40 C.F.R. § 49.10711
(b)
Definitions. The terms used in this section retain the meaning accorded them under the Clean Air Act, except as follows:
Astaris-Idaho or Astaris-Idaho facility means all of the pollutant-emitting activities that comprise the elemental phosphorus plant owned by or under the common control of Astaris-Idaho LLC in Township 6 south, Range 33 east, Sections 12, 13, and 14, and that lie within the exterior boundaries of the Fort Hall Indian Reservation, in Idaho, including, without limitation, all buildings, structures, facilities, installations, material handling areas, storage piles, roads, staging areas, parking lots, mechanical processes and related areas, and other processes and related areas. For purposes of this section, the term “Astaris-Idaho” or “Astaris-Idaho facility” shall not include pollutant emitting activities located on lands outside the exterior boundaries of the Fort Hall Indian Reservation.
Bag leak detection guidance means Office of Air Quality Planning and Standards (OAQPS): Fabric Filter Bag Leak Detection Guidance, EPA 454/R-98-015 (Sept. 1997).
Begin actual construction means, in general, initiation of physical on-site construction activities on a source which are of a permanent nature. Such activities include, but are not limited to, installation of building supports and foundations, laying of underground pipework, and construction of permanent storage structures. With respect to a change in the method of operating, this term refers to those on-site activities other than preparatory activities which mark the initiation of the change.
Certified observer means a visual emissions observer who has been properly certified using the initial certification and periodic semi-annual recertification procedures of 40 CFR part 60, appendix A, Method 9.
Construction means any physical change or change in the method of operation (including fabrication, erection, installation, demolition, or modification of a source) which would result in a change in actual emissions.
Emergency means any situation arising from sudden and reasonably unforeseeable events beyond the control of the owner or operator of the Astaris-Idaho facility, including acts of God, which requires immediate corrective action to restore normal operation. An emergency shall not include events caused by improperly designed equipment, lack of preventative maintenance, careless or improper operation, or operator error.
Emission limitation or emission standard means a requirement which limits the quantity, rate, or concentration of emissions of air pollutants on a continuous basis, including any requirements which limit the level of opacity, prescribe equipment, set fuel specifications, or prescribe operations or maintenance procedures to assure continuous emission reduction.
EPA means United States Environmental Protection Agency, Region 10.
Excess emissions means emissions of an air pollutant in excess of an emission limitation.
Excursion means a departure from a parameter range approved under paragraphs (e)(3) or (g)(1) of this section, consistent with any averaging period specified for averaging the results of monitoring.
Fugitive emissions means those emissions that do not actually pass through a stack, chimney, vent, or other functionally equivalent opening.
Malfunction means any sudden and unavoidable breakdown of process or control equipment. A sudden breakdown which could have been avoided by better operation and maintenance is not a malfunction.
Method 5 is the reference test method described in 40 CFR part 60, appendix A, conducted in accordance with the requirements of this section.
Method 9 is the reference test method described in 40 CFR part 60, appendix A.
Methods 201, 201A, and 202 are the reference test methods described in 40 CFR part 51, appendix M, conducted in accordance with the requirements of this section.
Mini-flush means the process of flushing elemental phosphorus, which has solidified in the secondary condenser, to the elevated secondary condenser flare or to the ground flare, and thus into the atmosphere.
Modification means any physical change in or a change in the method of operation of, an existing source which increases the amount of particulate matter emitted by that source. The following shall not, by themselves, be considered modifications:
(1)
Maintenance, repair, and replacement which the Regional Administrator determines to be routine for the particular source;
(2)
An increase in production rate of an existing source, if that increase can be accomplished without a physical change to the source or the Astaris-Idaho facility;
(3)
An increase in the hours of operation of an existing source, if that increase can be accomplished without a physical change to the source or the Astaris-Idaho facility;
(4)
Use of an alternative fuel or raw material, if the existing source is capable of accommodating that alternative without a physical change to the source or the Astaris-Idaho facility; or
(5)
The addition, replacement, or use of any system or device whose primary function is the reduction of an air pollutant, except when an emissions control system is removed or replaced by a system which the Regional Administrator determines to be less environmentally beneficial.
Monitoring malfunction means any sudden, infrequent, not reasonably preventable failure of the monitoring to provide valid data. Monitoring failures that are caused in part by poor maintenance or careless operation are not monitoring malfunctions.
O&M plan means an operation and maintenance plan developed by Astaris-Idaho and submitted to EPA in accordance with paragraph (e)(8) of this section.
Opacity means the degree to which emissions reduce the transmission of light and obscure the view of an object in the background.
Opacity action level means the level of opacity of emissions from a source requiring the owner or operator of the Astaris-Idaho facility to take prompt corrective action to minimize emissions, including without limitation those actions described in the approved operations and maintenance plan.
