§52.40. What are the requirements of the Federal Implementation Plans (FIPs) relating to ozone season emissions of nitrogen oxides from sources not subject to the CSAPR ozone season trading program? — Inbound Citations

40 C.F.R. § 52.40

Cited by 55 regulations in release Current.

Citations to 40 C.F.R. § 52.40 as a whole

Citations to §52.40(b)(2)

  • (ii) The stationary RICE is operated under limited circumstances for purposes other than those identified in paragraph (i) of this definition, as specified in paragraph (b)(1) of this section.
    Facility means all of the pollutant-emitting activities which belong to the same industrial grouping, are located on one or more contiguous or adjacent properties, and are under the control of the same person (or persons under common control). Pollutant-emitting activities shall be considered as part of the same industrial grouping if they belong to the same “Major Group” (i.e., which have the same first two digit code as described in the Standard Industrial Classification Manual, 1987). For purposes of this section, a facility may not extend beyond the 20 states identified in § 52.40(b)(2).
    Four stroke means any type of engine which completes the power cycle in two crankshaft revolutions, with intake and compression strokes in the first revolution and power and exhaust strokes in the second revolution.
    ISO conditions means 288 Kelvin (15 °C), 60 percent relative humidity, and 101.3 kilopascals pressure.
    Lean burn means any two-stroke or four-stroke spark ignited reciprocating internal combustion engine that does not meet the definition of a rich burn engine.
    Local Distribution Companies (LDCs) are companies that own or operate distribution pipelines, but not interstate pipelines or intrastate pipelines, that physically deliver natural gas to end users and that are within a single state that are regulated as separate operating companies by State public utility commissions or that operate as independent municipally-owned distribution systems. LDCs do not include pipelines (both interstate and intrastate) delivering natural gas directly to major industrial users and farm taps upstream of the local distribution company inlet.
    Local Distribution Company (LDC) custody transfer station means a metering station where the LDC receives a natural gas supply from an upstream supplier, which may be an interstate transmission pipeline or a local natural gas producer, for delivery to customers through the LDC's intrastate transmission or distribution lines.
    Nameplate rating means the manufacturer's maximum design capacity in horsepower (hp) at the installation site conditions. Starting from the completion of any physical change in the engine resulting in an increase in the maximum output (in hp) that the engine is capable of producing on a steady state basis and during continuous operation, such increased maximum output shall be as specified by the person conducting the physical change.
    Natural gas means a fluid mixture of hydrocarbons (e.g., methane, ethane, or propane) or non-hydrocarbons, composed of at least 70 percent methane by volume or that has a gross calorific value between 35 and 41 megajoules (MJ) per dry standard cubic meter (950 and 1,100 Btu per dry standard cubic foot), that maintains a gaseous state under ISO conditions. Natural gas does not include the following gaseous fuels: Landfill gas, digester gas, refinery gas, sour gas, blast furnace gas, coal-derived gas, producer gas, coke oven gas, or any gaseous fuel produced in a process which might result in highly variable CO2 content or heating value.
    Natural gas-fired means that greater than or equal to 90% of the engine's heat input, excluding recirculated or recuperated exhaust heat, is derived from the combustion of natural gas.
    Natural gas processing plant means any processing site engaged in the extraction of natural gas liquids from field gas, fractionation of mixed natural gas liquids to natural gas products, or both. A Joule-Thompson valve, a dew point depression valve, or an isolated or standalone Joule-Thompson skid is not a natural gas processing plant.
    Natural gas production facility means all equipment at a single stationary source directly associated with one or more natural gas wells upstream of the natural gas processing plant. This equipment includes, but is not limited to, equipment used for storage, separation, treating, dehydration, artificial lift, combustion, compression, pumping, metering, monitoring, and flowline.
    Operating day means a 24-hour period beginning at 12:00 midnight during which any fuel is combusted at any time in the engine.
    Pipeline transportation of natural gas means the movement of natural gas through an interconnected network of compressors and pipeline components, including the compressor and pipeline network used to transport the natural gas from processing plants over a distance (intrastate or interstate) to and from storage facilities, to large natural gas end-users, and prior to delivery to a “local distribution company custody transfer station” (as defined in this section) of an LDC that provides the natural gas to end-users. Pipeline transportation of natural gas does not include natural gas production facilities, natural gas processing plants, or the portion of a compressor and pipeline network that is upstream of a natural gas processing plant.
    Reciprocating internal combustion engine (RICE) means a reciprocating engine in which power, produced by heat and/or pressure that is developed in the engine combustion chambers by the burning of a mixture of air and fuel, is subsequently converted to mechanical work.
    Rich burn means any four-stroke spark ignited reciprocating internal combustion engine where the manufacturer's recommended operating air/fuel ratio divided by the stoichiometric air/fuel ratio at full load conditions is less than or equal to 1.1. Internal combustion engines originally manufactured as rich burn engines but modified with passive emissions control technology for nitrogen oxides (NOX) (such as pre-combustion chambers) will be considered lean burn engines. Existing affected unit where there are no manufacturer's recommendations regarding air/fuel ratio will be considered rich burn engines if the excess oxygen content of the exhaust at full load conditions is less than or equal to 2 percent.
    Spark ignition means a reciprocating internal combustion engine utilizing a spark plug (or other sparking device) to ignite the air/fuel mixture and with operating characteristics significantly similar to the theoretical Otto combustion cycle.
    Stoichiometric means the theoretical air-to-fuel ratio required for complete combustion.
    Two stroke means a type of reciprocating internal combustion engine which completes the power cycle in a single crankshaft revolution by combining the intake and compression operations into one stroke (one-half revolution) and the power and exhaust operations into a second stroke. This system requires auxiliary exhaust scavenging of the combustion products and inherently runs lean (excess of air) of stoichiometry.

Citations to §52.40(c)(1)

  • (4) Notwithstanding any other provision of this part, the effectiveness of paragraphs (a) and (b), (c)(1) through (3), and (d) through (g) of this section and §§ 52.41 through 52.46 is stayed for sources located in Arkansas, California, Illinois, Indiana, Kentucky, Louisiana, Maryland, Michigan, Mississippi, Missouri, Nevada, New Jersey, New York, Ohio, Oklahoma, Pennsylvania, Texas, Utah, Virginia, and West Virginia, including Indian country located within the borders of such States.

