§62.15040. What are the requirements for meeting increments of progress and achieving final compliance?
40 C.F.R. § 62.15040
Class I units. If you plan to achieve compliance more than 1 year following the effective date of this subpart and a permit modification is not required, or more than 1 year following the date of issuance of a revised construction or operation permit if a permit modification is required, you must meet five increments of progress:
Submit a final control plan.
Submit a notification of retrofit contract award.
Initiate onsite construction.
Complete onsite construction.
Achieve final compliance.
Class II units. If you plan to achieve compliance more than 1 year following the effective date of this subpart and a permit modification is not required, or more than 1 year following the date of issuance of a revised construction or operation permit if a permit modification is required, you must meet two increments of progress:
Submit a final control plan.
Achieve final compliance.
Notes, amendments, and revision history
Source
Source: 68 FR 5158, Jan. 31, 2003, unless otherwise noted.
Authority
Authority: 42 U.S.C. 7401 et seq.
Source
Source: 43 FR 51393, Nov. 3, 1978, unless otherwise noted.