The following definitions apply to this part:
-
(f) Each owner or operator of a controlled landfill must submit a closure report to the Administrator within 30 days of ceasing waste acceptance. The Administrator may request additional information as may be necessary to verify that permanent closure has taken place in accordance with the requirements of 40 CFR 258.60. If a closure report has been submitted to the Administrator, no additional wastes may be placed into the landfill without filing a notification of modification as described under § 60.7(a)(4).
-
(d) Each owner or operator of a controlled landfill shall submit a closure report to the Administrator within 30 days of waste acceptance cessation. The Administrator may request additional information as may be necessary to verify that permanent closure has taken place in accordance with the requirements of 40 CFR 258.60. If a closure report has been submitted to the Administrator, no additional wastes may be placed into the landfill without filing a notification of modification as described under § 60.7(a)(4).
-
(e) Each owner or operator of a controlled landfill must submit a closure report to the Administrator within 30 days of waste acceptance cessation. The Administrator may request additional information as may be necessary to verify that permanent closure has taken place in accordance with the requirements of 40 CFR 258.60. If a closure report has been submitted to the Administrator, no additional wastes may be placed into the landfill without filing a notification of modification as described under § 60.7(a)(4).
-
(f) Each owner or operator of a controlled landfill must submit a closure report to the Administrator within 30 days of ceasing waste acceptance. The Administrator may request additional information as may be necessary to verify that permanent closure has taken place in accordance with the requirements of 40 CFR 258.60. If a closure report has been submitted to the Administrator, no additional wastes may be placed into the landfill without filing a notification of modification as described under 40 CFR 60.7(a)(4).
-
(f) Each owner or operator of a controlled landfill must submit a closure report to the Administrator within 30 days of waste acceptance cessation. The Administrator may request additional information as may be necessary to verify that permanent closure has taken place in accordance with the requirements of § 258.60 of this chapter. If a closure report has been submitted to the Administrator, no additional wastes may be placed into the landfill without filing a notification of modification as described under § 63.9(b) of subpart A.
-
(a) Existing MSWLF units that cannot make the demonstration specified in § 258.10(a), pertaining to airports, § 258.11(a), pertaining to floodplains, or § 258.15(a), pertaining to unstable areas, must close by October 9, 1996, in accordance with § 258.60 of this part and conduct post-closure activities in accordance with § 258.61 of this part.
-
Unless otherwise noted, all terms contained in this part are defined by their plain meaning. This section contains definitions for terms that appear throughout this part; additional definitions appear in the specific sections to which they apply.
-
-
(4) A schedule for completing all activities necessary to satisfy the closure criteria in § 258.60.
-
(a) The owner or operator must have a detailed written estimate, in current dollars, of the cost of hiring a third party to close the largest area of all MSWLF units ever requiring a final cover as required under § 258.60 at any time during the active life in accordance with the closure plan. The owner or operator must notify the State Director that the estimate has been placed in the operating record.(1) The cost estimate must equal the cost of closing the largest area of all MSWLF unit ever requiring a final cover at any time during the active life when the extent and manner of its operation would make closure the most expensive, as indicated by its closure plan (see § 258.60(c)(2) of this part).(2) During the active life of the MSWLF unit, the owner or operator must annually adjust the closure cost estimate for inflation.(3) The owner or operator must increase the closure cost estimate and the amount of financial assurance provided under paragraph (b) of this section if changes to the closure plan or MSWLF unit conditions increase the maximum cost of closure at any time during the remaining active life.(4) The owner or operator may reduce the closure cost estimate and the amount of financial assurance provided under paragraph (b) of this section if the cost estimate exceeds the maximum cost of closure at any time during the remaining life of the MSWLF unit. The owner or operator must notify the State Director that the justification for the reduction of the closure cost estimate and the amount of financial assurance has been placed in the operating record.
Citations to §258.60(a)
-
(1) MSWLF units that meet the conditions of § 258.1(e)(2) and receive waste after October 9, 1991 but stop receiving waste before April 9, 1994, are exempt from all the requirements of this part 258, except the final cover requirement specified in § 258.60(a). The final cover must be installed by October 9, 1994. Owners or operators of MSWLF units described in this paragraph that fail to complete cover installation by October 9, 1994 will be subject to all the requirements of this part 258, unless otherwise specified.
-
(c) The owner or operator must prepare a written closure plan that describes the steps necessary to close all MSWLF units at any point during their active life in accordance with the cover design requirements in § 258.60(a) or (b), as applicable. The closure plan, at a minimum, must include the following information:(1) A description of the final cover, designed in accordance with § 258.60(a) and the methods and procedures to be used to install the cover;(2) An estimate of the largest area of the MSWLF unit ever requiring a final cover as required under § 258.60(a) at any time during the active life;(3) An estimate of the maximum inventory of wastes ever on-site over the active life of the landfill facility; and(4) A schedule for completing all activities necessary to satisfy the closure criteria in § 258.60.
