragraphs (a)(1) through (3) and (c)(1) through (5) of this section. This paragraph (c) does not apply for lumber moisture monitoring (covered in paragraphs (n) and (o) of this section) to show compliance with the lumber kilns standards in § 63.2241(e).(1) For dry rotary dryers, use a continuous moisture monitor with a minimum accuracy of 1 percent (dry basis) moisture or better in the 25 to 35 percent (dry basis) moisture content range. For veneer redryers, use a continuous moisture monitor with a minimum accuracy of 3 percent (dry basis) moisture or better in the 15 to 25 percent (dry basis) moisture content range. Alternatively, you may use a continuous moisture monitor with a minimum accuracy of 5 percent (dry basis) moisture or better for dry rotary dryers used to dry furnish with less than 25 percent (dry basis) moisture or for veneer redryers used to redry veneer with less than 20 percent (dry basis) moisture.(2) Locate the moisture monitor in a position that provides a representative measure of furnish or veneer moisture.(3) Calibrate the moisture monitor based on the procedures specified by the moisture monitor manufacturer at least once per semiannual compliance period (or more frequently if recommended by the moisture monitor manufacturer).(4) At least quarterly, inspect all components of the moisture monitor for integrity and all electrical connections for continuity.
Citations to §63.2269(c)(5)
-
(c) For each furnish or veneer moisture meter, you must meet the requirements in paragraphs (a)(1) through (3) and (c)(1) through (5) of this section. This paragraph (c) does not apply for lumber moisture monitoring (covered in paragraphs (n) and (o) of this section) to show compliance with the lumber kilns standards in § 63.2241(e).(1) For dry rotary dryers, use a continuous moisture monitor with a minimum accuracy of 1 percent (dry basis) moisture or better in the 25 to 35 percent (dry basis) moisture content range. For veneer redryers, use a continuous moisture monitor with a minimum accuracy of 3 percent (dry basis) moisture or better in the 15 to 25 percent (dry basis) moisture content range. Alternatively, you may use a continuous moisture monitor with a minimum accuracy of 5 percent (dry basis) moisture or better for dry rotary dryers used to dry furnish with less than 25 percent (dry basis) moisture or for veneer redryers used to redry veneer with less than 20 percent (dry basis) moisture.(2) Locate the moisture monitor in a position that provides a representative measure of furnish or veneer moisture.(3) Calibrate the moisture monitor based on the procedures specified by the moisture monitor manufacturer at least once per semiannual compliance period (or more frequently if recommended by the moisture monitor manufacturer).(4) At least quarterly, inspect all components of the moisture monitor for integrity and all electrical connections for continuity.
Citations to §63.2269(d)(1)
-
(d) Each CEMS must be installed, operated, and maintained according to paragraphs (d)(1) through (4) of this section.(1) Each CEMS for monitoring THC concentration must be installed, operated, and maintained according to Performance Specification 8 of 40 CFR part 60, appendix B. You must also comply with Procedure 1 of 40 CFR part 60, appendix F.(2) You must conduct a performance evaluation of each CEMS according to the requirements in § 63.8 and according to Performance Specification 8 of 40 CFR part 60, appendix B.(3) As specified in § 63.8(c)(4)(ii), each CEMS must complete a minimum of one cycle of operation (sampling, analyzing, and data recording) for each successive 15-minute period.(4) The CEMS data must be reduced as specified in §§ 63.8(g)(2) and 63.2270(d) and (e).
Citations to §63.2269(d)(2)
-
(d) Each CEMS must be installed, operated, and maintained according to paragraphs (d)(1) through (4) of this section.(1) Each CEMS for monitoring THC concentration must be installed, operated, and maintained according to Performance Specification 8 of 40 CFR part 60, appendix B. You must also comply with Procedure 1 of 40 CFR part 60, appendix F.(2) You must conduct a performance evaluation of each CEMS according to the requirements in § 63.8 and according to Performance Specification 8 of 40 CFR part 60, appendix B.(3) As specified in § 63.8(c)(4)(ii), each CEMS must complete a minimum of one cycle of operation (sampling, analyzing, and data recording) for each successive 15-minute period.(4) The CEMS data must be reduced as specified in §§ 63.8(g)(2) and 63.2270(d) and (e).