Citations to §52.40(c)(2)

  • (4) Notwithstanding any other provision of this part, the effectiveness of paragraphs (a) and (b), (c)(1) through (3), and (d) through (g) of this section and §§ 52.41 through 52.46 is stayed for sources located in Arkansas, California, Illinois, Indiana, Kentucky, Louisiana, Maryland, Michigan, Mississippi, Missouri, Nevada, New Jersey, New York, Ohio, Oklahoma, Pennsylvania, Texas, Utah, Virginia, and West Virginia, including Indian country located within the borders of such States.
  • (b) You are subject to the requirements under this section if you own or operate a new or existing natural gas-fired spark ignition engine, other than an emergency engine, with a nameplate rating of 1,000 hp or greater that is used for pipeline transportation of natural gas and is located within any of the States listed in § 52.40(c)(2), including Indian country located within the borders of any such State(s).
    (1) For purposes of this section, the owner or operator of an emergency stationary RICE must operate the RICE according to the requirements in paragraphs (b)(1)(i) through (iii) of this section to be treated as an emergency stationary RICE. In order for stationary RICE to be treated as an emergency RICE under this subpart, any operation other than emergency operation, maintenance and testing, and operation in non-emergency situations for up to 50 hours per year, as described in paragraphs (b)(1)(i) through (iii), is prohibited. If you do not operate the RICE according to the requirements in paragraphs (b)(1)(i) through (iii), the RICE will not be considered an emergency engine under this section and must meet all requirements for affected units in this section.
    (ii) The owner or operator may operate your emergency stationary RICE for maintenance checks and readiness testing for a maximum of 100 hours per calendar year, provided that the tests are recommended by a Federal, state, or local government agency, the manufacturer, the vendor, or the insurance company associated with the engine. Any operation for non-emergency situations as allowed by paragraph (b)(1)(iii) of this section counts as part of the 100 hours per calendar year allowed by paragraph (b)(1)(ii) of this section. The owner or operator may petition the Administrator for approval of additional hours to be used for maintenance checks and readiness testing, but a petition is not required if the owner or operator maintains records confirming that Federal, state, or local standards require maintenance and testing of emergency RICE beyond 100 hours per calendar year. Any approval of a petition for additional hours granted by the Administrator under 40 CFR part 63, subpart ZZZZ, shall constitute approval by the Administrator of the same petition under this paragraph (b)(1)(ii).
    (iii) Emergency stationary RICE may be operated for up to 50 hours per calendar year in non-emergency situations. The 50 hours of operation in non-emergency situations are counted as part of the 100 hours per calendar year for maintenance and testing provided in paragraph (b)(1)(ii) of this section.
    (2) If you own or operate a natural gas-fired two stroke lean burn spark ignition engine manufactured after July 1, 2007 that is meeting the applicable emissions limits in 40 CFR part 60, subpart JJJJ, table 1, the engine is not an affected unit under this section and you do not have to comply with the requirements of this section.
    (3) If you own or operate a natural gas-fired four stroke lean or rich burn spark ignition engine manufactured after July 1, 2010, that is meeting the applicable emissions limits in 40 CFR part 60, subpart JJJJ, table 1, the engine is not an affected unit under this section and you do not have to comply with the requirements of this section.
  • (b) You are subject to the requirements of this section if you own or operate a new or existing cement kiln that emits or has the potential to emit 100 tons per year or more of NOX on or after August 4, 2023, and is located within any of the States listed in § 52.40(c)(2), including Indian country located within the borders of any such State(s). Any existing cement kiln with a potential to emit of 100 tons per year or more of NOX on August 4, 2023, will continue to be subject to the requirements of this section even if that unit later becomes subject to a physical or operational limitation that lowers its potential to emit below 100 tons per year of NOX.
  • (b) The requirements of this section apply to each new or existing reheat furnace at an iron and steel mill or ferroalloy manufacturing facility that directly emits or has the potential to emit 100 tons per year or more of NOX on or after August 4, 2023, does not have low-NOX burners installed, and is located within any of the States listed in § 52.40(c)(2), including Indian country located within the borders of any such State(s). Any existing reheat furnace with a potential to emit of 100 tons per year or more of NOX on August 4, 2023, will continue to be subject to the requirements of this section even if that unit later becomes subject to a physical or operational limitation that lowers its potential to emit below 100 tons per year of NOX.
  • (b) You are subject to the requirements under this section if you own or operate a new or existing glass manufacturing furnace that directly emits or has the potential to emit 100 tons per year or more of NOX on or after August 4, 2023, and is located within any of the States listed in § 52.40(c)(2), including Indian country located within the borders of any such State(s). Any existing glass manufacturing furnace with a potential to emit of 100 tons per year or more of NOX on August 4, 2023, will continue to be subject to the requirements of this section even if that unit later becomes subject to a physical or operational limitation that lowers its potential to emit below 100 tons per year of NOX.
  • (1) The requirements of this section apply to each new or existing boiler with a design capacity of 100 mmBtu/hr or greater that receives 90% or more of its heat input from coal, residual oil, distillate oil, natural gas, or combinations of these fuels in the previous ozone season, is located at sources that are within the Basic Chemical Manufacturing industry, the Petroleum and Coal Products Manufacturing industry, the Pulp, Paper, and Paperboard industry, the Metal Ore Mining industry, and the Iron and Steel and Ferroalloys Manufacturing industry and which is located within any of the States listed in § 52.40(c)(2), including Indian country located within the borders of any such State(s). The requirements of this section do not apply to an emissions unit that meets the requirements for a low-use exemption as provided in paragraph (b)(2) of this section.
  • (b) The requirements of this section apply to each new or existing municipal waste combustor unit with a combustion capacity greater than 250 tons per day (225 megagrams per day) of municipal solid waste and which is located within any of the States listed in § 52.40(c)(2), including Indian country located within the borders of any such State(s).