Owner or operator means any person who owns, leases, operates, controls, or supervises the Astaris-Idaho facility or any portion thereof.
Particulate matter means any airborne finely-divided solid or liquid material with an aerodynamic diameter smaller than 100 micrometers.
PM-10 or PM-10 emissions means finely divided solid or liquid material, with an aerodynamic diameter less than or equal to a nominal ten micrometers emitted to the ambient air as measured by an applicable reference method such as Method 201, 201A, or 202, of 40 CFR Part 51, appendix M, or an equivalent or alternative method specifically approved by the Regional Administrator.
Regional Administrator means the Regional Administrator, EPA Region 10, or a duly designated representative of the Regional Administrator.
Road means access and haul roads, driveways or established vehicle paths, permanent or temporary, which are graded, constructed, used, reconstructed, improved, or maintained for use in vehicle movement throughout the Astaris-Idaho facility.
Shutdown means the cessation of operation of a source for any purpose.
Slag Pit Area means the area of the Astaris-Idaho facility immediately bordering the south side of the furnace building extending out 100 yards.
Source means any building, structure, facility, installation, material handling area, storage pile, road, staging area, parking lot, mechanical process or related area, or other process or related area which emits or may emit particulate matter.
Startup means the setting in operation of a source for any purpose.
Title V permit means an operating permit issued under 40 CFR part 70 or 71.
Tribes means the Shoshone-Bannock Tribes.
Visible emissions means the emission of pollutants into the atmosphere, excluding uncombined condensed water vapor (steam), that is observable by the naked eye.
Visual observation means the continuous observation of a source for the presence of visible emissions for a period of ten consecutive minutes conducted in accordance with section 5 of EPA Method 22, 40 CFR part 60, appendix A, by a person who meets the training guidelines described in section 1 of Method 22.
(e)
Monitoring and additional work practice requirements.
(1)
The owner or operator of the Astaris-Idaho facility shall conduct a performance test to measure PM-10 emissions as follows:
(i)
The owner or operator of the Astaris-Idaho facility shall conduct a performance test to measure PM-10 emissions from each of the following sources on an annual basis using the specified reference test methods: east shale baghouse (Table 1 of this section, source 5a), middle shale baghouse (Table 1 of this section, source 6a), west shale baghouse (Table 1 of this section, source 7a), calciner cooler vents (Table 1 of this section, source 10), north nodule discharge baghouse (Table 1 of this section, source 12a), south nodule discharge baghouse (Table 1 of this section, source 12b), proportioning building-east nodule baghouse (Table 1 of this section, source 15a), proportioning building-west nodule baghouse (Table 1 of this section, source 15b), nodule stockpile baghouse (Table 1 of this section, source 16a), dust silo baghouse (Table 1 of this section, source 17a), furnace building-east baghouse (Table 1 of this section, source 18a), furnace building-west baghouse (Table 1 of this section, source 18b), furnace #1, #2, #3, and #4—Medusa-Andersen scrubbers (Table 1 of this section, sources 18d, 18e, 18f and 18g), coke handling baghouse (Table 1 of this section, source 20a), and phos dock-Andersen scrubber (Table 1 of this section, source 21a).
(A)
The first annual test for each source shall be completed within 16 months of August 23, 2000. Subsequent annual tests shall be completed within 12 months of the most recent previous test.
(B)
If, after conducting annual source tests for a particular source for two consecutive years, the emissions from that source are less than 80% of the applicable emission limit, then the frequency of source testing for that source may be reduced to every other year. The frequency of source testing shall revert to annually if the emissions from any source test on the source are greater than or equal to 80% of the applicable emission limit.
(ii)
The owner or operator of the Astaris-Idaho facility shall conduct a performance test to measure PM-10 emissions from the calciner scrubbers (Table 1 of this section, source 9a) and the excess CO burner (Table 1 of this section, source 26b) on a semi-annual basis using the specified reference test methods.
(A)
The first semi-annual performance test for each source shall be conducted within 90 days after the date on which the PM-10 emission limitations become applicable to the source. Subsequent semi-annual tests shall be completed within 6 months of the most recent previous test.
(B)
If, after conducting semi-annual source tests for the calciners or the excess CO burner for two consecutive years, the emissions from that source during each of the four previous consecutive semi-annual tests are less than 80% of the applicable emission limit, then the frequency of source testing for the source may be reduced to annual testing. The frequency of source testing shall revert to semi-annually if the emissions from any source test on the source are greater than or equal to 80% of the applicable emission limit.
