§385.13. Projects implemented under additional program authority.

33 C.F.R. § 385.13

(a)
To expedite implementation of the Plan, the Corps of Engineers and non-Federal sponsors may implement projects under the authority of section 601(c) of WRDA 2000 that are described in the Plan and that will produce a substantial benefit to the restoration, preservation, and protection of the South Florida ecosystem.
(b)
Each project implemented under the authority of section 601(c) of WRDA 2000 shall—
(1)
In general, follow the process described in § 385.11;
(2)
Not be implemented until a Project Implementation Report is prepared and approved in accordance with § 385.26; and
(3)
Not exceed a total cost of $25,000,000.
(c)
The total aggregate cost of all projects implemented under the additional program authority shall not exceed $206,000,000.
Notes, amendments, and revision history

Authority

Authority: Section 601, Pub. L. 106-541, 114 Stat. 2680; 10 U.S.C. 3013(g)(3); 33 U.S.C. 1 and 701; and 5 U.S.C. 301.

Source

Source: 68 FR 64220, Nov. 12, 2003, unless otherwise noted.