§63.11415. What are my compliance dates?
40 C.F.R. § 63.11415
If you own or operate an existing slabstock flexible polyurethane foam production affected source, you must achieve compliance with the applicable provisions in this subpart by July 16, 2008.
If you own or operate an existing molded flexible polyurethane foam affected source, an existing rebond foam production affected sources, or an existing flexible polyurethane foam fabrication affected source, you must achieve compliance with the applicable provisions in this subpart by July 16, 2007.
If you startup a new affected source on or before July 16, 2007, you must achieve compliance with the applicable provisions in this subpart not later than July 16, 2007.
If you startup a new affected source after July 16, 2007, you must achieve compliance with the provisions in this subpart upon startup of your affected source.
Notes, amendments, and revision history
Source
Source: 72 FR 38910, July 16, 2007, unless otherwise noted.
Authority
Authority: 42 U.S.C. 7401 et seq.
Source
Source: 57 FR 61992, Dec. 29, 1992, unless otherwise noted.