Citations to §63.2269(d)(3)
-
(d) Each CEMS must be installed, operated, and maintained according to paragraphs (d)(1) through (4) of this section.(1) Each CEMS for monitoring THC concentration must be installed, operated, and maintained according to Performance Specification 8 of 40 CFR part 60, appendix B. You must also comply with Procedure 1 of 40 CFR part 60, appendix F.(2) You must conduct a performance evaluation of each CEMS according to the requirements in § 63.8 and according to Performance Specification 8 of 40 CFR part 60, appendix B.(3) As specified in § 63.8(c)(4)(ii), each CEMS must complete a minimum of one cycle of operation (sampling, analyzing, and data recording) for each successive 15-minute period.(4) The CEMS data must be reduced as specified in §§ 63.8(g)(2) and 63.2270(d) and (e).
Citations to §63.2269(d)(4)
-
(d) Each CEMS must be installed, operated, and maintained according to paragraphs (d)(1) through (4) of this section.(1) Each CEMS for monitoring THC concentration must be installed, operated, and maintained according to Performance Specification 8 of 40 CFR part 60, appendix B. You must also comply with Procedure 1 of 40 CFR part 60, appendix F.(2) You must conduct a performance evaluation of each CEMS according to the requirements in § 63.8 and according to Performance Specification 8 of 40 CFR part 60, appendix B.(3) As specified in § 63.8(c)(4)(ii), each CEMS must complete a minimum of one cycle of operation (sampling, analyzing, and data recording) for each successive 15-minute period.(4) The CEMS data must be reduced as specified in §§ 63.8(g)(2) and 63.2270(d) and (e).
Citations to §63.2269(e)(1)
-
(e) You must install, operate, certify and maintain each COMS according to the procedures in paragraphs (e)(1) through (7) of this section by the compliance date specified in § 63.2233.(1) Each COMS must be installed, operated, and maintained according to Performance Specification 1 at appendix B to part 60 of this chapter.(2) You must conduct a performance evaluation of each COMS according to the requirements in § 63.8(e) and according to Performance Specification 1 at appendix B to part 60 of this chapter.(3) As specified in § 63.8(c)(4)(i), each COMS must complete a minimum of one cycle of sampling and analyzing for each successive 10-second period and one cycle of data recording for each successive 6-minute period.(4) The COMS data must be reduced as specified in §§ 63.8(g)(2) and 63.2270(e).(5) You must document procedures and acceptance criteria for operating and maintaining each COMS according to the requirements in § 63.8(d). At a minimum, the documentation must include a daily calibration drift assessment, a quarterly performance audit, and an annual zero alignment audit of each COMS.(6) You must operate and maintain each COMS according to the requirements of § 63.8(e). You must identify periods the COMS is out of control including any periods that the COMS fails to pass a daily calibration drift assessment, a quarterly performance audit, or an annual zero alignment audit. Any 6-minute period for which the monitoring system is out of control and data are not available for a required calculation constitutes a deviation from the monitoring requirements.(7) You must determine and record all the 6-minute averages (and 24-hour block averages as applicable) collected for periods during which the COMS is not out of control.
