§60.113c. Testing, monitoring, and inspection procedures.
40 C.F.R. § 60.113c
(1) Method 1 or 1A of appendix A-1 to this part, as appropriate, for selection of the sampling sites. Sampling sites must be located at the inlet of the first control device and at the outlet of the final control device to determine compliance with a control device percent reduction requirement.
(2) Method 2, 2A, 2C, or 2D of appendix A-1 to this part, as appropriate to determine the gas volumetric flow rate.
(3) Method 25A of appendix A-7 to this part. Use propane as the calibration gas. You must use Method 4 of appendix A-3 to this part to convert the Method 25A of appendix A-7 results to a dry basis.
(1) You must compute the mass rate of TOC using the following equations:
(2) You must calculate the percent reduction in TOC as follows:
(1) If you use an enclosed combustion device, a boiler, or a process heater other than those specified in paragraph (c)(1)(iii) of this section to control emissions, you must set a minimum firebox temperature limit during the performance test. You must continuously monitor the firebox temperature with a temperature monitoring device installed in the firebox or in the ductwork immediately downstream from the firebox in a position before any substantial heat exchange occurs and equipped with a continuous recorder that records a reading at least once every 15 minutes. The monitoring device must have a minimum accuracy of ±1 percent of the temperature being monitored in degrees Celsius, or ±2.5 degrees Celsius, whichever value is greater.
(2) If you use a catalytic incinerator other than those specified in paragraph (c)(1)(iii) of this section to control emissions, you must set a minimum temperature limit on the temperature at the inlet of the catalyst bed and a minimum temperature limit on the temperature difference between the catalyst bed outlet and inlet. You must continuously monitor the temperatures with a temperature monitoring device equipped with a continuous recorder that records a reading at least once every 15 minutes. The device must be capable of monitoring temperature at two locations and have a minimum accuracy of ±1 percent of the temperature being monitored in degrees Celsius, or ±2.5 degrees Celsius, whichever value is greater. You must install one temperature sensor in the vent stream at the nearest feasible point to the catalyst bed inlet, and you must install a second temperature sensor in the vent stream at the nearest feasible point to the catalyst bed outlet. You must install the temperature sensor at a location representative of the firebox temperature.
(3) If you use a control device other than a flare or other than a device listed in paragraphs (c)(1)(ii)(E)(1), (c)(1)(ii)(E)(2), (c)(1)(ii)(E)(5), or (c)(1)(iii) to control emissions, you must submit the operating parameters you plan to monitor in the performance test notice you provide to the Administrator pursuant to § 60.8(d).
(4) Using the continuous monitoring system (CMS) data, you must calculate the hourly average of each operating parameter. You must demonstrate compliance by maintaining the operating parameter at or above the minimum operating parameter limit on a 3-hour rolling average basis. For each hour, calculate the hourly value of the operating parameter from your CMS. Average the three most recent hours of data to determine the 3-hour average. Determine the 3-hour rolling average by recalculating the 3-hour average each hour. You must not include periods of data collected during monitoring system breakdowns, repairs, maintenance periods, instrument adjustments, or checks to maintain precision and accuracy in the operating parameter averages.
(5) For enclosed combustion devices for which you elect to comply with the flare requirements in § 60.112c(d)(5), you must comply with the monitoring provisions in paragraph (c)(1)(iv) of this section instead of paragraphs (c)(1)(ii)(E)(1) through (4) of this section.
(1) Determine the unobstructed cross-sectional area of the flare tip, in units of square feet, as specified in 40 CFR 63.670(k)(1).
(2) Determine the maximum flow rate, in units of cubic feet per second, based on the maximum cumulative loading rate for a 15-minute block period considering maximum filling rates for all storage vessel affected facilities controlled by the flare and, if applicable, considering the maximum release pressure of any other vapors directed to the flare.
(3) Calculate the maximum flare tip velocity as the maximum flow rate from paragraph (c)(1)(iv)(C)(2) of this section divided by the unobstructed cross-sectional area of the flare tip from paragraph (c)(1)(iv)(C)(1) of this section.
(4) Demonstrate that the maximum flare tip velocity as calculated in paragraph (c)(1)(iv)(C)(3) of this section is less than 60 feet per second.
(1) You must conduct the CMS equipment performance checks, system accuracy audits, or other audit procedures specified in the monitoring plan at least once every 12 calendar months.
(2) You must also conduct calibration checks following any period of more than 24 hours throughout which the sensor exceeded the manufacturer's specified maximum range unless you install a new sensor.
(3) At least quarterly, you must inspect all components for integrity and all electrical connections for continuity, oxidation, and galvanic corrosion, unless you use a redundant CMS.
(4) Daily checks for indications that the system is responding.
Notes, amendments, and revision history
Source
Source: 89 FR 83319, Oct. 15, 2024, unless otherwise noted.
Authority
Authority: 42 U.S.C. 7401 et seq.
Source
Source: 36 FR 24877, Dec. 23, 1971, unless otherwise noted.