§35.2204. Project changes.

40 C.F.R. § 35.2204

(a)
Minor changes in the project work that are consistent with the objectives of the project and within the scope of the grant agreement do not require the execution of a formal grant amendment before the grantee's implementation of the change. However, the amount of the funding provided by the grant agreement may only be increased by a formal grant amendment.
(b)
The grantee must receive from the Regional Administrator a formal grant amendment before implementing changes which:
(1)
Alter the project performance standards;
(2)
Alter the type of wastewater treatment provided by the project;
(3)
Significantly delay or accelerate the project schedule;
(4)
Substantially alter the facilities plan, design drawings and specifications, or the location, size, capacity, or quality of any major part of the project; or
(5)
Otherwise require a formal grant amendment under part 30 of this subchapter.
(c)
Notwithstanding paragraph (a) of this section, changes to Step 7 projects cannot increase the amount of EPA assistance established at the time of the grant amendment.
Notes, amendments, and revision history

Amendments

[49 FR 6234, Feb. 17, 1984, as amended at 55 FR 27097, June 29, 1990]

Authority

Authority: Secs. 101(e), 109(b), 201 through 205, 207, 208(d), 210 through 212, 215 through 219, 304(d)(3), 313, 501, 502, 511 and 516(b) of the Clean Water Act, as amended, 33 U.S.C. 1251 et seq.

Source

Source: 49 FR 6234, Feb. 17, 1984, unless otherwise noted.

Authority

Authority: 42 U.S.C. 7401 et seq.; 33 U.S.C. 1251 et seq.; 42 U.S.C. 300f et seq.; 42 U.S.C. 6901 et seq.; 7 U.S.C. 136 et seq.; 15 U.S.C. 2601 et seq.; 42 U.S.C. 13101 et seq.; Pub. L. 104-134, 110 Stat. 1321, 1321-299 (1996); Pub. L. 105-65, 111 Stat. 1344, 1373 (1997), 2 CFR 200.

Amendments

[49 FR 6234, Feb. 17, 1984, as amended at 55 FR 27097, June 29, 1990]