Citations to §52.40(c)(3)

  • (4) Notwithstanding any other provision of this part, the effectiveness of paragraphs (a) and (b), (c)(1) through (3), and (d) through (g) of this section and §§ 52.41 through 52.46 is stayed for sources located in Arkansas, California, Illinois, Indiana, Kentucky, Louisiana, Maryland, Michigan, Mississippi, Missouri, Nevada, New Jersey, New York, Ohio, Oklahoma, Pennsylvania, Texas, Utah, Virginia, and West Virginia, including Indian country located within the borders of such States.

Citations to §52.40(d)

  • (4) Notwithstanding any other provision of this part, the effectiveness of paragraphs (a) and (b), (c)(1) through (3), and (d) through (g) of this section and §§ 52.41 through 52.46 is stayed for sources located in Arkansas, California, Illinois, Indiana, Kentucky, Louisiana, Maryland, Michigan, Mississippi, Missouri, Nevada, New Jersey, New York, Ohio, Oklahoma, Pennsylvania, Texas, Utah, Virginia, and West Virginia, including Indian country located within the borders of such States.

Citations to §52.40(e)

  • (4) Notwithstanding any other provision of this part, the effectiveness of paragraphs (a) and (b), (c)(1) through (3), and (d) through (g) of this section and §§ 52.41 through 52.46 is stayed for sources located in Arkansas, California, Illinois, Indiana, Kentucky, Louisiana, Maryland, Michigan, Mississippi, Missouri, Nevada, New Jersey, New York, Ohio, Oklahoma, Pennsylvania, Texas, Utah, Virginia, and West Virginia, including Indian country located within the borders of such States.

Citations to §52.40(f)

  • (4) Notwithstanding any other provision of this part, the effectiveness of paragraphs (a) and (b), (c)(1) through (3), and (d) through (g) of this section and §§ 52.41 through 52.46 is stayed for sources located in Arkansas, California, Illinois, Indiana, Kentucky, Louisiana, Maryland, Michigan, Mississippi, Missouri, Nevada, New Jersey, New York, Ohio, Oklahoma, Pennsylvania, Texas, Utah, Virginia, and West Virginia, including Indian country located within the borders of such States.

Citations to §52.40(g)

  • (4) Notwithstanding any other provision of this part, the effectiveness of paragraphs (a) and (b), (c)(1) through (3), and (d) through (g) of this section and §§ 52.41 through 52.46 is stayed for sources located in Arkansas, California, Illinois, Indiana, Kentucky, Louisiana, Maryland, Michigan, Mississippi, Missouri, Nevada, New Jersey, New York, Ohio, Oklahoma, Pennsylvania, Texas, Utah, Virginia, and West Virginia, including Indian country located within the borders of such States.
  • (1) If you are the owner or operator of an affected unit, you must submit the results of the performance test or performance evaluation of the CEMS following the procedures specified in § 52.40(g) within 60 days after completing each performance test required by this section.
  • (1) If you are the owner or operator of an affected unit, you shall submit the results of the performance test or performance evaluation of the CEMS following the procedures specified in § 52.40(g) within 60 days after the date of completing each performance test required by this section.
  • (1) The owner or operator of each affected unit must submit a work plan for each affected unit by August 5, 2024. The work plan must be submitted via CEDRI or analogous electronic reporting approach provided by the EPA to report data required by this section following the procedures specified in § 52.40(g). Each work plan must include a description of the affected unit and rated production and energy capacities, identification of the low-NOX burner or alternative low NOX technology selected, and the phased construction timeframe by which you will design, install, and consistently operate the device. Each work plan shall also include, where applicable, performance test results obtained no more than five years before August 4, 2023, to be used as baseline emissions testing data providing the basis for required emissions reductions. If no such data exist, then the owner or operator must perform pre-installation testing as described in paragraph (e)(3) of this section.
  • (1) If you are the owner or operator of an affected unit, you shall maintain records of the following information for each day the affected unit operates:
    (i) Calendar date;
    (ii) The average hourly NOX emissions rates measured or predicted;
    (iii) The 30-day average NOX emissions rates calculated at the end of each affected unit operating day from the measured or predicted hourly NOX emissions rates for the preceding 30 operating days;
    (iv) Identification of the affected unit operating days when the calculated 30-day average NOX emissions rates are in excess of the applicable site-specific NOX emissions limit with the reasons for such excess emissions as well as a description of corrective actions taken;
    (v) Identification of the affected unit operating days for which pollutant data have not been obtained, including reasons for not obtaining sufficient data and a description of corrective actions taken;
    (vi) Identification of the times when emissions data have been excluded from the calculation of average emissions rates and the reasons for excluding data;
    (vii) If a CEMS is used to verify compliance:
    (A) Identification of the times when the pollutant concentration exceeded full span of the CEMS;
    (B) Description of any modifications to the CEMS that could affect the ability of the CEMS to comply with Performance Specification 2 or 3 in appendix B to 40 CFR part 60; and
    (C) Results of daily CEMS drift tests and quarterly accuracy assessments as required under Procedure 1 of 40 CFR part 60, appendix F;
    (D) Operating parameters required under paragraph (g) to demonstrate compliance during the ozone season;
    (viii) Each fuel type, usage, and heat content; and
  • (2) If you are the owner or operator of an affected unit complying as a low-use boiler, you must maintain the following records consistent with the requirements of § 52.40(g):
    (i) Identification and location of the boiler;
    (ii) Nameplate capacity;
    (iii) The fuel or fuels used by the boiler;
    (iv) For each operating day, the type and amount of fuel combusted, and the date and total number of hours of operation; and
    (v) the annual hours of operation for each of the prior 3 years, and the 3-year average hours or operation.
  • (f) If you are the owner or operator of an affected unit, you shall maintain records of the following information, as applicable, for each affected unit consistent with the requirements of § 52.40(g).
    (ii) The average concentrations and percent reductions, as applicable, including all 24-hour daily arithmetic average NOX emissions concentrations.
    (3) Identification of the calendar dates and times (hours) for which valid hourly NOX emissions, including reasons for not obtaining the data and a description of corrective actions taken.
    (4) Identification of each occurrence that NOX emissions data, or operational data (i.e., unit load) have been excluded from the calculation of average emissions concentrations or parameters, and the reasons for excluding the data.
    (5) The results of daily drift tests and quarterly accuracy determinations for CEMS, as required under 40 CFR part 60, appendix F, Procedure 1.
    (i) Records showing the names of the municipal waste combustor chief facility operator, shift supervisors, and control room operators who have been provisionally certified by the American Society of Mechanical Engineers or an equivalent State-approved certification program as required by 40 CFR 60.54b(a) including the dates of initial and renewal certifications and documentation of current certification;
    (ii) Records showing the names of the municipal waste combustor chief facility operator, shift supervisors, and control room operators who have been fully certified by the American Society of Mechanical Engineers or an equivalent State-approved certification program as required by 40 CFR 60.54b(b) including the dates of initial and renewal certifications and documentation of current certification;
    (iii) Records showing the names of the municipal waste combustor chief facility operator, shift supervisors, and control room operators who have completed the EPA municipal waste combustor operator training course or a State-approved equivalent course as required by 40 CFR 60.54b(d) including documentation of training completion; and
    (iv) Include two main items:
    (A) If the certified chief facility operator and certified shift supervisor are off site for more than 12 hours, but for 2 weeks or less, and no other certified operator is on site, record the dates that the certified chief facility operator and certified shift supervisor were off site.
    (B) When all certified chief facility operators and certified shift supervisors are off site for more than 2 weeks and no other certified operator is on site, keep records of four items:
    (1) Time of day that all certified persons are off site.
    (2) The conditions that cause those people to be off site.
    (3) The corrective actions taken by the owner or operator of the affected unit to ensure a certified chief facility operator or certified shift supervisor is on site as soon as practicable.
    (4) Copies of the reports submitted every 4 weeks that summarize the actions taken by the owner or operator of the affected unit to ensure that a certified chief facility operator or certified shift supervisor will be on site as soon as practicable.
    (7) Records showing the names of persons who have completed a review of the operating manual as required by 40 CFR 60.54b(f) including the date of the initial review and subsequent annual reviews.
    (8) Records of steps taken to minimize emissions during startup and shutdown as required by paragraph (d)(5) of this section.