Citations to §63.2269(e)(2)
-
(e) You must install, operate, certify and maintain each COMS according to the procedures in paragraphs (e)(1) through (7) of this section by the compliance date specified in § 63.2233.(1) Each COMS must be installed, operated, and maintained according to Performance Specification 1 at appendix B to part 60 of this chapter.(2) You must conduct a performance evaluation of each COMS according to the requirements in § 63.8(e) and according to Performance Specification 1 at appendix B to part 60 of this chapter.(3) As specified in § 63.8(c)(4)(i), each COMS must complete a minimum of one cycle of sampling and analyzing for each successive 10-second period and one cycle of data recording for each successive 6-minute period.(4) The COMS data must be reduced as specified in §§ 63.8(g)(2) and 63.2270(e).(5) You must document procedures and acceptance criteria for operating and maintaining each COMS according to the requirements in § 63.8(d). At a minimum, the documentation must include a daily calibration drift assessment, a quarterly performance audit, and an annual zero alignment audit of each COMS.(6) You must operate and maintain each COMS according to the requirements of § 63.8(e). You must identify periods the COMS is out of control including any periods that the COMS fails to pass a daily calibration drift assessment, a quarterly performance audit, or an annual zero alignment audit. Any 6-minute period for which the monitoring system is out of control and data are not available for a required calculation constitutes a deviation from the monitoring requirements.(7) You must determine and record all the 6-minute averages (and 24-hour block averages as applicable) collected for periods during which the COMS is not out of control.
Citations to §63.2269(e)(3)
-
(e) You must install, operate, certify and maintain each COMS according to the procedures in paragraphs (e)(1) through (7) of this section by the compliance date specified in § 63.2233.(1) Each COMS must be installed, operated, and maintained according to Performance Specification 1 at appendix B to part 60 of this chapter.(2) You must conduct a performance evaluation of each COMS according to the requirements in § 63.8(e) and according to Performance Specification 1 at appendix B to part 60 of this chapter.(3) As specified in § 63.8(c)(4)(i), each COMS must complete a minimum of one cycle of sampling and analyzing for each successive 10-second period and one cycle of data recording for each successive 6-minute period.(4) The COMS data must be reduced as specified in §§ 63.8(g)(2) and 63.2270(e).(5) You must document procedures and acceptance criteria for operating and maintaining each COMS according to the requirements in § 63.8(d). At a minimum, the documentation must include a daily calibration drift assessment, a quarterly performance audit, and an annual zero alignment audit of each COMS.(6) You must operate and maintain each COMS according to the requirements of § 63.8(e). You must identify periods the COMS is out of control including any periods that the COMS fails to pass a daily calibration drift assessment, a quarterly performance audit, or an annual zero alignment audit. Any 6-minute period for which the monitoring system is out of control and data are not available for a required calculation constitutes a deviation from the monitoring requirements.(7) You must determine and record all the 6-minute averages (and 24-hour block averages as applicable) collected for periods during which the COMS is not out of control.
Citations to §63.2269(e)(4)
-
(e) You must install, operate, certify and maintain each COMS according to the procedures in paragraphs (e)(1) through (7) of this section by the compliance date specified in § 63.2233.(1) Each COMS must be installed, operated, and maintained according to Performance Specification 1 at appendix B to part 60 of this chapter.(2) You must conduct a performance evaluation of each COMS according to the requirements in § 63.8(e) and according to Performance Specification 1 at appendix B to part 60 of this chapter.(3) As specified in § 63.8(c)(4)(i), each COMS must complete a minimum of one cycle of sampling and analyzing for each successive 10-second period and one cycle of data recording for each successive 6-minute period.(4) The COMS data must be reduced as specified in §§ 63.8(g)(2) and 63.2270(e).(5) You must document procedures and acceptance criteria for operating and maintaining each COMS according to the requirements in § 63.8(d). At a minimum, the documentation must include a daily calibration drift assessment, a quarterly performance audit, and an annual zero alignment audit of each COMS.(6) You must operate and maintain each COMS according to the requirements of § 63.8(e). You must identify periods the COMS is out of control including any periods that the COMS fails to pass a daily calibration drift assessment, a quarterly performance audit, or an annual zero alignment audit. Any 6-minute period for which the monitoring system is out of control and data are not available for a required calculation constitutes a deviation from the monitoring requirements.(7) You must determine and record all the 6-minute averages (and 24-hour block averages as applicable) collected for periods during which the COMS is not out of control.