(iii)
The owner or operator of the Astaris-Idaho facility shall conduct a performance test to determine the control efficiency of the calciner scrubbers (Table 1 of this section, source 9a) and the excess CO burner (Table 1 of this section, source 26b) using the specified reference test methods as follows:
(A)
A performance test for the calciner scrubbers shall be conducted within 90 days after the date on which the PM-10 emission limitations become applicable to the source.
(B)
The first performance test for the excess CO burner shall be conducted within 90 days after the date on which the PM-10 emission limitations become applicable to the source. Subsequent semi-annual tests shall be completed within 6 months of the most recent previous test.
(C)
If, after conducting semi-annual source tests for the excess CO burner for two consecutive years, the emissions from that source during each of the four previous consecutive semi-annual tests are less than 80% of the mass emission limit, then the frequency of source testing for the control efficiency requirement for the excess CO burner may be reduced to annual testing. The frequency of source testing shall revert to semi-annually if the emissions from any source test on the source are greater than or equal to 80% of the mass emission limit.
(iv)
If a source test indicates an exceedence of the emission limit applicable to the source, the owner or operator of the Astaris-Idaho facility shall conduct a performance test of that source within 90 days of the source test showing the exceedence. The schedule for conducting future source tests shall not be affected by this requirement.
(v)
The time period for conducting any source test may be extended by a period of up to 90 days provided that:
(A)
The owner or operator of the Astaris-Idaho facility submits a written request to the Regional Administrator at least 30 days prior to the expiration of the time period for conducting the test which demonstrates the need for the extension; and
(B)
The Regional Administrator approves the request in writing.
(vi)
The owner or operator of the Astaris-Idaho facility shall provide the Regional Administrator a proposed test plan at least 30 days in advance of each scheduled source test. If the proposed test plan is unchanged for the next scheduled source test on the source, the owner or operator of the Astaris-Idaho facility shall not be required to resubmit a source test plan. Astaris-Idaho shall submit a new source test plan to EPA in accordance with this
paragraph (e)(1) if the proposed test plan will be different from the immediately preceding source test plan that had been submitted to EPA.
(vii)
The owner or operator of the Astaris-Idaho facility shall provide the Regional Administrator at least 30 days prior written notice of any performance test required under this section to afford the Regional Administrator the opportunity to have an observer present. If after 30 days notice for an initially scheduled performance test, there is a delay (due to operational problems, etc.) in conducting the scheduled performance test, the owner or operator of the Astaris-Idaho facility shall notify the Regional Administrator as soon as possible of any delay in the original test date, either by providing at least 7 days prior notice of the rescheduled date of the performance test or by arranging a rescheduled date with the Regional Administrator by mutual agreement.
(viii)
(A)
The owner or operator of the Astaris-Idaho facility shall provide, or cause to be provided, performance testing facilities as follows:
(1) Sampling ports adequate for test methods applicable to the source. This includes:
(i) Constructing any new or modified air pollution control system such that volumetric flow rates and pollutant emission rates can be accurately determined by the applicable test methods and procedures; and
(ii) Except with respect to the calciner scrubber stacks (Table 1 of this section, source 9a), providing a stack or duct free of cyclonic flow during performance tests, as demonstrated by applicable test methods and procedures.
(2) Safe sampling platforms.
(3) Safe access to sampling platforms.
(4) Utilities for sampling and testing equipment.
(B)
A modification to these requirements can be approved with respect a particular source provided that— (1) The owner or operator of the Astaris-Idaho facility submits a written request to the Regional Administrator which demonstrates the need for the modification; and
(2) The Regional Administrator approves the request in writing.
(ix)
During each test run and for at least two hours prior to the test and two hours after the test is completed, the owner or operator of the Astaris-Idaho facility shall monitor and record the parameters specified in paragraphs
(e)(2),
(e)(3),
(e)(4),
(e)(5), and
(e)(6) of this section, as appropriate, for the source being tested, and shall report the results to EPA as part of the performance test report referred to in
paragraph (g)(3)(i)(G) of this section.
(x)
The owner or operator of the Astaris-Idaho facility shall conduct a 12 minute visible emission observation using Method 9 of
40 CFR Part 60, appendix A, at least twice during the performance test at an interval of no less than one hour apart, and shall report the results of this observation to EPA as part of the performance test report referred to in
paragraph (g)(3)(i)(G) of this section.
(xi)
Concurrently with the performance testing, the owner or operator of the Astaris-Idaho facility shall measure the flow rate (throughput to the control device) using Method 2 of
40 CFR Part 60, appendix A, for the calciner scrubbers (Table 1 of this section, source 9a) and the phos dock Andersen scrubber (Table 1 of this section, source 21a) and shall report the results to EPA as part of the performance test report referred to in
paragraph (g)(3)(i)(G) of this section.