Citations to §52.40(g)(1)(i)

  • (1) You shall submit the results of the performance test following the procedures specified in paragraphs (g)(1)(i) through (iii) of this section:
    (i) Data collected using test methods supported by the EPA's Electronic Reporting Tool (ERT) as listed on the EPA's ERT website (https://www.epa.gov/electronic-reporting-air-emissions/electronic-reporting-tool-ert) at the time of the test. Submit the results of the performance test to the EPA via the CEDRI or analogous electronic reporting approach provided by the EPA to report data required by § 52.41, § 52.42, § 52.43, § 52.44, § 52.45, or § 52.46, which can be accessed through the EPA's Central Data Exchange (CDX) (https://cdx.epa.gov/). The data must be submitted in a file format generated using the EPA's ERT. Alternatively, you may submit an electronic file consistent with the extensible markup language (XML) schema listed on the EPA's ERT website.
    (ii) Data collected using test methods that are not supported by the EPA's ERT as listed on the EPA's ERT website at the time of the test. The results of the performance test must be included as an attachment in the ERT or an alternate electronic file consistent with the XML schema listed on the EPA's ERT website. Submit the ERT generated package or alternative file to the EPA via CEDRI.
    (A) The EPA will make all the information submitted through CEDRI available to the public without further notice to you. Do not use CEDRI to submit information you claim as confidential business information (CBI). Although we do not expect persons to assert a claim of CBI, if you wish to assert a CBI claim for some of the information submitted under paragraph (g)(1) or (2) of this section, you should submit a complete file, including information claimed to be CBI, to the EPA.
    (B) The file must be generated using the EPA's ERT or an alternate electronic file consistent with the XML schema listed on the EPA's ERT website.
    (C) Information not marked as CBI may be authorized for public release without prior notice. Information marked as CBI will not be disclosed except in accordance with procedures set forth in 40 CFR part 2.
    (D) The preferred method to receive CBI is for it to be transmitted electronically using email attachments, File Transfer Protocol, or other online file sharing services. Electronic submissions must be transmitted directly to the Office of Air Quality Planning and Standards (OAQPS) CBI Office at the email address [email protected], and as described in this paragraph (g), should include clear CBI markings and be flagged to the attention of Lead of 2015 Ozone Transport FIP. If assistance is needed with submitting large electronic files that exceed the file size limit for email attachments, and if you do not have your own file sharing service, please email [email protected] to request a file transfer link.
    (E) If you cannot transmit the file electronically, you may send CBI information through the postal service to the following address: OAQPS Document Control Officer (C404-02), OAQPS, U.S. Environmental Protection Agency, Research Triangle Park, North Carolina 27711, Attention Lead of 2015 Ozone Transport FIP. The mailed CBI material should be double wrapped and clearly marked. Any CBI markings should not show through the outer envelope.
    (F) All CBI claims must be asserted at the time of submission. Anything submitted using CEDRI cannot later be claimed CBI. Furthermore, under CAA section 114(c), emissions data is not entitled to confidential treatment, and the EPA is required to make emissions data available to the public. Thus, emissions data will not be protected as CBI and will be made publicly available.
    (G) You must submit the same file submitted to the CBI office with the CBI omitted to the EPA via the EPA's CDX as described in paragraphs (g)(1) and (2) of this section.

