§62.2354. Compliance schedules.
40 C.F.R. § 62.2354
The State of Florida has provided that the individual source compliance schedules would be developed and submitted by the affected sources to the State following plan adoption; and that the increments of progress pursuant to 40 CFR 60.21(h) would be specified at that time; this is an acceptable procedure pursuant to 40 CFR 60.24(e)(2). However, the State must submit these schedules to EPA for approval; and these schedules must meet the public hearing requirements of 40 CFR 60.23 or ones deemed equivalent by the Administrator pursuant to 40 CFR 60.23(g).
Notes, amendments, and revision history
Amendments
[53 FR 30053, Aug. 10, 1988]
Authority
Authority: Secs. 110(a) and 111(d), Clean Air Act (42 U.S.C. 7410(a) and 7411(d)).
Source
Source: 48 FR 31402, July 8, 1983, unless otherwise noted.
Authority
Authority: 42 U.S.C. 7401 et seq.
Source
Source: 43 FR 51393, Nov. 3, 1978, unless otherwise noted.
Amendments
[53 FR 30053, Aug. 10, 1988]