(2)
The owner or operator of the Astaris-Idaho facility shall install, calibrate, maintain, and operate in accordance with the manufacturer's specifications a device to continuously measure and continuously record the pressure drop across the baghouse for each of the following sources identified in Column II of Table I: east shale baghouse (Table 1 of this section, source 5a), middle shale baghouse (Table 1 of this section, source 6a), west shale baghouse (Table 1 of this section, source 7a), north nodule discharge baghouse (Table 1 of this section, source 12a), north reclaim baghouse (Table 1 of this section, source 13), south nodule discharge baghouse (Table 1 of this section, source 12b), proportioning building-east nodule baghouse (Table 1 of this section, source 15a), proportioning building-west nodule baghouse (Table 1 of this section, source 15b), nodule stockpile baghouse (Table 1 of this section, source 16a), dust silo baghouse (Table 1 of this section, source 17a), furnace building-east baghouse (Table 1 of this section, source 18a), furnace building-west baghouse (Table 1 of this section, source 18b), and coke handling baghouse (Table 1 of this section, source 20a).
(i)
The devices shall be installed and fully operational no later than 210 days after August 23, 2000.
(ii)
Upon EPA approval of the acceptable range of baghouse pressure drop for each source, as provided in
paragraph (g)(1) of this section, the owner or operator of the Astaris-Idaho facility shall maintain and operate the source to stay within the approved range. Until EPA approval of the acceptable range of baghouse pressure drop for each source, the owner or operator of the Astaris-Idaho facility shall maintain and operate the source to stay within the proposed range for that source, as provided in
paragraph (g)(1) of this section.
(iii)
If an excursion from an approved range occurs, the owner or operator of the Astaris-Idaho facility shall immediately upon discovery, but no later than within three hours of discovery, initiate corrective action to bring source operation back within the approved range.
(iv)
The owner or operator of the Astaris-Idaho facility shall complete the corrective action as expeditiously as possible.
(3)
The owner or operator of the Astaris-Idaho facility shall install, calibrate, maintain, and operate in accordance with the manufacture's specifications and the bag leak detection guidance a triboelectric monitor to continuously monitor and record the readout of the instrument response for each of the following sources identified in Column II of Table 1 to this section: east shale baghouse (Table 1 of this section, source 5a), middle shale baghouse (Table 1 of this section, source 6a), west shale baghouse (Table 1 of this section, source 7a), north nodule discharge baghouse (Table 1 of this section, source 12a), south nodule discharge baghouse (Table 1 of this section, source 12b), north reclaim baghouse (Table 1 of this section, source 13), proportioning building-east nodule baghouse (Table 1 of this section, source 15a), proportioning building-west nodule baghouse (Table 1 of this section, source 15b), nodule stockpile baghouse (Table 1 of this section, source 16a), dust silo baghouse (Table 1 of this section, source 17a), furnace building-east baghouse (Table 1 of this section, source 18a), furnace building-west baghouse (Table 1 of this section, source 18b), and coke handling baghouse (Table 1 of this section, source 20a).
(i)
The triboelectric monitors shall be installed and fully operational no later than 210 days after August 23, 2000.
(ii)
The owner or operator of the Astaris-Idaho facility shall maintain and operate the source to stay within the approved range. For the triboelectric monitors, the “approved range” shall be defined as operating the source so that an “alarm,” as defined in and as determined in accordance with the bag leak detection guidance, does not occur.
(iii)
If an excursion from an approved range occurs, the owner or operator of the Astaris-Idaho facility shall immediately upon discovery, but no later than within three hours of discovery, initiate corrective action to bring source operation back within the approved range.
(iv)
The owner or operator of the Astaris-Idaho facility shall complete the corrective action as expeditiously as possible.
(4)
The owner or operator of the Astaris-Idaho facility shall install, calibrate, maintain, and operate in accordance with the manufacturer's specifications, a device to continuously measure and continuously record the pressure drop across the scrubber and the scrubber liquor flowrate for each of the calciner scrubbers (Table 1 of this section, source 9a).
(i)
The devices for the calciner scrubbers (Table 1 of this section, source 9a) shall be installed and fully operational on or before December 1, 2000.
(ii)
Upon EPA approval of the acceptable range of pressure drop, scrubber liquor flow rate, and scrubber liquor pH for the calciner scrubbers, as provided in
paragraph (g)(1) of this section, the owner or operator of the Astaris-Idaho facility shall maintain and operate the source to stay within the approved range. Until EPA approval of the acceptable ranges for each source, the owner or operator of the Astaris-Idaho facility shall maintain and operate the calciner scrubbers to stay within the proposed range for that source, as provided in
paragraph (g)(1) of this section.
(iii)
If an excursion from an approved range occurs, Astaris-Idaho shall immediately upon discovery, but no later than within three hours of discovery, initiate corrective action to bring calciner scrubber operation back within the approved range.
