§9.102. How will the NPS conduct formal review? — Inbound Citations
36 C.F.R. § 9.102
Statutory Authority
Cited by 3 regulations in release Current.
Citations to 36 U.S.C. § 9.102 as a whole
-
If you propose operations in System units, other than Big Cypress National Preserve, we will process your application in accordance with §§ 9.101 through 9.104. If you propose operations in Big Cypress National Preserve, we will process your application in accordance with §§ 9.103 and 9.105.
-
The NPS will review your application and take action under §§ 9.100 through 9.104.
-
(c) If you need an operations permit, the information provided under § 9.71 is your permit application and the NPS will review your application under §§ 9.100 through 9.104.