Citations to §63.2269(e)(5)
-
(e) You must install, operate, certify and maintain each COMS according to the procedures in paragraphs (e)(1) through (7) of this section by the compliance date specified in § 63.2233.(1) Each COMS must be installed, operated, and maintained according to Performance Specification 1 at appendix B to part 60 of this chapter.(2) You must conduct a performance evaluation of each COMS according to the requirements in § 63.8(e) and according to Performance Specification 1 at appendix B to part 60 of this chapter.(3) As specified in § 63.8(c)(4)(i), each COMS must complete a minimum of one cycle of sampling and analyzing for each successive 10-second period and one cycle of data recording for each successive 6-minute period.(4) The COMS data must be reduced as specified in §§ 63.8(g)(2) and 63.2270(e).(5) You must document procedures and acceptance criteria for operating and maintaining each COMS according to the requirements in § 63.8(d). At a minimum, the documentation must include a daily calibration drift assessment, a quarterly performance audit, and an annual zero alignment audit of each COMS.(6) You must operate and maintain each COMS according to the requirements of § 63.8(e). You must identify periods the COMS is out of control including any periods that the COMS fails to pass a daily calibration drift assessment, a quarterly performance audit, or an annual zero alignment audit. Any 6-minute period for which the monitoring system is out of control and data are not available for a required calculation constitutes a deviation from the monitoring requirements.(7) You must determine and record all the 6-minute averages (and 24-hour block averages as applicable) collected for periods during which the COMS is not out of control.
Citations to §63.2269(e)(6)
-
(e) You must install, operate, certify and maintain each COMS according to the procedures in paragraphs (e)(1) through (7) of this section by the compliance date specified in § 63.2233.(1) Each COMS must be installed, operated, and maintained according to Performance Specification 1 at appendix B to part 60 of this chapter.(2) You must conduct a performance evaluation of each COMS according to the requirements in § 63.8(e) and according to Performance Specification 1 at appendix B to part 60 of this chapter.(3) As specified in § 63.8(c)(4)(i), each COMS must complete a minimum of one cycle of sampling and analyzing for each successive 10-second period and one cycle of data recording for each successive 6-minute period.(4) The COMS data must be reduced as specified in §§ 63.8(g)(2) and 63.2270(e).(5) You must document procedures and acceptance criteria for operating and maintaining each COMS according to the requirements in § 63.8(d). At a minimum, the documentation must include a daily calibration drift assessment, a quarterly performance audit, and an annual zero alignment audit of each COMS.(6) You must operate and maintain each COMS according to the requirements of § 63.8(e). You must identify periods the COMS is out of control including any periods that the COMS fails to pass a daily calibration drift assessment, a quarterly performance audit, or an annual zero alignment audit. Any 6-minute period for which the monitoring system is out of control and data are not available for a required calculation constitutes a deviation from the monitoring requirements.(7) You must determine and record all the 6-minute averages (and 24-hour block averages as applicable) collected for periods during which the COMS is not out of control.
Citations to §63.2269(e)(7)
-
(e) You must install, operate, certify and maintain each COMS according to the procedures in paragraphs (e)(1) through (7) of this section by the compliance date specified in § 63.2233.(1) Each COMS must be installed, operated, and maintained according to Performance Specification 1 at appendix B to part 60 of this chapter.(2) You must conduct a performance evaluation of each COMS according to the requirements in § 63.8(e) and according to Performance Specification 1 at appendix B to part 60 of this chapter.(3) As specified in § 63.8(c)(4)(i), each COMS must complete a minimum of one cycle of sampling and analyzing for each successive 10-second period and one cycle of data recording for each successive 6-minute period.(4) The COMS data must be reduced as specified in §§ 63.8(g)(2) and 63.2270(e).(5) You must document procedures and acceptance criteria for operating and maintaining each COMS according to the requirements in § 63.8(d). At a minimum, the documentation must include a daily calibration drift assessment, a quarterly performance audit, and an annual zero alignment audit of each COMS.(6) You must operate and maintain each COMS according to the requirements of § 63.8(e). You must identify periods the COMS is out of control including any periods that the COMS fails to pass a daily calibration drift assessment, a quarterly performance audit, or an annual zero alignment audit. Any 6-minute period for which the monitoring system is out of control and data are not available for a required calculation constitutes a deviation from the monitoring requirements.(7) You must determine and record all the 6-minute averages (and 24-hour block averages as applicable) collected for periods during which the COMS is not out of control.