(iv)
The owner or operator of the Astaris-Idaho facility shall complete the corrective action as expeditiously as possible.
(5)
The owner or operator of the Astaris-Idaho facility shall install, calibrate, maintain, and operate in accordance with the manufacturer's specifications, a device to continuously measure and continuously record the pressure drop across the scrubber for each of the following sources identified in Column II of Table 1 to this section: furnaces #1, #2, #3 and #4—Medusa-Andersen scrubbers (Table 1 of this section, sources 18d, 18e, 18f and 18g), phos dock Andersen scrubber (Table 1 of this section, source 21a), and excess CO burner—Andersen scrubber (Table 1 of this section, source 26b).
(i)
The device for furnaces #1, #2, #3 and #4— Medusa-Andersen scrubbers (Table 1 of this section, sources 18d, 18e, 18f and 18g) and the phos dock Andersen scrubber (Table 1 of this section, source 21a) shall be installed and fully operational no later than 210 days after August 23, 2000. The device for the excess CO burner (Table 1 of this section, source 26b) shall be installed and fully operational no later than January 1, 2001.
(ii)
Upon EPA approval of the acceptable range of scrubber pressure drop for each source, as provided in
paragraph (g)(1) of this section, the owner or operator of the Astaris-Idaho facility shall maintain and operate the source to stay within the approved range. Until EPA approval of the acceptable ranges of scrubber pressure drop for each source, the owner or operator of the Astaris-Idaho facility shall maintain and operate the source to stay within the proposed range for that source, as provided in
paragraph (g)(1) of this section.
(iii)
If an excursion from an approved range occurs, the owner or operator of the Astaris-Idaho facility shall immediately upon discovery, but no later than within three hours of discovery, initiate corrective action to bring source operation back within the approved range.
(iv)
The owner or operator of the Astaris-Idaho facility shall complete the corrective action as expeditiously as possible.
(6)
The owner or operator of the Astaris-Idaho facility shall develop and implement a written plan for monitoring the scrubber water quality (through a parameter(s) such as total dissolved solids, total suspended solids, conductivity, specific gravity, etc) on a daily basis for the following sources: calciner scrubbers (Table 1 of this section, source 9a) and furnace #1, #2, #3 and #4—Medusa-Andersen scrubbers (Table 1 of this section, sources 18d, 18e, 18f and 18g).
(i)
The plan for furnaces #1, #2, #3 and #4— Medusa-Andersen scrubbers (Table 1 of this section, sources 18d, 18e, 18f and 18g) shall be submitted to the Regional Administrator within 180 days after September 22, 2000. The plan for the calciner scrubbers (Table 1 of this section, source 9a) shall submitted to the Regional Administrator no later than December 1, 2000.
(ii)
Upon EPA approval of the acceptable parameter range for water quality for each source, as provided in
paragraph (g)(1) of this section, the owner or operator of the Astaris-Idaho facility shall maintain and operate the source to stay within the approved range. Until EPA approval of the acceptable range of water quality for each source, the owner or operator of the Astaris-Idaho facility shall maintain and operate the source to stay within the proposed range for that source, as provided in
paragraph (g)(1) of this section.
(iii)
If an excursion from an approved range occurs, the owner or operator of the Astaris-Idaho facility shall immediately upon discovery, but no later than within three hours of discovery, initiate corrective action to bring source operation back within the approved range.
(iv)
The owner or operator of the Astaris-Idaho facility shall complete the corrective action as expeditiously as possible.
(7)
For each of the pressure relief vents on the furnaces (Table 1 of this section, source 24), Astaris-Idaho shall install, calibrate, maintain, and operate in accordance with the manufacturer's specifications, devices to continuously measure and continuously record the temperature and pressure of gases in the relief vent downstream of the pressure relief valve and the water level of the pressure relief valve.
(i)
The devices shall be installed and fully operational no later than 90 days after August 23, 2000.
(ii)
A “pressure release” is defined as an excursion of the temperature, pressure, or water level outside of the parameters approved in accordance with
paragraph (g)(1) of this section. Until EPA approval of the acceptable range of parameters for the pressure release vents, a “pressure release” is defined as an excursion of the temperature, pressure, or water level outside of the parameters proposed by the owner or operator of the Astaris-Idaho facility for the pressure relief vents, as provided in
paragraph (g)(1) of this section.
(iii)
The release point on each pressure relief vent shall be maintained at no less than 18 inches of water.
(iv)
When a pressure release through a pressure relief vent is detected, the owner or operator of the Astaris-Idaho facility shall, within 30 minutes of the beginning of the pressure release, inspect the pressure relief valve to ensure that it has properly sealed and verify that at least 18 inches of water seal pressure is maintained.