Citations to §52.40(g)(1)(ii)

  • (1) You shall submit the results of the performance test following the procedures specified in paragraphs (g)(1)(i) through (iii) of this section:
    (i) Data collected using test methods supported by the EPA's Electronic Reporting Tool (ERT) as listed on the EPA's ERT website (https://www.epa.gov/electronic-reporting-air-emissions/electronic-reporting-tool-ert) at the time of the test. Submit the results of the performance test to the EPA via the CEDRI or analogous electronic reporting approach provided by the EPA to report data required by § 52.41, § 52.42, § 52.43, § 52.44, § 52.45, or § 52.46, which can be accessed through the EPA's Central Data Exchange (CDX) (https://cdx.epa.gov/). The data must be submitted in a file format generated using the EPA's ERT. Alternatively, you may submit an electronic file consistent with the extensible markup language (XML) schema listed on the EPA's ERT website.
    (ii) Data collected using test methods that are not supported by the EPA's ERT as listed on the EPA's ERT website at the time of the test. The results of the performance test must be included as an attachment in the ERT or an alternate electronic file consistent with the XML schema listed on the EPA's ERT website. Submit the ERT generated package or alternative file to the EPA via CEDRI.
    (A) The EPA will make all the information submitted through CEDRI available to the public without further notice to you. Do not use CEDRI to submit information you claim as confidential business information (CBI). Although we do not expect persons to assert a claim of CBI, if you wish to assert a CBI claim for some of the information submitted under paragraph (g)(1) or (2) of this section, you should submit a complete file, including information claimed to be CBI, to the EPA.
    (B) The file must be generated using the EPA's ERT or an alternate electronic file consistent with the XML schema listed on the EPA's ERT website.
    (C) Information not marked as CBI may be authorized for public release without prior notice. Information marked as CBI will not be disclosed except in accordance with procedures set forth in 40 CFR part 2.
    (D) The preferred method to receive CBI is for it to be transmitted electronically using email attachments, File Transfer Protocol, or other online file sharing services. Electronic submissions must be transmitted directly to the Office of Air Quality Planning and Standards (OAQPS) CBI Office at the email address [email protected], and as described in this paragraph (g), should include clear CBI markings and be flagged to the attention of Lead of 2015 Ozone Transport FIP. If assistance is needed with submitting large electronic files that exceed the file size limit for email attachments, and if you do not have your own file sharing service, please email [email protected] to request a file transfer link.
    (E) If you cannot transmit the file electronically, you may send CBI information through the postal service to the following address: OAQPS Document Control Officer (C404-02), OAQPS, U.S. Environmental Protection Agency, Research Triangle Park, North Carolina 27711, Attention Lead of 2015 Ozone Transport FIP. The mailed CBI material should be double wrapped and clearly marked. Any CBI markings should not show through the outer envelope.
    (F) All CBI claims must be asserted at the time of submission. Anything submitted using CEDRI cannot later be claimed CBI. Furthermore, under CAA section 114(c), emissions data is not entitled to confidential treatment, and the EPA is required to make emissions data available to the public. Thus, emissions data will not be protected as CBI and will be made publicly available.
    (G) You must submit the same file submitted to the CBI office with the CBI omitted to the EPA via the EPA's CDX as described in paragraphs (g)(1) and (2) of this section.

Citations to §52.40(g)(1)(iii)

  • (1) You shall submit the results of the performance test following the procedures specified in paragraphs (g)(1)(i) through (iii) of this section:
    (i) Data collected using test methods supported by the EPA's Electronic Reporting Tool (ERT) as listed on the EPA's ERT website (https://www.epa.gov/electronic-reporting-air-emissions/electronic-reporting-tool-ert) at the time of the test. Submit the results of the performance test to the EPA via the CEDRI or analogous electronic reporting approach provided by the EPA to report data required by § 52.41, § 52.42, § 52.43, § 52.44, § 52.45, or § 52.46, which can be accessed through the EPA's Central Data Exchange (CDX) (https://cdx.epa.gov/). The data must be submitted in a file format generated using the EPA's ERT. Alternatively, you may submit an electronic file consistent with the extensible markup language (XML) schema listed on the EPA's ERT website.
    (ii) Data collected using test methods that are not supported by the EPA's ERT as listed on the EPA's ERT website at the time of the test. The results of the performance test must be included as an attachment in the ERT or an alternate electronic file consistent with the XML schema listed on the EPA's ERT website. Submit the ERT generated package or alternative file to the EPA via CEDRI.
    (A) The EPA will make all the information submitted through CEDRI available to the public without further notice to you. Do not use CEDRI to submit information you claim as confidential business information (CBI). Although we do not expect persons to assert a claim of CBI, if you wish to assert a CBI claim for some of the information submitted under paragraph (g)(1) or (2) of this section, you should submit a complete file, including information claimed to be CBI, to the EPA.
    (B) The file must be generated using the EPA's ERT or an alternate electronic file consistent with the XML schema listed on the EPA's ERT website.
    (C) Information not marked as CBI may be authorized for public release without prior notice. Information marked as CBI will not be disclosed except in accordance with procedures set forth in 40 CFR part 2.
    (D) The preferred method to receive CBI is for it to be transmitted electronically using email attachments, File Transfer Protocol, or other online file sharing services. Electronic submissions must be transmitted directly to the Office of Air Quality Planning and Standards (OAQPS) CBI Office at the email address [email protected], and as described in this paragraph (g), should include clear CBI markings and be flagged to the attention of Lead of 2015 Ozone Transport FIP. If assistance is needed with submitting large electronic files that exceed the file size limit for email attachments, and if you do not have your own file sharing service, please email [email protected] to request a file transfer link.
    (E) If you cannot transmit the file electronically, you may send CBI information through the postal service to the following address: OAQPS Document Control Officer (C404-02), OAQPS, U.S. Environmental Protection Agency, Research Triangle Park, North Carolina 27711, Attention Lead of 2015 Ozone Transport FIP. The mailed CBI material should be double wrapped and clearly marked. Any CBI markings should not show through the outer envelope.
    (F) All CBI claims must be asserted at the time of submission. Anything submitted using CEDRI cannot later be claimed CBI. Furthermore, under CAA section 114(c), emissions data is not entitled to confidential treatment, and the EPA is required to make emissions data available to the public. Thus, emissions data will not be protected as CBI and will be made publicly available.
    (G) You must submit the same file submitted to the CBI office with the CBI omitted to the EPA via the EPA's CDX as described in paragraphs (g)(1) and (2) of this section.

