§61.145. Standard for demolition and renovation. — Inbound Citations

40 C.F.R. § 61.145

Cited by 18 regulations in release Current.

Citations to 40 U.S.C. § 61.145 as a whole

  • The provisions of this subpart are applicable to those sources specified in §§ 61.142 through 61.151, 61.154, and 61.155.
  • Each owner or operator of any source covered under the provisions of §§ 61.144, 61.145, 61.146, and 61.147 shall comply with the following provisions:
  • (a) Any new source to which this subpart applies (with the exception of sources subject to §§ 61.143, 61.145, 61.146, and 61.148), which has an initial startup date preceding the effective date of this revision, shall provide the following information to the Administrator postmarked or delivered within 90 days of the effective date. In the case of a new source that does not have an initial startup date preceding the effective date, the information shall be provided, postmarked or delivered, within 90 days of the initial startup date. Any owner or operator of an existing source shall provide the following information to the Administrator within 90 days of the effective date of this subpart unless the owner or operator of the existing source has previously provided this information to the Administrator. Any changes in the information provided by any existing source shall be provided to the Administrator, postmarked or delivered, within 30 days after the change.
    (1) A description of the emission control equipment used for each process; and
    (i) If the fabric device uses a woven fabric, the airflow permeability in m 3/min/m 2 and; if the fabric is synthetic, whether the fill yarn is spun or not spun; and
    (ii) If the fabric filter device uses a felted fabric, the density in g/m 2, the minimum thickness in inches, and the airflow permeability in m 3/min/m 2.
    (2) If a fabric filter device is used to control emissions,
    (i) The airflow permeability in m 3/min/m 2 (ft 3/min/ft 2) if the fabric filter device uses a woven fabric, and, if the fabric is synthetic, whether the fill yarn is spun or not spun; and
    (ii) If the fabric filter device uses a felted fabric, the density in g/m 2 (oz/yd 2), the minimum thickness in millimeters (inches), and the airflow permeability in m 3/min/m 2 (ft 3/min/ft 2).
    (3) If a HEPA filter is used to control emissions, the certified efficiency.
    (4) For sources subject to §§ 61.149 and 61.150:
    (i) A brief description of each process that generates asbestos-containing waste material; and
    (ii) The average volume of asbestos-containing waste material disposed of, measured in m 3/day (yd 3/day); and
    (iii) The emission control methods used in all stages of waste disposal; and
    (iv) The type of disposal site or incineration site used for ultimate disposal, the name of the site operator, and the name and location of the disposal site.
    (5) For sources subject to §§ 61.151 and 61.154:
    (i) A brief description of the site; and
  • In addition to this subpart, the regulations referenced in Table 1 also apply to asbestos and may be applicable to those sources specified in §§ 61.142 through 61.151, 61.154, and 61.155 of this subpart. These cross-references are presented for the reader's information and to promote compliance with the cited regulations.
  • (ii) All sources and source categories that would be required to obtain a permit solely because they are subject to part 61, subpart M—National Emission Standard for Hazardous Air Pollutants for Asbestos, § 61.145, Standard for Demolition and Renovation.
  • (ii) All sources and source categories that would be required to obtain a permit solely because they are subject to 40 CFR part 61, subpart M—National Emission Standard for Hazardous Air Pollutants for Asbestos, § 61.145, Standard for Demolition and Renovation.

Citations to §61.145(b)(4)(i)

  • (2) In a facility being demolished, only the notification requirements of paragraphs (b)(1), (2), (3)(i) and (iv), and (4)(i) through (vii) and (4)(ix) and (xvi) of this section apply, if the combined amount of RACM is
    (i) Less than 80 linear meters (260 linear feet) on pipes and less than 15 square meters (160 square feet) on other facility components, and
    (ii) Less than one cubic meter (35 cubic feet) off facility components where the length or area could not be measured previously or there is no asbestos.

Citations to §61.145(b)(4)(ii)

  • (2) In a facility being demolished, only the notification requirements of paragraphs (b)(1), (2), (3)(i) and (iv), and (4)(i) through (vii) and (4)(ix) and (xvi) of this section apply, if the combined amount of RACM is
    (i) Less than 80 linear meters (260 linear feet) on pipes and less than 15 square meters (160 square feet) on other facility components, and
    (ii) Less than one cubic meter (35 cubic feet) off facility components where the length or area could not be measured previously or there is no asbestos.

Citations to §61.145(b)(4)(iii)

  • (2) In a facility being demolished, only the notification requirements of paragraphs (b)(1), (2), (3)(i) and (iv), and (4)(i) through (vii) and (4)(ix) and (xvi) of this section apply, if the combined amount of RACM is
    (i) Less than 80 linear meters (260 linear feet) on pipes and less than 15 square meters (160 square feet) on other facility components, and
    (ii) Less than one cubic meter (35 cubic feet) off facility components where the length or area could not be measured previously or there is no asbestos.

Citations to §61.145(b)(4)(iv)

  • (2) In a facility being demolished, only the notification requirements of paragraphs (b)(1), (2), (3)(i) and (iv), and (4)(i) through (vii) and (4)(ix) and (xvi) of this section apply, if the combined amount of RACM is
    (i) Less than 80 linear meters (260 linear feet) on pipes and less than 15 square meters (160 square feet) on other facility components, and
    (ii) Less than one cubic meter (35 cubic feet) off facility components where the length or area could not be measured previously or there is no asbestos.