(8)
The owner or operator of the Astaris-Idaho facility shall develop and implement a written O&M plan covering all sources of PM-10 at the Astaris-Idaho facility, including without limitation, each source identified in Column II of Table 1 of this section and uncaptured fugitive and general fugitive emissions of PM-10 from each source.
(i)
The purpose of the O&M plan is to ensure each source at the Astaris-Idaho facility will be operated and maintained consistent with good air pollution control practices and procedures for maximizing control efficiency and minimizing emissions at all times, including periods of startup, shutdown, emergency, and malfunction, and to establish procedures for assuring continuous compliance with the emission limitations, work practice requirements, and other requirements of this section.
(ii)
The O&M plan shall be submitted to the Regional Administrator within 60 days of September 22, 2000 and shall cover all sources and requirements for which compliance is required 90 days after August 23, 2000.
(A)
A revision to the O&M plan covering each source or requirement with a compliance date of more than 60 days after September 22, 2000 shall be submitted at least 60 days before the source is required to comply with the requirement.
(B)
The owner or operator of the Astaris-Idaho facility shall review and, as appropriate, update the O&M plan at least annually.
(C)
The Regional Administrator may require the owner or operator of the Astaris-Idaho facility to modify the plan if, at any time, the Regional Administrator determines that the O&M plan does not:
(1) Adequately ensure that each source at the Astaris-Idaho facility will be operated and maintained consistent with good air pollution control practices and procedures for maximizing control efficiency and minimizing emissions at all times;
(2) Contain adequate procedures for assuring continuous compliance with the emission limitations, work practice requirements, and other requirements of this section;
(3) Adequately address the topics identified in this paragraph (e)(8); or
(4) Include sufficient mechanisms for ensuring that the O&M plan is being implemented.
(iii)
The O&M plan shall address at least the following topics:
(A)
Procedures for minimizing fugitive PM-10 emissions from material handling, storage piles, roads, staging areas, parking lots, mechanical processes, and other processes, including but not limited to:
(1) A visual inspection of all material handling, storage piles, roads, staging areas, parking lots, mechanical processes, and other processes at least once each week at a regularly scheduled time. The O&M plan shall include a list of equipment, operations, and storage piles, and what to look for at each source during this regularly scheduled inspection.
(2) A requirement to document the time, date, and results of each visual inspection, including any problems identified and any corrective actions taken.
(3) A requirement to take corrective action as soon as possible but no later than within 48 hours of identification of operations or maintenance problems identified during the visual inspection (unless a shorter time frame is specified by this rule or is warranted by the nature of the problem).
(4) Procedures for the application of dust suppressants to and the sweeping of material from storage piles, roads, staging areas, parking lots, or any open area as appropriate to maintain compliance with applicable emission limitations or work practice requirements. Such procedures shall include the specification of dust suppressants, the application rate, and application frequency, and the frequency of sweeping. Such procedures shall also include the procedures for application of latex to the main shale pile (source 2) and the emergency/contingency raw ore shale pile (source 3) after each reforming of the pile or portion of the pile.
(B)
Specifications for parts or elements of control or process equipment needing replacement after some set interval prior to breakdown or malfunction.
(C)
Process conditions that indicate need for repair, maintenance or cleaning of control or process equipment, such as the need to open furnace access ports or holes.
(D)
Procedures for the visual inspection of all baghouses, scrubbers, and other control equipment of at least once each week at a regularly scheduled time.
(E)
Procedures for the regular maintenance of control equipment, including without limitation, procedures for the rapid identification and replacement of broken or ripped bags for all sources controlled by a baghouse, bag dimensions, bag fabric, air-to-cloth ratio, bag cleaning methods, cleaning type, bag spacing, compartment design, bag replacement schedule, and typical exhaust gas volume.
(F)
Procedures that meet or exceed the manufacturer's recommendations for the inspection, maintenance, operation, and calibration of each monitoring device required by this part.
(G)
Procedures for the rapid identification and repair of equipment or processes causing a malfunction or emergency and for reducing or minimizing the duration of and emissions resulting from any malfunction or emergency.
(H)
Procedures for the training of staff in procedures listed in paragraph (e)(8)(i) of this section.
(I)
For each source identified in Column II of Table 2 to this section, additional control measures or other actions to be taken if the emissions from the source exceed the opacity action level identified in Column III of Table 2 to this section.
(9)
For each source identified in Column II of Table 1 to this section, the owner or operator of the Astaris-Idaho facility shall conduct a visual observation of each source at least once during each calendar week.