Citations to §52.40(g)(3)(i)

  • (3) If you are required to electronically submit a report through CEDRI in the EPA's CDX, you may assert a claim of EPA system outage for failure to timely comply with that reporting requirement. To assert a claim of EPA system outage, you must meet the requirements outlined in paragraphs (g)(3)(i) through (vii) of this section.
    (i) You must have been or will be precluded from accessing CEDRI and submitting a required report within the time prescribed due to an outage of either the EPA's CEDRI or CDX systems.
    (ii) The outage must have occurred within the period of time beginning five business days prior to the date that the submission is due.
    (iii) The outage may be planned or unplanned.
    (iv) You must submit notification to the Administrator in writing as soon as possible following the date you first knew, or through due diligence should have known, that the event may cause or has caused a delay in reporting.
    (v) You must provide to the Administrator a written description identifying:
    (A) The date(s) and time(s) when CDX or CEDRI was accessed and the system was unavailable;
    (B) A rationale for attributing the delay in reporting beyond the regulatory deadline to EPA system outage;
    (C) A description of measures taken or to be taken to minimize the delay in reporting; and
    (D) The date by which you propose to report, or if you have already met the reporting requirement at the time of the notification, the date you reported.
    (vi) The decision to accept the claim of EPA system outage and allow an extension to the reporting deadline is solely within the discretion of the Administrator.
    (vii) In any circumstance, the report must be submitted electronically as soon as possible after the outage is resolved.

Citations to §52.40(g)(3)(ii)

  • (3) If you are required to electronically submit a report through CEDRI in the EPA's CDX, you may assert a claim of EPA system outage for failure to timely comply with that reporting requirement. To assert a claim of EPA system outage, you must meet the requirements outlined in paragraphs (g)(3)(i) through (vii) of this section.
    (i) You must have been or will be precluded from accessing CEDRI and submitting a required report within the time prescribed due to an outage of either the EPA's CEDRI or CDX systems.
    (ii) The outage must have occurred within the period of time beginning five business days prior to the date that the submission is due.
    (iii) The outage may be planned or unplanned.
    (iv) You must submit notification to the Administrator in writing as soon as possible following the date you first knew, or through due diligence should have known, that the event may cause or has caused a delay in reporting.
    (v) You must provide to the Administrator a written description identifying:
    (A) The date(s) and time(s) when CDX or CEDRI was accessed and the system was unavailable;
    (B) A rationale for attributing the delay in reporting beyond the regulatory deadline to EPA system outage;
    (C) A description of measures taken or to be taken to minimize the delay in reporting; and
    (D) The date by which you propose to report, or if you have already met the reporting requirement at the time of the notification, the date you reported.
    (vi) The decision to accept the claim of EPA system outage and allow an extension to the reporting deadline is solely within the discretion of the Administrator.
    (vii) In any circumstance, the report must be submitted electronically as soon as possible after the outage is resolved.

Citations to §52.40(g)(3)(iii)

  • (3) If you are required to electronically submit a report through CEDRI in the EPA's CDX, you may assert a claim of EPA system outage for failure to timely comply with that reporting requirement. To assert a claim of EPA system outage, you must meet the requirements outlined in paragraphs (g)(3)(i) through (vii) of this section.
    (i) You must have been or will be precluded from accessing CEDRI and submitting a required report within the time prescribed due to an outage of either the EPA's CEDRI or CDX systems.
    (ii) The outage must have occurred within the period of time beginning five business days prior to the date that the submission is due.
    (iii) The outage may be planned or unplanned.
    (iv) You must submit notification to the Administrator in writing as soon as possible following the date you first knew, or through due diligence should have known, that the event may cause or has caused a delay in reporting.
    (v) You must provide to the Administrator a written description identifying:
    (A) The date(s) and time(s) when CDX or CEDRI was accessed and the system was unavailable;
    (B) A rationale for attributing the delay in reporting beyond the regulatory deadline to EPA system outage;
    (C) A description of measures taken or to be taken to minimize the delay in reporting; and
    (D) The date by which you propose to report, or if you have already met the reporting requirement at the time of the notification, the date you reported.
    (vi) The decision to accept the claim of EPA system outage and allow an extension to the reporting deadline is solely within the discretion of the Administrator.
    (vii) In any circumstance, the report must be submitted electronically as soon as possible after the outage is resolved.

Citations to §52.40(g)(3)(iv)

  • (3) If you are required to electronically submit a report through CEDRI in the EPA's CDX, you may assert a claim of EPA system outage for failure to timely comply with that reporting requirement. To assert a claim of EPA system outage, you must meet the requirements outlined in paragraphs (g)(3)(i) through (vii) of this section.
    (i) You must have been or will be precluded from accessing CEDRI and submitting a required report within the time prescribed due to an outage of either the EPA's CEDRI or CDX systems.
    (ii) The outage must have occurred within the period of time beginning five business days prior to the date that the submission is due.
    (iii) The outage may be planned or unplanned.
    (iv) You must submit notification to the Administrator in writing as soon as possible following the date you first knew, or through due diligence should have known, that the event may cause or has caused a delay in reporting.
    (v) You must provide to the Administrator a written description identifying:
    (A) The date(s) and time(s) when CDX or CEDRI was accessed and the system was unavailable;
    (B) A rationale for attributing the delay in reporting beyond the regulatory deadline to EPA system outage;
    (C) A description of measures taken or to be taken to minimize the delay in reporting; and
    (D) The date by which you propose to report, or if you have already met the reporting requirement at the time of the notification, the date you reported.
    (vi) The decision to accept the claim of EPA system outage and allow an extension to the reporting deadline is solely within the discretion of the Administrator.
    (vii) In any circumstance, the report must be submitted electronically as soon as possible after the outage is resolved.

