§60.2705. By what date must I conduct the initial performance test?
40 C.F.R. § 60.2705
The initial performance test must be conducted no later than 180 days after your final compliance date. Your final compliance date is specified in table 1 of this subpart.
If you commence or recommence combusting a solid waste at an existing combustion unit at any commercial or industrial facility and you conducted a test consistent with the provisions of this subpart while combusting the given solid waste within the 6 months preceding the reintroduction of that solid waste in the combustion chamber, you do not need to retest until 6 months from the date you reintroduce that solid waste.
If you commence or recommence combusting a solid waste at an existing combustion unit at any commercial or industrial facility and you have not conducted a performance test consistent with the provisions of this subpart while combusting the given solid waste within the 6 months preceding the reintroduction of that solid waste in the combustion chamber, you must conduct a performance test within 60 days from the date you reintroduce solid waste.
Notes, amendments, and revision history
Source
Source: 84 FR 15884, Apr. 16, 2019, unless otherwise noted.
Authority
Authority: 42 U.S.C. 7401 et seq.
Source
Source: 36 FR 24877, Dec. 23, 1971, unless otherwise noted.