§35.2118. Preaward costs.

40 C.F.R. § 35.2118

(a)
EPA will not award grant assistance for Step 2 + 3 and Step 3 work performed before award of grant assistance for that project, except:
(1)
In emergencies or instances where delay could result in significant cost increases, the Regional Administrator may approve preliminary building work (such as procurement of major equipment requiring long lead times, field testing of innovative and alternative technologies, minor sewer rehabilitation, acquisition of eligible land or an option for the purchase of eligible land or advance building on minor portions of treatment works) after completion of the environmental review as required by § 35.2113.
(2)
If the Regional Administrator approves preliminary Step 3 work, such approval is not an actual or implied commitment of grant assistance and the applicant proceeds at its own risk.
(b)
Any procurement is subject to the requirements of 40 CFR part 33, and in the case of acquisition of eligible real property, 40 CFR part 4.
Notes, amendments, and revision history

Amendments

[49 FR 6234, Feb. 17, 1984, as amended at 55 FR 27097, June 29, 1990]

Authority

Authority: Secs. 101(e), 109(b), 201 through 205, 207, 208(d), 210 through 212, 215 through 219, 304(d)(3), 313, 501, 502, 511 and 516(b) of the Clean Water Act, as amended, 33 U.S.C. 1251 et seq.

Source

Source: 49 FR 6234, Feb. 17, 1984, unless otherwise noted.

Authority

Authority: 42 U.S.C. 7401 et seq.; 33 U.S.C. 1251 et seq.; 42 U.S.C. 300f et seq.; 42 U.S.C. 6901 et seq.; 7 U.S.C. 136 et seq.; 15 U.S.C. 2601 et seq.; 42 U.S.C. 13101 et seq.; Pub. L. 104-134, 110 Stat. 1321, 1321-299 (1996); Pub. L. 105-65, 111 Stat. 1344, 1373 (1997), 2 CFR 200.

Amendments

[49 FR 6234, Feb. 17, 1984, as amended at 55 FR 27097, June 29, 1990]