Citations to §52.40(g)(3)(v)

  • (3) If you are required to electronically submit a report through CEDRI in the EPA's CDX, you may assert a claim of EPA system outage for failure to timely comply with that reporting requirement. To assert a claim of EPA system outage, you must meet the requirements outlined in paragraphs (g)(3)(i) through (vii) of this section.
    (i) You must have been or will be precluded from accessing CEDRI and submitting a required report within the time prescribed due to an outage of either the EPA's CEDRI or CDX systems.
    (ii) The outage must have occurred within the period of time beginning five business days prior to the date that the submission is due.
    (iii) The outage may be planned or unplanned.
    (iv) You must submit notification to the Administrator in writing as soon as possible following the date you first knew, or through due diligence should have known, that the event may cause or has caused a delay in reporting.
    (v) You must provide to the Administrator a written description identifying:
    (A) The date(s) and time(s) when CDX or CEDRI was accessed and the system was unavailable;
    (B) A rationale for attributing the delay in reporting beyond the regulatory deadline to EPA system outage;
    (C) A description of measures taken or to be taken to minimize the delay in reporting; and
    (D) The date by which you propose to report, or if you have already met the reporting requirement at the time of the notification, the date you reported.
    (vi) The decision to accept the claim of EPA system outage and allow an extension to the reporting deadline is solely within the discretion of the Administrator.
    (vii) In any circumstance, the report must be submitted electronically as soon as possible after the outage is resolved.

Citations to §52.40(g)(3)(vi)

  • (3) If you are required to electronically submit a report through CEDRI in the EPA's CDX, you may assert a claim of EPA system outage for failure to timely comply with that reporting requirement. To assert a claim of EPA system outage, you must meet the requirements outlined in paragraphs (g)(3)(i) through (vii) of this section.
    (i) You must have been or will be precluded from accessing CEDRI and submitting a required report within the time prescribed due to an outage of either the EPA's CEDRI or CDX systems.
    (ii) The outage must have occurred within the period of time beginning five business days prior to the date that the submission is due.
    (iii) The outage may be planned or unplanned.
    (iv) You must submit notification to the Administrator in writing as soon as possible following the date you first knew, or through due diligence should have known, that the event may cause or has caused a delay in reporting.
    (v) You must provide to the Administrator a written description identifying:
    (A) The date(s) and time(s) when CDX or CEDRI was accessed and the system was unavailable;
    (B) A rationale for attributing the delay in reporting beyond the regulatory deadline to EPA system outage;
    (C) A description of measures taken or to be taken to minimize the delay in reporting; and
    (D) The date by which you propose to report, or if you have already met the reporting requirement at the time of the notification, the date you reported.
    (vi) The decision to accept the claim of EPA system outage and allow an extension to the reporting deadline is solely within the discretion of the Administrator.
    (vii) In any circumstance, the report must be submitted electronically as soon as possible after the outage is resolved.

Citations to §52.40(g)(3)(vii)

  • (3) If you are required to electronically submit a report through CEDRI in the EPA's CDX, you may assert a claim of EPA system outage for failure to timely comply with that reporting requirement. To assert a claim of EPA system outage, you must meet the requirements outlined in paragraphs (g)(3)(i) through (vii) of this section.
    (i) You must have been or will be precluded from accessing CEDRI and submitting a required report within the time prescribed due to an outage of either the EPA's CEDRI or CDX systems.
    (ii) The outage must have occurred within the period of time beginning five business days prior to the date that the submission is due.
    (iii) The outage may be planned or unplanned.
    (iv) You must submit notification to the Administrator in writing as soon as possible following the date you first knew, or through due diligence should have known, that the event may cause or has caused a delay in reporting.
    (v) You must provide to the Administrator a written description identifying:
    (A) The date(s) and time(s) when CDX or CEDRI was accessed and the system was unavailable;
    (B) A rationale for attributing the delay in reporting beyond the regulatory deadline to EPA system outage;
    (C) A description of measures taken or to be taken to minimize the delay in reporting; and
    (D) The date by which you propose to report, or if you have already met the reporting requirement at the time of the notification, the date you reported.
    (vi) The decision to accept the claim of EPA system outage and allow an extension to the reporting deadline is solely within the discretion of the Administrator.
    (vii) In any circumstance, the report must be submitted electronically as soon as possible after the outage is resolved.

Citations to §52.40(g)(4)(i)

  • (4) If you are required to electronically submit a report through CEDRI in the EPA's CDX, you may assert a claim of force majeure for failure to timely comply with that reporting requirement. To assert a claim of force majeure, you must meet the requirements outlined in paragraphs (g)(4)(i) through (v) of this section.
    (i) You may submit a claim if a force majeure event is about to occur, occurs, or has occurred or there are lingering effects from such an event within the period of time beginning five business days prior to the date the submission is due. For the purposes of this section, a force majeure event is defined as an event that will be or has been caused by circumstances beyond the control of the affected unit, its contractors, or any entity controlled by the affected unit that prevents you from complying with the requirement to submit a report electronically within the time period prescribed. Examples of such events are acts of nature (e.g., hurricanes, earthquakes, or floods), acts of war or terrorism, or equipment failure or safety hazard beyond the control of the affected unit (e.g., large scale power outage).
    (ii) You must submit notification to the Administrator in writing as soon as possible following the date you first knew, or through due diligence should have known, that the event may cause or has caused a delay in reporting.
    (iii) You must provide to the Administrator:
    (A) A written description of the force majeure event;
    (B) A rationale for attributing the delay in reporting beyond the regulatory deadline to the force majeure event;
    (C) A description of measures taken or to be taken to minimize the delay in reporting; and
    (D) The date by which you propose to report, or if you have already met the reporting requirement at the time of the notification, the date you reported.
    (iv) The decision to accept the claim of force majeure and allow an extension to the reporting deadline is solely within the discretion of the Administrator.
    (v) In any circumstance, the reporting must occur as soon as possible after the force majeure event occurs.