Citations to §61.145(b)(4)(v)

  • (2) In a facility being demolished, only the notification requirements of paragraphs (b)(1), (2), (3)(i) and (iv), and (4)(i) through (vii) and (4)(ix) and (xvi) of this section apply, if the combined amount of RACM is
    (i) Less than 80 linear meters (260 linear feet) on pipes and less than 15 square meters (160 square feet) on other facility components, and
    (ii) Less than one cubic meter (35 cubic feet) off facility components where the length or area could not be measured previously or there is no asbestos.

Citations to §61.145(b)(4)(vi)

  • (2) In a facility being demolished, only the notification requirements of paragraphs (b)(1), (2), (3)(i) and (iv), and (4)(i) through (vii) and (4)(ix) and (xvi) of this section apply, if the combined amount of RACM is
    (i) Less than 80 linear meters (260 linear feet) on pipes and less than 15 square meters (160 square feet) on other facility components, and
    (ii) Less than one cubic meter (35 cubic feet) off facility components where the length or area could not be measured previously or there is no asbestos.

Citations to §61.145(b)(4)(vii)

  • (2) In a facility being demolished, only the notification requirements of paragraphs (b)(1), (2), (3)(i) and (iv), and (4)(i) through (vii) and (4)(ix) and (xvi) of this section apply, if the combined amount of RACM is
    (i) Less than 80 linear meters (260 linear feet) on pipes and less than 15 square meters (160 square feet) on other facility components, and
    (ii) Less than one cubic meter (35 cubic feet) off facility components where the length or area could not be measured previously or there is no asbestos.

Citations to §61.145(c)(1)

  • (3) For facilities demolished where the RACM is not removed prior to demolition according to §§ 61.145(c)(1) (i), (ii), (iii), and (iv) or for facilities demolished according to § 61.145(c)(9), adequately wet asbestos-containing waste material at all times after demolition and keep wet during handling and loading for transport to a disposal site. Asbestos-containing waste materials covered by this paragraph do not have to be sealed in leak-tight containers or wrapping but may be transported and disposed of in bulk.

Citations to §61.145(c)(3)(i)(B)(1)

  • (1) Use fabric filter collection devices, except as noted in paragraph (b) of this section, doing all of the following:
    (i) Ensuring that the airflow permeability, as determined by ASTM Method D737-75, does not exceed 9 m 3/min/m 2 (30 ft 3/min/ft 2) for woven fabrics or 11 3/min/m 2(35 ft 3/min/ft 2) for felted fabrics, except that 12 m 3/min/m 2 (40 ft 3min/ft 2) for woven and 14 m 3/min/m 2 (45 ft 3min/ft 2) for felted fabrics is allowed for filtering air from asbestos ore dryers; and
    (ii) Ensuring that felted fabric weighs at least 475 grams per square meter (14 ounces per square yard) and is at least 1.6 millimeters (one-sixteenth inch) thick throughout; and
    (2) Bypass devices may be used only during upset or emergency conditions and then only for so long as it takes to shut down the operation generating the particulate asbestos material.
    (3) For fabric filter collection devices installed after January 10, 1989, provide for easy inspection for faulty bags.

Citations to §61.145(c)(4)(ii)

  • (1) Use fabric filter collection devices, except as noted in paragraph (b) of this section, doing all of the following:
    (i) Ensuring that the airflow permeability, as determined by ASTM Method D737-75, does not exceed 9 m 3/min/m 2 (30 ft 3/min/ft 2) for woven fabrics or 11 3/min/m 2(35 ft 3/min/ft 2) for felted fabrics, except that 12 m 3/min/m 2 (40 ft 3min/ft 2) for woven and 14 m 3/min/m 2 (45 ft 3min/ft 2) for felted fabrics is allowed for filtering air from asbestos ore dryers; and
    (ii) Ensuring that felted fabric weighs at least 475 grams per square meter (14 ounces per square yard) and is at least 1.6 millimeters (one-sixteenth inch) thick throughout; and
    (2) Bypass devices may be used only during upset or emergency conditions and then only for so long as it takes to shut down the operation generating the particulate asbestos material.
    (3) For fabric filter collection devices installed after January 10, 1989, provide for easy inspection for faulty bags.

Citations to §61.145(c)(9)

  • (3) For facilities demolished where the RACM is not removed prior to demolition according to §§ 61.145(c)(1) (i), (ii), (iii), and (iv) or for facilities demolished according to § 61.145(c)(9), adequately wet asbestos-containing waste material at all times after demolition and keep wet during handling and loading for transport to a disposal site. Asbestos-containing waste materials covered by this paragraph do not have to be sealed in leak-tight containers or wrapping but may be transported and disposed of in bulk.

Citations to §61.145(c)(11)(i)

  • (1) Use fabric filter collection devices, except as noted in paragraph (b) of this section, doing all of the following:
    (i) Ensuring that the airflow permeability, as determined by ASTM Method D737-75, does not exceed 9 m 3/min/m 2 (30 ft 3/min/ft 2) for woven fabrics or 11 3/min/m 2(35 ft 3/min/ft 2) for felted fabrics, except that 12 m 3/min/m 2 (40 ft 3min/ft 2) for woven and 14 m 3/min/m 2 (45 ft 3min/ft 2) for felted fabrics is allowed for filtering air from asbestos ore dryers; and
    (ii) Ensuring that felted fabric weighs at least 475 grams per square meter (14 ounces per square yard) and is at least 1.6 millimeters (one-sixteenth inch) thick throughout; and
    (2) Bypass devices may be used only during upset or emergency conditions and then only for so long as it takes to shut down the operation generating the particulate asbestos material.
    (3) For fabric filter collection devices installed after January 10, 1989, provide for easy inspection for faulty bags.