§60.6330. What are my requirements for meeting increments of progress and achieving final compliance?
40 C.F.R. § 60.6330
If you plan to achieve compliance more than 1 year but less than 3 years following the effective date of state plan approval and a permit modification is not required, or more than 1 year but less than 3 years following the date of issuance of a revised construction or operation permit if a permit modification is required, you must meet five increments of progress:
Submit a final control plan.
Submit a notification of retrofit contract award.
Initiate onsite construction.
Complete onsite construction.
Achieve final compliance.