Citations to §52.40(g)(4)(ii)

  • (4) If you are required to electronically submit a report through CEDRI in the EPA's CDX, you may assert a claim of force majeure for failure to timely comply with that reporting requirement. To assert a claim of force majeure, you must meet the requirements outlined in paragraphs (g)(4)(i) through (v) of this section.
    (i) You may submit a claim if a force majeure event is about to occur, occurs, or has occurred or there are lingering effects from such an event within the period of time beginning five business days prior to the date the submission is due. For the purposes of this section, a force majeure event is defined as an event that will be or has been caused by circumstances beyond the control of the affected unit, its contractors, or any entity controlled by the affected unit that prevents you from complying with the requirement to submit a report electronically within the time period prescribed. Examples of such events are acts of nature (e.g., hurricanes, earthquakes, or floods), acts of war or terrorism, or equipment failure or safety hazard beyond the control of the affected unit (e.g., large scale power outage).
    (ii) You must submit notification to the Administrator in writing as soon as possible following the date you first knew, or through due diligence should have known, that the event may cause or has caused a delay in reporting.
    (iii) You must provide to the Administrator:
    (A) A written description of the force majeure event;
    (B) A rationale for attributing the delay in reporting beyond the regulatory deadline to the force majeure event;
    (C) A description of measures taken or to be taken to minimize the delay in reporting; and
    (D) The date by which you propose to report, or if you have already met the reporting requirement at the time of the notification, the date you reported.
    (iv) The decision to accept the claim of force majeure and allow an extension to the reporting deadline is solely within the discretion of the Administrator.
    (v) In any circumstance, the reporting must occur as soon as possible after the force majeure event occurs.

Citations to §52.40(g)(4)(iii)

  • (4) If you are required to electronically submit a report through CEDRI in the EPA's CDX, you may assert a claim of force majeure for failure to timely comply with that reporting requirement. To assert a claim of force majeure, you must meet the requirements outlined in paragraphs (g)(4)(i) through (v) of this section.
    (i) You may submit a claim if a force majeure event is about to occur, occurs, or has occurred or there are lingering effects from such an event within the period of time beginning five business days prior to the date the submission is due. For the purposes of this section, a force majeure event is defined as an event that will be or has been caused by circumstances beyond the control of the affected unit, its contractors, or any entity controlled by the affected unit that prevents you from complying with the requirement to submit a report electronically within the time period prescribed. Examples of such events are acts of nature (e.g., hurricanes, earthquakes, or floods), acts of war or terrorism, or equipment failure or safety hazard beyond the control of the affected unit (e.g., large scale power outage).
    (ii) You must submit notification to the Administrator in writing as soon as possible following the date you first knew, or through due diligence should have known, that the event may cause or has caused a delay in reporting.
    (iii) You must provide to the Administrator:
    (A) A written description of the force majeure event;
    (B) A rationale for attributing the delay in reporting beyond the regulatory deadline to the force majeure event;
    (C) A description of measures taken or to be taken to minimize the delay in reporting; and
    (D) The date by which you propose to report, or if you have already met the reporting requirement at the time of the notification, the date you reported.
    (iv) The decision to accept the claim of force majeure and allow an extension to the reporting deadline is solely within the discretion of the Administrator.
    (v) In any circumstance, the reporting must occur as soon as possible after the force majeure event occurs.

Citations to §52.40(g)(4)(iv)

  • (4) If you are required to electronically submit a report through CEDRI in the EPA's CDX, you may assert a claim of force majeure for failure to timely comply with that reporting requirement. To assert a claim of force majeure, you must meet the requirements outlined in paragraphs (g)(4)(i) through (v) of this section.
    (i) You may submit a claim if a force majeure event is about to occur, occurs, or has occurred or there are lingering effects from such an event within the period of time beginning five business days prior to the date the submission is due. For the purposes of this section, a force majeure event is defined as an event that will be or has been caused by circumstances beyond the control of the affected unit, its contractors, or any entity controlled by the affected unit that prevents you from complying with the requirement to submit a report electronically within the time period prescribed. Examples of such events are acts of nature (e.g., hurricanes, earthquakes, or floods), acts of war or terrorism, or equipment failure or safety hazard beyond the control of the affected unit (e.g., large scale power outage).
    (ii) You must submit notification to the Administrator in writing as soon as possible following the date you first knew, or through due diligence should have known, that the event may cause or has caused a delay in reporting.
    (iii) You must provide to the Administrator:
    (A) A written description of the force majeure event;
    (B) A rationale for attributing the delay in reporting beyond the regulatory deadline to the force majeure event;
    (C) A description of measures taken or to be taken to minimize the delay in reporting; and
    (D) The date by which you propose to report, or if you have already met the reporting requirement at the time of the notification, the date you reported.
    (iv) The decision to accept the claim of force majeure and allow an extension to the reporting deadline is solely within the discretion of the Administrator.
    (v) In any circumstance, the reporting must occur as soon as possible after the force majeure event occurs.

Citations to §52.40(g)(4)(v)

  • (4) If you are required to electronically submit a report through CEDRI in the EPA's CDX, you may assert a claim of force majeure for failure to timely comply with that reporting requirement. To assert a claim of force majeure, you must meet the requirements outlined in paragraphs (g)(4)(i) through (v) of this section.
    (i) You may submit a claim if a force majeure event is about to occur, occurs, or has occurred or there are lingering effects from such an event within the period of time beginning five business days prior to the date the submission is due. For the purposes of this section, a force majeure event is defined as an event that will be or has been caused by circumstances beyond the control of the affected unit, its contractors, or any entity controlled by the affected unit that prevents you from complying with the requirement to submit a report electronically within the time period prescribed. Examples of such events are acts of nature (e.g., hurricanes, earthquakes, or floods), acts of war or terrorism, or equipment failure or safety hazard beyond the control of the affected unit (e.g., large scale power outage).
    (ii) You must submit notification to the Administrator in writing as soon as possible following the date you first knew, or through due diligence should have known, that the event may cause or has caused a delay in reporting.
    (iii) You must provide to the Administrator:
    (A) A written description of the force majeure event;
    (B) A rationale for attributing the delay in reporting beyond the regulatory deadline to the force majeure event;
    (C) A description of measures taken or to be taken to minimize the delay in reporting; and
    (D) The date by which you propose to report, or if you have already met the reporting requirement at the time of the notification, the date you reported.
    (iv) The decision to accept the claim of force majeure and allow an extension to the reporting deadline is solely within the discretion of the Administrator.
    (v) In any circumstance, the reporting must occur as soon as possible after the force majeure event occurs.