(i)
If visible emissions are observed for any period of time during the observation period, the owner or operator of the Astaris-Idaho facility shall immediately, but no later than within 24 hours of discovery, take corrective action to minimize visible emissions from the source. Such actions shall include, but not be limited to, those actions identified in the O&M plan for the source. Immediately upon completion of the corrective action, a certified observer shall conduct a visible emissions observation of the source using the reference test method for the opacity limit with an observation duration of at least six minutes. If opacity exceeds the opacity action level, the owner or operator of the Astaris-Idaho facility shall take prompt corrective action. This process shall be repeated until opacity returns to below the opacity action level.
(ii)
In lieu of the periodic visual observation under this
paragraph (e)(9), the owner or operator of the Astaris-Idaho facility may conduct a visible emission observation of any source subject to the requirements of this
paragraph (e)(9) using the reference test method for the opacity limit, in which case corrective action must be taken only if opacity exceeds the opacity action level.
(iii)
Should, for good cause, the visible emissions reading not be conducted on schedule, the owner or operator of the Astaris-Idaho facility shall record the reason observations were not conducted. Visible emissions observations shall be conducted immediately upon the return of conditions suitable for visible emissions observations.
(iv)
If, after conducting weekly visible emissions observations for a given source for more than one year and detecting no visible emissions from that source for 52 consecutive weeks, the frequency of observations may be reduced to monthly. The frequency of observations for such source shall revert to weekly if visible emissions are detected from that source during any monthly observation or at any other time.
(v)
With respect to slag handling (Table 1 of this section, source 8a)—
(A)
Visible emission observations shall be made of the slag tapping area as viewed from the exterior of the furnace building and in the general area of the old slag pits;
(B)
For the first three months after the effective date of the opacity limit, the owner or operator of the Astaris-Idaho facility shall conduct a visual observation of this source three days each week and shall submit the results of such observations at the end of the three month time frame. Thereafter, such observations shall be conducted weekly or as otherwise provided in this
paragraph (e)(9).
(10)
Except for, as applicable, monitoring malfunctions, associated repairs, and required quality assurance or control activities (including, as applicable, calibration checks and required zero span adjustments), the owner or operator of the Astaris-Idaho facility shall conduct all monitoring with the monitoring devices required by paragraphs
(e)(2),
(e)(3),
(e)(4),
(e)(5),
(e)(6), and
(e)(7) of this section in continuous operation at all times that the monitored process is in operation. Data recorded during monitoring malfunctions, associated repairs, and required quality assurance or control activities shall not be used for purposes of this section, including data averages and calculations, or fulfilling a minimum data availability requirement. The owner or operator of the Astaris-Idaho facility shall use data collected during all other periods in assessing the operation of the control device and associated control system.
(11)
The minimum data availability requirement for monitoring data pursuant to paragraphs
(e)(2),
(e)(3),
(e)(4),
(e)(5),
(e)(6), and
(e)(7) of this section is 90% on a monthly average basis. Data availability is determined by dividing the time (or number of data points) representing valid data by the time (or number of data points) that the monitored process is in operation.
(12)
Nothing in this
paragraph (e) shall preclude EPA from requiring any other testing or monitoring pursuant to
section 114 of the Clean Air Act.
(f)
Record keeping requirements.
(1)
The owner or operator of the Astaris-Idaho facility shall keep records of all monitoring required by this section that include, at a minimum, the following information:
(i)
The date, place as defined in this section, and time of the sampling or measurement.
(ii)
The dates the analyses were performed.
(iii)
The company or entity that performed the analyses.
(iv)
The analytical techniques or methods used.
(v)
The results of the analyses.
(vi)
The operating conditions existing at the time of the sampling or measurement.
(2)
(i)
The owner or operator of the Astaris-Idaho facility shall keep records of all inspections and all visible emissions observations required by this section or conducted pursuant to the O&M plan, which records shall include the following:
(A)
The date, place, and time of the inspection or observation.
(B)
The name and title of the person conducting the inspection or observation.
(C)
In the case of a visible emission observation, the test method (Method 9 or visual observation), the relevant or specified meteorological conditions, and the results of the observation, including raw data and calculations. In the case of visible emission observations of slag handling (Table 1 of this section, source 8a), the owner or operator of the Astaris-Idaho facility shall also document whether visible emissions emanate from fuming of hot slag from pots or other points in the old slag pit area.
(D)
For any corrective action required by this section or the O&M plan or taken in response to a problem identified during an inspection or visible emissions observation required by this section or the O&M plan, the time and date corrective action was initiated and completed and the nature of corrective action taken.
(E)
The reason for any monitoring not conducted on schedule.
(3)
The owner or operator of the Astaris-Idaho facility shall continuously record the parameters specified in paragraphs
(e)(2),
(e)(3),
(e)(4),
(e)(5), and
(e)(7) of this section, and shall record the parameters specified in
paragraphs (e)(6) of this section on the frequency specified in the monitoring plan required under
paragraph (e)(6) of this section.
