(x) A draft of the operations manual for the proposed deepwater port, containing the information under § 150.15 of this subchapter, must demonstrate the applicant's ability to operate the deepwater port safely and effectively. To the extent that circumstances are similar, this demonstration can be in the form of evidence appended to the draft operations manual of the applicant's participation in the safe and effective management or operation of other offshore facilities, for example, evidence of compliance with BOEM requirements for those facilities. If the information required for the manual is not available, state why it is not and when it will be available.
-
(a) Each deepwater port must have an operations manual that addresses policies and procedures for normal and emergency operations conducted at the deepwater port. The operations manual must, at a minimum, include the requirements outlined in § 150.15 of this part.
Citations to §150.15(i)
-
(a) A tanker must enter or depart the port's safety zone or area to be avoided in accordance with the navigation procedures in the port's approved operations manual as described in § 150.15(i) of this part.
Citations to §150.15(i)(1)
-
(i) The procedures for tanker navigation, including the information required in paragraphs (i)(1) through (i)(9) of this section.(1) The operating limits, maneuvering capability, draft, net under keel clearance, tonnage, length, and breadth of the tanker that will be accommodated at each designated mooring.(2) The speed limits proposed for tankers in the safety zone and area to be avoided around the deepwater port.(3) Any special navigation or communication equipment that may be required for operating in the safety zone and area to be avoided.(4) The measures for routing vessels, including a description of the radar navigation system to be used in operation of the deepwater port:(i) Type of radar;(ii) Characteristics of the radar;(iii) Antenna location;(iv) Procedures for surveillance of vessels approaching, departing, navigating, and transiting the safety zone and area to be avoided;(v) Advisories to each tanker underway in the safety zone regarding the vessel's position, deepwater port conditions, and status of adjacent vessel traffic;(vi) Notices that must be made, as outlined in § 150.325 of this part, by the tanker master regarding the vessel's characteristics and status; and(6) The procedures for clearing tankers, support vessels, and other vessels and aircraft during emergency and routine conditions.(7) Weather limits for tankers, including a detailed description of how to forecast the wind, wave, and current conditions for:(i) Shutdown of cargo transfer operations;(ii) Departure of the tanker from the mooring;(iii) Prohibition on mooring at the deepwater port or SPM; and
Citations to §150.15(i)(2)
-
(i) The procedures for tanker navigation, including the information required in paragraphs (i)(1) through (i)(9) of this section.(1) The operating limits, maneuvering capability, draft, net under keel clearance, tonnage, length, and breadth of the tanker that will be accommodated at each designated mooring.(2) The speed limits proposed for tankers in the safety zone and area to be avoided around the deepwater port.(3) Any special navigation or communication equipment that may be required for operating in the safety zone and area to be avoided.(4) The measures for routing vessels, including a description of the radar navigation system to be used in operation of the deepwater port:(i) Type of radar;(ii) Characteristics of the radar;(iii) Antenna location;(iv) Procedures for surveillance of vessels approaching, departing, navigating, and transiting the safety zone and area to be avoided;(v) Advisories to each tanker underway in the safety zone regarding the vessel's position, deepwater port conditions, and status of adjacent vessel traffic;(vi) Notices that must be made, as outlined in § 150.325 of this part, by the tanker master regarding the vessel's characteristics and status; and(6) The procedures for clearing tankers, support vessels, and other vessels and aircraft during emergency and routine conditions.(7) Weather limits for tankers, including a detailed description of how to forecast the wind, wave, and current conditions for:(i) Shutdown of cargo transfer operations;(ii) Departure of the tanker from the mooring;(iii) Prohibition on mooring at the deepwater port or SPM; and
Citations to §150.15(i)(3)
-
