§60.5379c. What are my requirements for meeting increments of progress and achieving final compliance?

40 C.F.R. § 60.5379c

You must meet one increment of progress as specified in paragraph (a) of this section and you must submit the Notification of Compliance report as specified in paragraph (b) of this section.
(a)
Submit a final compliance control plan on or before 28 months after the state plan submittal deadline specified in § 60.5362c(c).
(b)
Submit a Notification of Compliance report on or before 60 days after the state plan compliance date as specified in § 60.5420c.
Notes, amendments, and revision history

Source

Source: 89 FR 17140, Mar. 8, 2024, unless otherwise noted.

Authority

Authority: 42 U.S.C. 7401 et seq.

Source

Source: 36 FR 24877, Dec. 23, 1971, unless otherwise noted.

§60.5380c. What if I do not meet the final control plan increment of progress compliance date?

40 C.F.R. § 60.5380c

If you fail to meet the final compliance control plan increment of progress report compliance date, you must submit a notification to the Administrator postmarked within 10 business days after the required submittal date for that increment of progress. You must inform the Administrator that you did not meet the increment, and you must continue to submit reports each subsequent calendar month until the increment of progress is met.
Notes, amendments, and revision history

Source

Source: 89 FR 17140, Mar. 8, 2024, unless otherwise noted.

Authority

Authority: 42 U.S.C. 7401 et seq.

Source

Source: 36 FR 24877, Dec. 23, 1971, unless otherwise noted.

§60.5381c. How do I comply with the increment of progress for submittal of a final compliance control plan?

40 C.F.R. § 60.5381c

For your final compliance control plan increment of progress report, you must satisfy the requirements specified in paragraphs (a) through (c) of this section.
(a)
Your final control plan must include the information specified paragraphs (a)(1) and (2) of this section.
(1)
A description of the designated facilities covered under your plan.
(2)
The emissions control methods that you plan to implement for each designated facility covered under your plan.
(b)
A company is allowed to submit one plan that covers all of the company's designated facilities in a state in lieu of submitting a plan for each designated facility.
(c)
Maintain an onsite copy of the final control plan.
Notes, amendments, and revision history

Source

Source: 89 FR 17140, Mar. 8, 2024, unless otherwise noted.

Authority

Authority: 42 U.S.C. 7401 et seq.

Source

Source: 36 FR 24877, Dec. 23, 1971, unless otherwise noted.