(4)
The owner or operator of the Astaris-Idaho facility shall keep records of all excursions from ranges approved under paragraph
(e)(3) or
(g)(1) of this section, including without limitation, the measured excursion, time and date of the excursion, duration of the excursion, time and date corrective action was initiated and completed, and nature of corrective action taken.
(5)
The owner or operator of the Astaris-Idaho facility shall keep records of:
(i)
The time, date, and duration of each pressure release from a furnace pressure relief vent (Table 1 of this section, source 24), the method of detecting the release, the results of the inspection required by
paragraph (e)(7) of this section, and any actions taken to ensure resealing, including the time and date of such actions; and
(ii)
The time, date, and duration of the steaming and draining of the pressure relief vent drop tank.
(6)
The owner or operator of the Astaris-Idaho facility shall keep records of the time, date, and duration of each flaring of the emergency CO flares (Table 1 of this section, source 25) due to an emergency, the method of detecting the emergency, and all corrective action taken in response to the emergency.
(7)
Until January 1, 2001, the owner or operator of the Astaris-Idaho facility shall keep records of the date and start/stop time of each mini-flush; the phossy water flow rate and outlet temperature immediately preceding the start time; whether the operating parameters for conducting the mini-flush set forth in
paragraph (c)(5)(ii) of this section were met; and, if the parameters were not met, whether the failure to comply with the parameters was attributable to a malfunction or emergency.
(8)
The owner or operator of the Astaris-Idaho facility shall keep records of the application of dust suppressants to all storage piles, roads, staging areas, parking lots, and any other area, including the purchase of dust suppressants, the identification of the surface covered, type of dust suppressant used, the application rate (gallons per square foot), and date of application.
(9)
The owner or operator of the Astaris-Idaho facility shall keep records of the frequency of sweeping of all roads, staging areas, parking lots, and any other area, including the identification of the surface swept and date and duration of sweeping.
(10)
The owner or operator of the Astaris-Idaho facility shall keep the following records with respect to the main shale pile (Table 1 of this section, source 2) and emergency/contingency raw ore shale pile (Table 1 of this section, source 3):
(i)
The date and time of each reforming of the pile or portion of the pile.
(ii)
The date, time, and quantity of latex applied.
(11)
The owner or operator of the Astaris-Idaho facility shall keep a log for each control device of all inspections of and maintenance on the control device, including without limitation the following information:
(i)
The date, place, and time of the inspection or maintenance activity.
(ii)
The name and title of the person conducting the inspection or maintenance activity.
(iii)
The condition of the control device at the time.
(iv)
For any corrective action required by this section or the O&M plan or taken in response to a problem identified during an inspection required by this section or the O&M plan, the time and date corrective action was initiated and completed, and the nature of corrective action taken.
(v)
A description of, reason for, and the date of all maintenance activities, including without limitation any bag replacements.
(vi)
The reason any monitoring was not conducted on schedule, including a description of any monitoring malfunction, and the reason any required data was not collected.
(12)
The owner or operator of the Astaris-Idaho facility shall keep the following records:
(i)
The Method 9 initial certification and recertification for all individuals conducting visual emissions observations using Method 9 as required by this section.
(ii)
Evidence that all individuals conducting visual observations as required by this section meet the training guidelines described in
section 1 of Method 22,
40 CFR part 60, appendix A.
(13)
The owner or operator of the Astaris-Idaho facility shall keep records on the type and quantity of fuel used in the boilers (Table 1 of this section, source 23), including without limitation the date of any change in the type of fuel used.
(14)
The owner or operator of the Astaris-Idaho facility shall keep records of the results of the daily monitoring of the water quality of the scrubber water in the calciner scrubbers (Table 1 of this section, source 9a) and the Medusa-Andersen furnace scrubbers (Table 1 of this section, sources 18d, 18e, 18f, and 18g) as specified in the O&M plan.
(15)
The owner or operator of the Astaris-Idaho facility shall keep records of the time, date, and duration of each damper vent opening for the furnace building east and west baghouses (Table 1 of this section, sources 18a and 18b), the reason for the damper vent opening, and all corrective action taken in response to the damper vent opening.
(16)
The owner or operator of the Astaris-Idaho facility shall keep a copy of all reports required to be submitted to EPA under
paragraph (g) of this section.
(17)
All records required to be maintained by this section and records of all required monitoring data and support information shall be maintained on site at the Astaris-Idaho facility in a readily accessible location for a period of at least five years from the date of the monitoring sample, measurement, report, or record.
(i)
Such records shall be made available to EPA on request.
(ii)
Support information includes all calibration and maintenance records and all original strip chart recordings for continuous monitoring instrumentation.