(i) The procedures for tanker navigation, including the information required in paragraphs (i)(1) through (i)(9) of this section.(1) The operating limits, maneuvering capability, draft, net under keel clearance, tonnage, length, and breadth of the tanker that will be accommodated at each designated mooring.(2) The speed limits proposed for tankers in the safety zone and area to be avoided around the deepwater port.(3) Any special navigation or communication equipment that may be required for operating in the safety zone and area to be avoided.(4) The measures for routing vessels, including a description of the radar navigation system to be used in operation of the deepwater port:(i) Type of radar;(ii) Characteristics of the radar;(iii) Antenna location;(iv) Procedures for surveillance of vessels approaching, departing, navigating, and transiting the safety zone and area to be avoided;(v) Advisories to each tanker underway in the safety zone regarding the vessel's position, deepwater port conditions, and status of adjacent vessel traffic;(vi) Notices that must be made, as outlined in § 150.325 of this part, by the tanker master regarding the vessel's characteristics and status; and(6) The procedures for clearing tankers, support vessels, and other vessels and aircraft during emergency and routine conditions.(7) Weather limits for tankers, including a detailed description of how to forecast the wind, wave, and current conditions for:(i) Shutdown of cargo transfer operations;(ii) Departure of the tanker from the mooring;(iii) Prohibition on mooring at the deepwater port or SPM; and
Citations to §150.15(i)(4)
-
(i) The procedures for tanker navigation, including the information required in paragraphs (i)(1) through (i)(9) of this section.(1) The operating limits, maneuvering capability, draft, net under keel clearance, tonnage, length, and breadth of the tanker that will be accommodated at each designated mooring.(2) The speed limits proposed for tankers in the safety zone and area to be avoided around the deepwater port.(3) Any special navigation or communication equipment that may be required for operating in the safety zone and area to be avoided.(4) The measures for routing vessels, including a description of the radar navigation system to be used in operation of the deepwater port:(i) Type of radar;(ii) Characteristics of the radar;(iii) Antenna location;(iv) Procedures for surveillance of vessels approaching, departing, navigating, and transiting the safety zone and area to be avoided;(v) Advisories to each tanker underway in the safety zone regarding the vessel's position, deepwater port conditions, and status of adjacent vessel traffic;(vi) Notices that must be made, as outlined in § 150.325 of this part, by the tanker master regarding the vessel's characteristics and status; and(6) The procedures for clearing tankers, support vessels, and other vessels and aircraft during emergency and routine conditions.(7) Weather limits for tankers, including a detailed description of how to forecast the wind, wave, and current conditions for:(i) Shutdown of cargo transfer operations;(ii) Departure of the tanker from the mooring;(iii) Prohibition on mooring at the deepwater port or SPM; and
Citations to §150.15(i)(4)(vi)
-
(b) The owner, master, agent, or person in charge of a tanker bound for a manned deepwater port must report the pertinent information required in § 150.15(i)(4)(vi) of this part for the vessel, including:(1) The name, gross tonnage, and draft of the tanker;(2) The type and amount of cargo in the tanker;(3) The location of the tanker at the time of the report;(4) Any conditions on the tanker that may impair its navigation, such as fire, or malfunctioning propulsion, steering, navigational, or radiotelephone equipment. The testing requirements in § 164.25 of this chapter are applicable to vessels arriving at a deepwater port;(5) Any leaks, structural damage, or machinery malfunctions that may impair cargo transfer operations or cause a product discharge; and(6) The operational condition of the equipment listed under § 164.35 of this chapter on the tanker.
Citations to §150.15(i)(5)
-
(i) The procedures for tanker navigation, including the information required in paragraphs (i)(1) through (i)(9) of this section.(1) The operating limits, maneuvering capability, draft, net under keel clearance, tonnage, length, and breadth of the tanker that will be accommodated at each designated mooring.(2) The speed limits proposed for tankers in the safety zone and area to be avoided around the deepwater port.(3) Any special navigation or communication equipment that may be required for operating in the safety zone and area to be avoided.(4) The measures for routing vessels, including a description of the radar navigation system to be used in operation of the deepwater port:(i) Type of radar;(ii) Characteristics of the radar;(iii) Antenna location;(iv) Procedures for surveillance of vessels approaching, departing, navigating, and transiting the safety zone and area to be avoided;(v) Advisories to each tanker underway in the safety zone regarding the vessel's position, deepwater port conditions, and status of adjacent vessel traffic;(vi) Notices that must be made, as outlined in § 150.325 of this part, by the tanker master regarding the vessel's characteristics and status; and(6) The procedures for clearing tankers, support vessels, and other vessels and aircraft during emergency and routine conditions.(7) Weather limits for tankers, including a detailed description of how to forecast the wind, wave, and current conditions for:(i) Shutdown of cargo transfer operations;(ii) Departure of the tanker from the mooring;(iii) Prohibition on mooring at the deepwater port or SPM; and
