§265.142. Cost estimate for closure. — Inbound Citations
40 C.F.R. § 265.142
Statutory Authority
Cited by 10 regulations in release Current.
Citations to 40 C.F.R. § 265.142 as a whole
-
(a) The requirements of §§ 265.142, 265.143 and 265.147 through 265.150 apply to owners or operators of all hazardous waste facilities, except as provided otherwise in this section or in § 265.1.
-
-
-
(A) (1) Lists all the applicable current types, amounts, and sums of environmental obligations covered by a financial test. These obligations include both obligations in the programs which EPA directly operates and obligations where EPA has delegated authority to a State or approved a State's program. These obligations include, but are not limited to:(i) Liability, closure, post-closure and corrective action cost estimates required for hazardous waste treatment, storage, and disposal facilities under 40 CFR 264.101, 264.142, 264.144, 264.147, 265.142, 265.144, and 265.147;(ii) Cost estimates required for municipal solid waste management facilities under 40 CFR 258.71, 258.72, and 258.73;(iii) Current plugging cost estimates required for UIC facilities under 40 CFR 144.62;(iv) Cost estimates required for petroleum underground storage tank facilities under 40 CFR 280.93;(v) Cost estimates required for PCB storage facilities under 40 CFR 761.65;(vi) Any financial assurance required under, or as part of an action undertaken under, the Comprehensive Environmental Response, Compensation, and Liability Act; and(vii) Any other environmental obligations that are assured through a financial test.(2) Provides evidence demonstrating that the firm meets the conditions of either paragraph (f)(1)(i)(A) or (f)(1)(i)(B) or (f)(1)(i)(C) of this section and paragraphs (f)(1)(ii) and (f)(1)(iii) of this section.
Citations to §265.142(a)
-
(b) Current closure cost estimate means the most recent of the estimates prepared in accordance with § 265.142 (a), (b), and (c).
-
(d) The owner or operator must keep the following at the facility during the operating life of the facility: The latest closure cost estimate prepared in accordance with §§ 265.142 (a) and (c) and, when this estimate has been adjusted in accordance with § 265.142(b), the latest adjusted closure cost estimate.
Citations to §265.142(b)
-
(b) Current closure cost estimate means the most recent of the estimates prepared in accordance with § 265.142 (a), (b), and (c).
-
(c) During the active life of the facility, the owner or operator must revise the closure cost estimate no later than 30 days after a revision has been made to the closure plan which increases the cost of closure. If the owner or operator has an approved closure plan, the closure cost estimate must be revised no later than 30 days after the Regional Administrator has approved the request to modify the closure plan, if the change in the closure plan increases the cost of closure. The revised closure cost estimate must be adjusted for inflation as specified in § 265.142(b).
Citations to §265.142(c)
-
(b) Current closure cost estimate means the most recent of the estimates prepared in accordance with § 265.142 (a), (b), and (c).
-
(d) The owner or operator must keep the following at the facility during the operating life of the facility: The latest closure cost estimate prepared in accordance with §§ 265.142 (a) and (c) and, when this estimate has been adjusted in accordance with § 265.142(b), the latest adjusted closure cost estimate.