Citations to §63.2269(f)(1)
-
(f) If you have an operating requirement that requires the use of a pressure monitoring system, you must meet the requirements in paragraphs (a) and (f)(1) through (6) of this section.(1) Install the pressure sensor(s) in a position that provides a representative measurement of the pressure (e.g., PM scrubber pressure drop).(2) Minimize or eliminate pulsating pressure, vibration, and internal and external corrosion consistent with good engineering practices.(3) Use a pressure sensor with a minimum tolerance of 1.27 centimeters of water or a minimum tolerance of 1 percent of the pressure monitoring system operating range, whichever is less.(4) Perform checks at least once each process operating day to ensure pressure measurements are not obstructed (e.g., check for pressure tap pluggage daily).(5) Conduct a performance evaluation of the pressure monitoring system at the time of each performance test but no less frequently than annually.(6) If at any time the measured pressure exceeds the manufacturer's specified maximum operating pressure range, conduct a performance evaluation of the pressure monitoring system and confirm that the pressure monitoring system continues to meet the performance requirements. Alternatively, install and verify the operation of a new pressure sensor.
Citations to §63.2269(f)(2)
-
(f) If you have an operating requirement that requires the use of a pressure monitoring system, you must meet the requirements in paragraphs (a) and (f)(1) through (6) of this section.(1) Install the pressure sensor(s) in a position that provides a representative measurement of the pressure (e.g., PM scrubber pressure drop).(2) Minimize or eliminate pulsating pressure, vibration, and internal and external corrosion consistent with good engineering practices.(3) Use a pressure sensor with a minimum tolerance of 1.27 centimeters of water or a minimum tolerance of 1 percent of the pressure monitoring system operating range, whichever is less.(4) Perform checks at least once each process operating day to ensure pressure measurements are not obstructed (e.g., check for pressure tap pluggage daily).(5) Conduct a performance evaluation of the pressure monitoring system at the time of each performance test but no less frequently than annually.(6) If at any time the measured pressure exceeds the manufacturer's specified maximum operating pressure range, conduct a performance evaluation of the pressure monitoring system and confirm that the pressure monitoring system continues to meet the performance requirements. Alternatively, install and verify the operation of a new pressure sensor.
Citations to §63.2269(f)(3)
-
(f) If you have an operating requirement that requires the use of a pressure monitoring system, you must meet the requirements in paragraphs (a) and (f)(1) through (6) of this section.(1) Install the pressure sensor(s) in a position that provides a representative measurement of the pressure (e.g., PM scrubber pressure drop).(2) Minimize or eliminate pulsating pressure, vibration, and internal and external corrosion consistent with good engineering practices.(3) Use a pressure sensor with a minimum tolerance of 1.27 centimeters of water or a minimum tolerance of 1 percent of the pressure monitoring system operating range, whichever is less.(4) Perform checks at least once each process operating day to ensure pressure measurements are not obstructed (e.g., check for pressure tap pluggage daily).(5) Conduct a performance evaluation of the pressure monitoring system at the time of each performance test but no less frequently than annually.(6) If at any time the measured pressure exceeds the manufacturer's specified maximum operating pressure range, conduct a performance evaluation of the pressure monitoring system and confirm that the pressure monitoring system continues to meet the performance requirements. Alternatively, install and verify the operation of a new pressure sensor.