Citations to §150.15(i)(6)
-
(i) The procedures for tanker navigation, including the information required in paragraphs (i)(1) through (i)(9) of this section.(1) The operating limits, maneuvering capability, draft, net under keel clearance, tonnage, length, and breadth of the tanker that will be accommodated at each designated mooring.(2) The speed limits proposed for tankers in the safety zone and area to be avoided around the deepwater port.(3) Any special navigation or communication equipment that may be required for operating in the safety zone and area to be avoided.(4) The measures for routing vessels, including a description of the radar navigation system to be used in operation of the deepwater port:(i) Type of radar;(ii) Characteristics of the radar;(iii) Antenna location;(iv) Procedures for surveillance of vessels approaching, departing, navigating, and transiting the safety zone and area to be avoided;(v) Advisories to each tanker underway in the safety zone regarding the vessel's position, deepwater port conditions, and status of adjacent vessel traffic;(vi) Notices that must be made, as outlined in § 150.325 of this part, by the tanker master regarding the vessel's characteristics and status; and(6) The procedures for clearing tankers, support vessels, and other vessels and aircraft during emergency and routine conditions.(7) Weather limits for tankers, including a detailed description of how to forecast the wind, wave, and current conditions for:(i) Shutdown of cargo transfer operations;(ii) Departure of the tanker from the mooring;(iii) Prohibition on mooring at the deepwater port or SPM; and
Citations to §150.15(i)(7)
-
(i) The procedures for tanker navigation, including the information required in paragraphs (i)(1) through (i)(9) of this section.(1) The operating limits, maneuvering capability, draft, net under keel clearance, tonnage, length, and breadth of the tanker that will be accommodated at each designated mooring.(2) The speed limits proposed for tankers in the safety zone and area to be avoided around the deepwater port.(3) Any special navigation or communication equipment that may be required for operating in the safety zone and area to be avoided.(4) The measures for routing vessels, including a description of the radar navigation system to be used in operation of the deepwater port:(i) Type of radar;(ii) Characteristics of the radar;(iii) Antenna location;(iv) Procedures for surveillance of vessels approaching, departing, navigating, and transiting the safety zone and area to be avoided;(v) Advisories to each tanker underway in the safety zone regarding the vessel's position, deepwater port conditions, and status of adjacent vessel traffic;(vi) Notices that must be made, as outlined in § 150.325 of this part, by the tanker master regarding the vessel's characteristics and status; and(6) The procedures for clearing tankers, support vessels, and other vessels and aircraft during emergency and routine conditions.(7) Weather limits for tankers, including a detailed description of how to forecast the wind, wave, and current conditions for:(i) Shutdown of cargo transfer operations;(ii) Departure of the tanker from the mooring;(iii) Prohibition on mooring at the deepwater port or SPM; and
Citations to §150.15(i)(8)
-
(i) The procedures for tanker navigation, including the information required in paragraphs (i)(1) through (i)(9) of this section.(1) The operating limits, maneuvering capability, draft, net under keel clearance, tonnage, length, and breadth of the tanker that will be accommodated at each designated mooring.(2) The speed limits proposed for tankers in the safety zone and area to be avoided around the deepwater port.(3) Any special navigation or communication equipment that may be required for operating in the safety zone and area to be avoided.(4) The measures for routing vessels, including a description of the radar navigation system to be used in operation of the deepwater port:(i) Type of radar;(ii) Characteristics of the radar;(iii) Antenna location;(iv) Procedures for surveillance of vessels approaching, departing, navigating, and transiting the safety zone and area to be avoided;(v) Advisories to each tanker underway in the safety zone regarding the vessel's position, deepwater port conditions, and status of adjacent vessel traffic;(vi) Notices that must be made, as outlined in § 150.325 of this part, by the tanker master regarding the vessel's characteristics and status; and(6) The procedures for clearing tankers, support vessels, and other vessels and aircraft during emergency and routine conditions.(7) Weather limits for tankers, including a detailed description of how to forecast the wind, wave, and current conditions for:(i) Shutdown of cargo transfer operations;(ii) Departure of the tanker from the mooring;(iii) Prohibition on mooring at the deepwater port or SPM; and
Citations to §150.15(i)(9)
-
