§333.12. Determine the appropriate level of NEPA review. — Inbound Citations

33 C.F.R. § 333.12

Cited by 6 regulations in release Current.

Citations to 33 U.S.C. § 333.12 as a whole

Citations to §333.12(a)(1)

  • (4) If the District Engineer cannot apply a categorical exclusion to the proposed activity consistent with paragraphs (a)(1)-(3), the District Engineer will determine the appropriate level of review, i.e., whether the proposed activity warrants preparation of an environmental assessment or an environmental impact statement. Most activities requiring a Corps permit that are not otherwise covered by a categorical exclusion normally require only an environmental assessment. In determining the level of review, the District Engineer will consider the proposed action's reasonably foreseeable effects consistent with paragraph (b), and then will:
    (i) develop an environmental assessment, as described in § 333.15, if the proposed activity is not likely to have reasonably foreseeable significant effects or the significance of the effects is unknown; or
    (ii) develop an environmental impact statement, as described in § 333.21, if the proposed activity is likely to have reasonably foreseeable significant effects.

Citations to §333.12(a)(2)

  • (4) If the District Engineer cannot apply a categorical exclusion to the proposed activity consistent with paragraphs (a)(1)-(3), the District Engineer will determine the appropriate level of review, i.e., whether the proposed activity warrants preparation of an environmental assessment or an environmental impact statement. Most activities requiring a Corps permit that are not otherwise covered by a categorical exclusion normally require only an environmental assessment. In determining the level of review, the District Engineer will consider the proposed action's reasonably foreseeable effects consistent with paragraph (b), and then will:
    (i) develop an environmental assessment, as described in § 333.15, if the proposed activity is not likely to have reasonably foreseeable significant effects or the significance of the effects is unknown; or
    (ii) develop an environmental impact statement, as described in § 333.21, if the proposed activity is likely to have reasonably foreseeable significant effects.

Citations to §333.12(a)(3)

  • (4) If the District Engineer cannot apply a categorical exclusion to the proposed activity consistent with paragraphs (a)(1)-(3), the District Engineer will determine the appropriate level of review, i.e., whether the proposed activity warrants preparation of an environmental assessment or an environmental impact statement. Most activities requiring a Corps permit that are not otherwise covered by a categorical exclusion normally require only an environmental assessment. In determining the level of review, the District Engineer will consider the proposed action's reasonably foreseeable effects consistent with paragraph (b), and then will:
    (i) develop an environmental assessment, as described in § 333.15, if the proposed activity is not likely to have reasonably foreseeable significant effects or the significance of the effects is unknown; or
    (ii) develop an environmental impact statement, as described in § 333.21, if the proposed activity is likely to have reasonably foreseeable significant effects.

Citations to §333.12(a)(5)(i)

  • (a) Prior to initiating an environmental impact statement, the District Engineer must determine the proposed activity is likely to have reasonably foreseeable significant effects on the quality of the human environment, after consideration of any mitigation the Corps may require. As described in § 333.12(a)(5)(i) and § 333.15 of this part, this determination can be made following the completion of an environmental assessment in cases where that environmental assessment cannot conclude in a finding of no significant impact; in other situations, it can be made without first preparing an environmental assessment in instances where initial consideration as to the appropriate level of review as described indicates that the proposed activity is likely to have reasonably foreseeable significant effects. In cases where it is obvious that the proposed activity is likely to result in reasonably foreseeable significant effects and an environmental assessment terminating in a finding of no significant impact is therefore not prepared, the District Engineer must make a determination that an environmental impact statement is required due to the likely significant effects of the activity. This determination will be made in accordance with § 333.12(b) and documented. Whether an impact rises to the level of significant is a matter of the District Engineer's expert judgment.

Citations to §333.12(b)

  • (a) Prior to initiating an environmental impact statement, the District Engineer must determine the proposed activity is likely to have reasonably foreseeable significant effects on the quality of the human environment, after consideration of any mitigation the Corps may require. As described in § 333.12(a)(5)(i) and § 333.15 of this part, this determination can be made following the completion of an environmental assessment in cases where that environmental assessment cannot conclude in a finding of no significant impact; in other situations, it can be made without first preparing an environmental assessment in instances where initial consideration as to the appropriate level of review as described indicates that the proposed activity is likely to have reasonably foreseeable significant effects. In cases where it is obvious that the proposed activity is likely to result in reasonably foreseeable significant effects and an environmental assessment terminating in a finding of no significant impact is therefore not prepared, the District Engineer must make a determination that an environmental impact statement is required due to the likely significant effects of the activity. This determination will be made in accordance with § 333.12(b) and documented. Whether an impact rises to the level of significant is a matter of the District Engineer's expert judgment.