Citations to §63.2269(f)(4)
-
(f) If you have an operating requirement that requires the use of a pressure monitoring system, you must meet the requirements in paragraphs (a) and (f)(1) through (6) of this section.(1) Install the pressure sensor(s) in a position that provides a representative measurement of the pressure (e.g., PM scrubber pressure drop).(2) Minimize or eliminate pulsating pressure, vibration, and internal and external corrosion consistent with good engineering practices.(3) Use a pressure sensor with a minimum tolerance of 1.27 centimeters of water or a minimum tolerance of 1 percent of the pressure monitoring system operating range, whichever is less.(4) Perform checks at least once each process operating day to ensure pressure measurements are not obstructed (e.g., check for pressure tap pluggage daily).(5) Conduct a performance evaluation of the pressure monitoring system at the time of each performance test but no less frequently than annually.(6) If at any time the measured pressure exceeds the manufacturer's specified maximum operating pressure range, conduct a performance evaluation of the pressure monitoring system and confirm that the pressure monitoring system continues to meet the performance requirements. Alternatively, install and verify the operation of a new pressure sensor.
Citations to §63.2269(f)(5)
-
(f) If you have an operating requirement that requires the use of a pressure monitoring system, you must meet the requirements in paragraphs (a) and (f)(1) through (6) of this section.(1) Install the pressure sensor(s) in a position that provides a representative measurement of the pressure (e.g., PM scrubber pressure drop).(2) Minimize or eliminate pulsating pressure, vibration, and internal and external corrosion consistent with good engineering practices.(3) Use a pressure sensor with a minimum tolerance of 1.27 centimeters of water or a minimum tolerance of 1 percent of the pressure monitoring system operating range, whichever is less.(4) Perform checks at least once each process operating day to ensure pressure measurements are not obstructed (e.g., check for pressure tap pluggage daily).(5) Conduct a performance evaluation of the pressure monitoring system at the time of each performance test but no less frequently than annually.(6) If at any time the measured pressure exceeds the manufacturer's specified maximum operating pressure range, conduct a performance evaluation of the pressure monitoring system and confirm that the pressure monitoring system continues to meet the performance requirements. Alternatively, install and verify the operation of a new pressure sensor.
Citations to §63.2269(f)(6)
-
(f) If you have an operating requirement that requires the use of a pressure monitoring system, you must meet the requirements in paragraphs (a) and (f)(1) through (6) of this section.(1) Install the pressure sensor(s) in a position that provides a representative measurement of the pressure (e.g., PM scrubber pressure drop).(2) Minimize or eliminate pulsating pressure, vibration, and internal and external corrosion consistent with good engineering practices.(3) Use a pressure sensor with a minimum tolerance of 1.27 centimeters of water or a minimum tolerance of 1 percent of the pressure monitoring system operating range, whichever is less.(4) Perform checks at least once each process operating day to ensure pressure measurements are not obstructed (e.g., check for pressure tap pluggage daily).(5) Conduct a performance evaluation of the pressure monitoring system at the time of each performance test but no less frequently than annually.(6) If at any time the measured pressure exceeds the manufacturer's specified maximum operating pressure range, conduct a performance evaluation of the pressure monitoring system and confirm that the pressure monitoring system continues to meet the performance requirements. Alternatively, install and verify the operation of a new pressure sensor.
Citations to §63.2269(g)(1)
-
(g) If you have an operating limit that requires a pH monitoring system, you must meet the requirements in paragraphs (a) and (g)(1) through (4) of this section.(1) Install the pH sensor in a position that provides a representative measurement of scrubber effluent pH.(3) Clean the pH probe at least once each process operating day. Maintain on-site documentation that your calibration frequency is sufficient to maintain the specified accuracy of your device.(4) Conduct a performance evaluation (including a two-point calibration with one of the two buffer solutions having a pH within 1 of the pH of the operating limit) of the pH monitoring system at the time of each performance test but no less frequently than annually.
