§60.5420a. What are my notification, reporting, and recordkeeping requirements?
40 C.F.R. § 60.5420a
(1) The latitude and longitude of the well in decimal degrees to an accuracy and precision of five (5) decimals of a degree using North American Datum of 1983; the United States Well Number; the date and time of the onset of flowback following hydraulic fracturing or refracturing; the date and time that the well was shut in and the flowback equipment was permanently disconnected, or the startup of production; the duration of flowback; duration of recovery and disposition of recovery (i.e., routed to the gas flow line or collection system, re-injected into the well or another well, used as an onsite fuel source, or used for another useful purpose that a purchased fuel or raw material would serve); duration of combustion; duration of venting; and specific reasons for venting in lieu of capture or combustion. The duration must be specified in hours.
(2) If applicable, records that the conditions of § 60.5375a(a)(1)(iii)(A) are no longer met and that the well completion operation has been stopped and a separator installed. The records shall include the date and time the well completion operation was stopped and the date and time the separator was installed.
(3) A record of the claim signed by the certifying official that no liquids collection is at the well site. The claim must include a certification by a certifying official of truth, accuracy, and completeness. This certification shall state that, based on information and belief formed after reasonable inquiry, the statements and information in the document are true, accurate, and complete.
(1) Records that the pilot flame is present at all times of operation.
(2) Records that the device was operated with no visible emissions except for periods not to exceed a total of 1 minute during any 15-minute period.
(3) Records of the maintenance and repair log.
(4) Records of the visible emissions test following return to operation from a maintenance or repair activity, including the date of the visible emissions test, the length of the test, and the amount of time for which visible emissions were present.
(5) Records of the manufacturer's written operating instructions, procedures, and maintenance schedule to ensure good air pollution control practices for minimizing emissions.
(1) Location of each fugitive emission identified.
(2) Type of fugitive emissions component, including designation as difficult-to-monitor or unsafe-to-monitor, if applicable.
(3) If Method 21 of appendix A-7 of this part is used for detection, record the component ID and instrument reading.
(4) For each repair that cannot be made during the monitoring survey when the fugitive emissions are initially found, a digital photograph or video must be taken of that component or the component must be tagged for identification purposes. The digital photograph must include the date that the photograph was taken and must clearly identify the component by location within the site (e.g., the latitude and longitude of the component or by other descriptive landmarks visible in the picture). The digital photograph or identification (e.g., tag) may be removed after the repair is completed, including verification of repair with the resurvey.
(5) The date of first attempt at repair of the fugitive emissions component(s).
(6) The date of successful repair of the fugitive emissions component, including the resurvey to verify repair and instrument used for the resurvey.
(7) Identification of each fugitive emission component placed on delay of repair and explanation for each delay of repair
(8) For each fugitive emission component placed on delay of repair for reason of replacement component unavailability, the operator must document: the date the component was added to the delay of repair list, the date the replacement fugitive component or part thereof was ordered, the anticipated component delivery date (including any estimated shipment or delivery date provided by the vendor), and the actual arrival date of the component.
(9) Date of planned shutdowns that occur while there are any components that have been placed on delay of repair.
Notes, amendments, and revision history
Amendments
[85 FR 57449, Sept. 15, 2020, as amended at 89 FR 17041, Mar. 8, 2024]
Source
Source: 81 FR 35898, June 3, 2016, unless otherwise noted.
Authority
Authority: 42 U.S.C. 7401 et seq.
Source
Source: 36 FR 24877, Dec. 23, 1971, unless otherwise noted.
Amendments
[85 FR 57449, Sept. 15, 2020, as amended at 89 FR 17041, Mar. 8, 2024]