(1) Clearly identify the leaking equipment. A weatherproof and readily visible identification, marked with the equipment identification number, must be attached to the leaking equipment. The identification on the equipment may be removed after it is repaired.
(2) A first attempt at repair must be made no later than 5 calendar days after the leak is detected.
(3) The piece of equipment must be repaired as soon as practicable, but no later than 15 calendar days after the leak is detected, except as provided in paragraph (a)(6)(viii) of this section.
(4) The leak is repaired when instrument re-monitoring of the equipment does not detect a leak.
(5) It is a deviation to fail to take action to repair the leaks within the specified time. If action is taken to repair the leaks within the specified time, failure of that action to successfully repair the leak is not a deviation. However, if the repairs are unsuccessful, a leak is detected and you must take further action as required by applicable provisions of this paragraph (a)(6).
(1) You determine that the pump, valve, or connector is unsafe to monitor because monitoring personnel would be exposed to an immediate danger as a consequence of complying with paragraph (a)(6)(i) of this section; and
(2) You have a written plan that requires monitoring of the pump, valve, or connector as frequently as practical during safe-to-monitor times, but not more frequently than the annual leak detection monitoring.
(1) You determine that the valve cannot be monitored without elevating the monitoring personnel more than 2 meters above a support surface or it is not accessible at anytime in a safe manner;
(2) The CMPU within which the valve is located is an existing source or you designate less than 3 percent of the total number of valves in a new source as difficult-to-monitor; and
(3) You follow a written plan that requires monitoring of the valve as frequently as practical, but not more frequently than the annual leak detection monitoring.
(1) You determine that repair personnel would be exposed to an immediate danger as a consequence of complying with paragraph (a)(6)(i) of this section; and
(2) The connector will be repaired before the end of the next scheduled CMPU shutdown.
Notes, amendments, and revision history
Amendments
[74 FR 56041, Oct. 29, 2009, as amended at 77 FR 75756, Dec. 21, 2012; 91 FR 16523, Apr. 1, 2026]
Source
Source: 74 FR 56041, Oct. 29, 2009, unless otherwise noted.
Authority
Authority: 42 U.S.C. 7401 et seq.
Source
Source: 57 FR 61992, Dec. 29, 1992, unless otherwise noted.
Amendments
[74 FR 56041, Oct. 29, 2009, as amended at 77 FR 75756, Dec. 21, 2012; 91 FR 16523, Apr. 1, 2026]