Citations to §63.2269(g)(2)
-
(g) If you have an operating limit that requires a pH monitoring system, you must meet the requirements in paragraphs (a) and (g)(1) through (4) of this section.(1) Install the pH sensor in a position that provides a representative measurement of scrubber effluent pH.(3) Clean the pH probe at least once each process operating day. Maintain on-site documentation that your calibration frequency is sufficient to maintain the specified accuracy of your device.(4) Conduct a performance evaluation (including a two-point calibration with one of the two buffer solutions having a pH within 1 of the pH of the operating limit) of the pH monitoring system at the time of each performance test but no less frequently than annually.
Citations to §63.2269(g)(3)
-
(g) If you have an operating limit that requires a pH monitoring system, you must meet the requirements in paragraphs (a) and (g)(1) through (4) of this section.(1) Install the pH sensor in a position that provides a representative measurement of scrubber effluent pH.(3) Clean the pH probe at least once each process operating day. Maintain on-site documentation that your calibration frequency is sufficient to maintain the specified accuracy of your device.(4) Conduct a performance evaluation (including a two-point calibration with one of the two buffer solutions having a pH within 1 of the pH of the operating limit) of the pH monitoring system at the time of each performance test but no less frequently than annually.
Citations to §63.2269(g)(4)
-
(g) If you have an operating limit that requires a pH monitoring system, you must meet the requirements in paragraphs (a) and (g)(1) through (4) of this section.(1) Install the pH sensor in a position that provides a representative measurement of scrubber effluent pH.(3) Clean the pH probe at least once each process operating day. Maintain on-site documentation that your calibration frequency is sufficient to maintain the specified accuracy of your device.(4) Conduct a performance evaluation (including a two-point calibration with one of the two buffer solutions having a pH within 1 of the pH of the operating limit) of the pH monitoring system at the time of each performance test but no less frequently than annually.
Citations to §63.2269(h)(1)
-
(h) If you have an operating limit that requires the use of a flow measurement device, you must meet the requirements in paragraphs (h)(1) through (4) of this section.(1) Locate the flow sensor and other necessary equipment in a position that provides a representative flow.(i) If you have an operating requirement that requires a secondary electric power monitoring system, you must meet the requirements in paragraphs (a) and (i)(1) and (2) of this section.(2) Conduct a performance evaluation of the electric power monitoring at the time of each performance test but no less frequently than annually.
Citations to §63.2269(h)(2)
-
(h) If you have an operating limit that requires the use of a flow measurement device, you must meet the requirements in paragraphs (h)(1) through (4) of this section.(1) Locate the flow sensor and other necessary equipment in a position that provides a representative flow.(i) If you have an operating requirement that requires a secondary electric power monitoring system, you must meet the requirements in paragraphs (a) and (i)(1) and (2) of this section.(2) Conduct a performance evaluation of the electric power monitoring at the time of each performance test but no less frequently than annually.
Citations to §63.2269(h)(3)
-
(h) If you have an operating limit that requires the use of a flow measurement device, you must meet the requirements in paragraphs (h)(1) through (4) of this section.(1) Locate the flow sensor and other necessary equipment in a position that provides a representative flow.(i) If you have an operating requirement that requires a secondary electric power monitoring system, you must meet the requirements in paragraphs (a) and (i)(1) and (2) of this section.(2) Conduct a performance evaluation of the electric power monitoring at the time of each performance test but no less frequently than annually.
Citations to §63.2269(h)(4)
-
(h) If you have an operating limit that requires the use of a flow measurement device, you must meet the requirements in paragraphs (h)(1) through (4) of this section.(1) Locate the flow sensor and other necessary equipment in a position that provides a representative flow.(i) If you have an operating requirement that requires a secondary electric power monitoring system, you must meet the requirements in paragraphs (a) and (i)(1) and (2) of this section.(2) Conduct a performance evaluation of the electric power monitoring at the time of each performance test but no less frequently than annually.
