§9.62. When will the NPS grant a temporary access permit?
36 C.F.R. § 9.62
If the Regional Director determines that your proposed reconnaissance surveys will not result in surface disturbance, except for minimal disturbance necessary to perform required surveys, the Regional Director will issue you a temporary access permit within 30 days after receipt of a complete application, unless the Regional Director notifies you that additional time is necessary to evaluate or process your application.
Notes, amendments, and revision history
Authority
Authority: 16 U.S.C. 230a(a)(4), 459d-3, 460cc-2(i), 460ee(c)(4), 698c(b)(2), 698i(b)(2), and 698m-4; 18 U.S.C. 3571 and 3581; 31 U.S.C. 9701; 54 U.S.C. 100101, 100751, and 103104.
Source
Source: 81 FR 77992, Nov. 4, 2016, unless otherwise noted.