-
(2) In accordance with § 258.60(b), the owner and operator may replace the prescriptive final cover set forth in § 258.60(a), with an alternative final cover as follows:(i) The owner and operator may install an evapotranspiration cover system as an alternative final cover for the 12.5 acre site.(ii) The alternative final cover system shall be constructed to achieve an equivalent reduction in infiltration as the infiltration layer specified in § 258.60(a)(1) and (2), and provide an equivalent protection from wind and water erosion as the erosion layer specified in § 258.60(a)(3).(iii) The final cover system shall consist of a minimum three-foot-thick multi-layer cover system comprised, from bottom to top, of:(A) (1) Existing intermediate cover; and(2) Additional cover soil which, prior to placement, shall be wetted to optimal moisture and thoroughly mixed to near uniform condition, and the material shall then be placed in lifts with an uncompacted thickness of six to eight inches, spread evenly and compacted to 90 percent of the maximum dry density, and shall:(i) Exhibit a grain size distribution that excludes particles in excess of three inches in diameter;(ii) Have a minimum fines content (percent by weight passing U.S. No. 200 Sieve) of seven percent for an individual test and eight percent for the average of ten consecutive tests;(iii) Have a grain size distribution with a minimum of five percent smaller than five microns for an individual test and six percent for the average of ten consecutive tests; and(iv) Exhibit a maximum saturated hydraulic conductivity on the order of 1.0E-03 cm/sec.; and(3) A minimum six-inch surface erosion layer comprised of a rock/soil admixture. The surface erosion layer admixture and gradations for 3% slopes and 3:1 slopes are detailed below:(i) 3% slopes: For the 3% slopes the surface admixture shall be composed of pea gravel ( 3/8-inch to 1/2-inch diameter) mixed with cover soil at the ratio of 25% rock to soil by volume with a minimum six-inch erosion layer.(ii) For the 3:1 side slopes the surface admixture shall be composed of either: gravel/rock ( 3/4-inch to one-inch diameter) mixed with additional cover soil as described in paragraph (b)(2)(iii)(A)(2) of this section at the ratio of 50% rock to soil by volume and result in a minimum six-inch erosion layer, or gravel/rock ( 3/4-inch to two-inch diameter) mixed with additional cover soil as described in paragraph (b)(2)(iii)(A)(2) of this section at the ratio of 50% rock to soil by volume and result in a minimum 12-inch erosion layer.(iii) The owner and operator shall place documentation demonstrating compliance with the provisions of this section in the operating record.(iv) All other applicable provisions of this part remain in effect.(B) [Reserved]
Citations to §258.60(a)(1)
-
(b) The Director of an approved State may issue a research, development, and demonstration permit for a new MSWLF unit, existing MSWLF unit, or lateral expansion, for which the owner or operator proposes to utilize innovative and new methods which vary from the final cover criteria of § 258.60(a)(1), (a)(2) and (b)(1), provided the MSWLF unit owner/operator demonstrates that the infiltration of liquid through the alternative cover system will not cause contamination of groundwater or surface water, or cause leachate depth on the liner to exceed 30-cm.
-
(3) The final cover system shall be constructed to achieve an equivalent reduction in infiltration as the infiltration layer specified in § 258.60(a)(1) and (a)(2), and provide an equivalent protection from wind and water erosion as the erosion layer specified in paragraph (a)(3) of this section.
Citations to §258.60(a)(2)
-
(b) The Director of an approved State may issue a research, development, and demonstration permit for a new MSWLF unit, existing MSWLF unit, or lateral expansion, for which the owner or operator proposes to utilize innovative and new methods which vary from the final cover criteria of § 258.60(a)(1), (a)(2) and (b)(1), provided the MSWLF unit owner/operator demonstrates that the infiltration of liquid through the alternative cover system will not cause contamination of groundwater or surface water, or cause leachate depth on the liner to exceed 30-cm.
-
(3) The final cover system shall be constructed to achieve an equivalent reduction in infiltration as the infiltration layer specified in § 258.60(a)(1) and (a)(2), and provide an equivalent protection from wind and water erosion as the erosion layer specified in paragraph (a)(3) of this section.
Citations to §258.60(a)(3)
-
(ii) The alternative final cover system shall be constructed to achieve an equivalent reduction in infiltration as the infiltration layer specified in § 258.60(a)(1) and (2), and provide an equivalent protection from wind and water erosion as the erosion layer specified in § 258.60(a)(3).