Citations to §63.2269(k)
-
(d) The following combustion unit tune-up and bypass stack monitoring requirements must be conducted for all direct-fired dryers (including direct wood-fired PCWP dryers, direct natural gas-fired PCWP dryers, and direct-fired lumber kilns) by the dates specified in § 63.2233(e) and table 3 to this subpart. You must conduct an annual tune-up of each combustion unit used to directly-fire the PCWP dryer or lumber kiln following the procedures in § 63.2271(c) as specified in paragraphs (d)(1) through (3) of this section. You must monitor usage of combustion unit bypass stacks (defined in § 63.2292) following the procedures specified in § 63.2269(k) by the compliance date specified in § 63.2233(e).(1) The initial tune-up must be completed by the compliance date specified in § 63.2233(e). After the initial tune-up, each annual tune-up is required to be completed no more than 13 months after the previous tune-up.(2) If a combustion unit that direct-fires a PCWP dryer or lumber kiln is not operating on the required date for a tune-up, the tune-up must be conducted within 30 calendar days of startup of the combustion unit for the purpose of direct-firing a PCWP dryer or lumber kiln.(3) For combustion units with tune-up requirements in this subpart, you may use documentation (required in § 63.7550(c)(1)) of the tune-up conducted according to §§ 63.7515(d) and 63.7540(a)(10), in place of the annual combustion unit tune-up requirements in this paragraph (d) and § 63.2271(c), provided the documentation required in § 63.7550(c)(1) is provided according to the schedule in paragraphs (d)(1) and (2) of this section.
Citations to §63.2269(m)
-
(i) Operate the lumber kiln with a maximum dry bulb temperature limit of no more than 210 °F for batch indirect fired (IF) kilns, 235 °F for batch direct-fired (DF) kilns, 245 °F for continuous IF kilns, or 245 °F for continuous DF kilns. You must continuously monitor and record the dry bulb temperature during the kiln drying cycle according to § 63.2269(m) and maintain the batch cycle average dry bulb temperature (for batch kilns) or daily block average dry bulb temperature (for continuous kilns) below the maximum limit specified in this paragraph (e)(3)(i) according to § 63.2270(h)(1).
-
(1) You must continuously monitor and record the dry bulb temperature during the kiln drying cycle and record the dry bulb temperature at least once every 15 minutes as specified in § 63.2269(m). The readings from multiple dry bulb temperature monitors positioned to determine the temperature of the heated air that exits the lumber may be averaged together to determine the kiln-wide, dry bulb temperature.(i) For batch kilns, calculate the average from the recorded readings during each batch cycle, and maintain the batch cycle average dry bulb temperature at or below the maximum temperature limits specified in either § 63.2241(e)(3)(i) or (ii), whichever applies.(ii) For continuous dry kilns, calculate the daily block average from the recorded readings and maintain the daily block average dry bulb temperature at or below the maximum temperature limits specified in either § 63.2241(e)(3)(i) or (ii), whichever applies.
Citations to §63.2269(n)
-
(B) Operate the kiln to dry to a semiannual average lumber moisture content (weight percent, dry basis) at or above the minimum limit of moisture content considered to be over-dried lumber as specified in paragraph (e)(4) of this section and table 11 of this subpart. Lumber moisture must be monitored and recorded according to § 63.2269(n). The semiannual average must be determined according to § 63.2270(i).
-
(1) Using the lumber moisture content measurement data collected according to § 63.2269(n), calculate and record the semiannual average kiln-dried lumber moisture content for lumber with a given moisture specification produced at the facility.
Citations to §63.2269(o)
-
(B) The site-specific plan must include a method for monitoring lumber moisture content (weight percent, dry basis); specify the location of such monitoring within the lumber manufacturing process (for example, at the kiln unloading track, in lumber storage, or at the planer); specify the minimum kiln-dried lumber moisture content limit based on the lumber moisture specifications produced at the facility based on paragraph (e)(4) of this section and table 11 of subpart DDDD; and adhere to the minimum data and lumber moisture content averaging requirements in §§ 63.2269(o) and 63.2270(j).