US Codex
C.F.R.
Browse by date
Notes

§51.57. How does a concessioner request arbitration of the construction cost of a capital improvement?

36 C.F.R. § 51.57

If a concessioner requests arbitration of the construction cost of a capital improvement determined by the Director, the request must be made in writing to the Director within 3 months of the date of the Director's determination of construction cost under § 51.56. The arbitration procedures are described in § 51.51. The decision of the arbitration panel as to the construction cost of the capital improvement will be binding on the concessioner and the Director.
Notes, amendments, and revision history

Amendments

[66 FR 35083, July 3, 2001]

Authority

Authority: 54 U.S.C. 101901-101926 and title IV of the National Parks Omnibus Management Act of 1998 (Pub. L. 105-391).

Source

Source: 65 FR 20668, Apr. 17, 2000, unless otherwise noted.

Amendments

[66 FR 35083, July 3, 2001]