Citations to §258.60(b)
-
(c) The owner or operator must prepare a written closure plan that describes the steps necessary to close all MSWLF units at any point during their active life in accordance with the cover design requirements in § 258.60(a) or (b), as applicable. The closure plan, at a minimum, must include the following information:(1) A description of the final cover, designed in accordance with § 258.60(a) and the methods and procedures to be used to install the cover;(2) An estimate of the largest area of the MSWLF unit ever requiring a final cover as required under § 258.60(a) at any time during the active life;(3) An estimate of the maximum inventory of wastes ever on-site over the active life of the landfill facility; and(4) A schedule for completing all activities necessary to satisfy the closure criteria in § 258.60.
-
(2) In accordance with § 258.60(b), the owner and operator may replace the prescriptive final cover set forth in § 258.60(a), with an alternative final cover as follows:(i) The owner and operator may install an evapotranspiration cover system as an alternative final cover for the 12.5 acre site.(ii) The alternative final cover system shall be constructed to achieve an equivalent reduction in infiltration as the infiltration layer specified in § 258.60(a)(1) and (2), and provide an equivalent protection from wind and water erosion as the erosion layer specified in § 258.60(a)(3).(iii) The final cover system shall consist of a minimum three-foot-thick multi-layer cover system comprised, from bottom to top, of:(A) (1) Existing intermediate cover; and(2) Additional cover soil which, prior to placement, shall be wetted to optimal moisture and thoroughly mixed to near uniform condition, and the material shall then be placed in lifts with an uncompacted thickness of six to eight inches, spread evenly and compacted to 90 percent of the maximum dry density, and shall:(i) Exhibit a grain size distribution that excludes particles in excess of three inches in diameter;(ii) Have a minimum fines content (percent by weight passing U.S. No. 200 Sieve) of seven percent for an individual test and eight percent for the average of ten consecutive tests;(iii) Have a grain size distribution with a minimum of five percent smaller than five microns for an individual test and six percent for the average of ten consecutive tests; and(iv) Exhibit a maximum saturated hydraulic conductivity on the order of 1.0E-03 cm/sec.; and(3) A minimum six-inch surface erosion layer comprised of a rock/soil admixture. The surface erosion layer admixture and gradations for 3% slopes and 3:1 slopes are detailed below:(i) 3% slopes: For the 3% slopes the surface admixture shall be composed of pea gravel ( 3/8-inch to 1/2-inch diameter) mixed with cover soil at the ratio of 25% rock to soil by volume with a minimum six-inch erosion layer.(ii) For the 3:1 side slopes the surface admixture shall be composed of either: gravel/rock ( 3/4-inch to one-inch diameter) mixed with additional cover soil as described in paragraph (b)(2)(iii)(A)(2) of this section at the ratio of 50% rock to soil by volume and result in a minimum six-inch erosion layer, or gravel/rock ( 3/4-inch to two-inch diameter) mixed with additional cover soil as described in paragraph (b)(2)(iii)(A)(2) of this section at the ratio of 50% rock to soil by volume and result in a minimum 12-inch erosion layer.(iii) The owner and operator shall place documentation demonstrating compliance with the provisions of this section in the operating record.(iv) All other applicable provisions of this part remain in effect.(B) [Reserved]
Citations to §258.60(b)(1)
-
(b) The Director of an approved State may issue a research, development, and demonstration permit for a new MSWLF unit, existing MSWLF unit, or lateral expansion, for which the owner or operator proposes to utilize innovative and new methods which vary from the final cover criteria of § 258.60(a)(1), (a)(2) and (b)(1), provided the MSWLF unit owner/operator demonstrates that the infiltration of liquid through the alternative cover system will not cause contamination of groundwater or surface water, or cause leachate depth on the liner to exceed 30-cm.
Citations to §258.60(b)(3)
-
(2) An owner or operator of a MSWLF unit that disposes of 20 tons of municipal solid waste per day or less, based on an annual average, is not eligible for a variance from § 258.60 (b)(1),except in accordance with § 258.60(b)(3).
Citations to §258.60(c)(2)
-
(1) The cost estimate must equal the cost of closing the largest area of all MSWLF unit ever requiring a final cover at any time during the active life when the extent and manner of its operation would make closure the most expensive, as indicated by its closure plan (see § 258.60(c)(2) of this part).
Citations to §258.60(f)
-
(e) Prior to beginning closure of each MSWLF unit as specified in § 258.60(f), an owner or operator must notify the State Director that a notice of the intent to close the unit has been placed in the operating record.
Citations to §258.60(h)
-
(b) The owner or operator of each MSWLF unit must establish financial assurance for closure of the MSWLF unit in compliance with § 258.74. The owner or operator must provide continuous coverage for closure until released from financial assurance requirements by demonstrating compliance with § 258.60 (h) and (i).
Citations to §258.60(i)
-
(b) The owner or operator of each MSWLF unit must establish financial assurance for closure of the MSWLF unit in compliance with § 258.74. The owner or operator must provide continuous coverage for closure until released from financial assurance requirements by demonstrating compliance with § 258.60 (h) and (i).