§1065.395. Inertial PM balance verifications.

40 C.F.R. § 1065.395

This section describes how to verify the performance of an inertial PM balance.
(a)
Independent verification. Have the balance manufacturer (or a representative approved by the balance manufacturer) verify the inertial balance performance within 370 days before testing.
(b)
Other verifications. Perform other verifications using good engineering judgment and instrument manufacturer recommendations.