§147.3107. Mechanical integrity.

40 C.F.R. § 147.3107

(a)
Monitoring of annulus pressure conducted pursuant to § 146.8(b)(1) shall be preceded by an initial pressure test. A positive gauge pressure on the casing/tubing annulus (filled with liquid) shall be maintained continuously. The pressure shall be monitored monthly.
(b)
Pressure tests conducted pursuant to § 146.8(b)(2) of this chapter shall be performed with a pressure on the casing/tubing annulus of at least 200 p.s.i. unless otherwise specified by the Director. In addition, pressure tests conducted during well operation shall maintain an injection/annulus pressure differential of at least 100 p.s.i. throughout the tubing length.
(c)
Monitoring of enhanced recovery wells conducted pursuant to § 146.8(b)(3), must be preceded by an initial pressure test that was conducted no more than 90 days prior to the commencement of monitoring.
Notes, amendments, and revision history

Source

Source: 53 FR 43109, Oct. 25, 1988, unless otherwise noted.

Authority

Authority: 42 U.S.C. 300f et seq.; and 42 U.S.C. 6901 et seq.