(i) The procedures for tanker navigation, including the information required in paragraphs (i)(1) through (i)(9) of this section.(1) The operating limits, maneuvering capability, draft, net under keel clearance, tonnage, length, and breadth of the tanker that will be accommodated at each designated mooring.(2) The speed limits proposed for tankers in the safety zone and area to be avoided around the deepwater port.(3) Any special navigation or communication equipment that may be required for operating in the safety zone and area to be avoided.(4) The measures for routing vessels, including a description of the radar navigation system to be used in operation of the deepwater port:(i) Type of radar;(ii) Characteristics of the radar;(iii) Antenna location;(iv) Procedures for surveillance of vessels approaching, departing, navigating, and transiting the safety zone and area to be avoided;(v) Advisories to each tanker underway in the safety zone regarding the vessel's position, deepwater port conditions, and status of adjacent vessel traffic;(vi) Notices that must be made, as outlined in § 150.325 of this part, by the tanker master regarding the vessel's characteristics and status; and(6) The procedures for clearing tankers, support vessels, and other vessels and aircraft during emergency and routine conditions.(7) Weather limits for tankers, including a detailed description of how to forecast the wind, wave, and current conditions for:(i) Shutdown of cargo transfer operations;(ii) Departure of the tanker from the mooring;(iii) Prohibition on mooring at the deepwater port or SPM; and
Citations to §150.15(l)(1)
-
(l) The procedures for cargo transfer must comply with the applicable requirements of parts 154 and 156 for oil, and subpart B (Operations) to part 127 for natural gas, respectively, of this chapter, including the requirements specified in paragraphs (l)(1) through (l)(10) of this section.(i) Pre-transfer conference;(ii) Inspection of transfer site and equipment such as hoses, connectors, closure devices, monitoring devices, and containment;(iii) Connecting and disconnecting transfer equipment, including a floating hose string for a single point mooring (SPM);(iv) Preparation of the Declaration of Inspection; and(2) The requirements for natural gas transfers in accordance with subpart B to part 127 of this chapter regarding:(i) Pre-transfer conference;(ii) Inspection of transfer site and equipment such as hoses, connectors, closure devices, leak monitoring devices, and containment;(iii) Connecting and disconnecting of transfer equipment, including to a floating hose string for a SPM;(iv) Line purging to test for leaks and to prepare for cool-down or heat-up phases as appropriate;(v) Preparation of the Declaration of Inspection; and(4) The duties, title, qualifications, and training of personnel of the deepwater port designated as the person in charge and responsible for managing cargo transfers, including ballasting operations if applicable to the deepwater port, in accordance with subpart D of part 154 for oil, and subpart B (Operations) of part 127 for natural gas, respectively, of this chapter.(5) Minimum requirements for watch personnel on board the vessel during transfer operations, such as personnel necessary for checking mooring gear, monitoring communications, and maintaining propulsion and steering on standby.(8) The maximum relief valve settings, the maximum available working pressure, and hydraulic shock to the system without relief valves, or both.(9) Equipment necessary to discharge cargo to the port complex without harm to the environment or to persons involved in the cargo transfer, including piping, adapters, bolted flanges, and quick-disconnect coupling.
Citations to §150.15(l)(2)
-
(l) The procedures for cargo transfer must comply with the applicable requirements of parts 154 and 156 for oil, and subpart B (Operations) to part 127 for natural gas, respectively, of this chapter, including the requirements specified in paragraphs (l)(1) through (l)(10) of this section.(i) Pre-transfer conference;(ii) Inspection of transfer site and equipment such as hoses, connectors, closure devices, monitoring devices, and containment;(iii) Connecting and disconnecting transfer equipment, including a floating hose string for a single point mooring (SPM);(iv) Preparation of the Declaration of Inspection; and(2) The requirements for natural gas transfers in accordance with subpart B to part 127 of this chapter regarding:(i) Pre-transfer conference;(ii) Inspection of transfer site and equipment such as hoses, connectors, closure devices, leak monitoring devices, and containment;(iii) Connecting and disconnecting of transfer equipment, including to a floating hose string for a SPM;(iv) Line purging to test for leaks and to prepare for cool-down or heat-up phases as appropriate;(v) Preparation of the Declaration of Inspection; and(4) The duties, title, qualifications, and training of personnel of the deepwater port designated as the person in charge and responsible for managing cargo transfers, including ballasting operations if applicable to the deepwater port, in accordance with subpart D of part 154 for oil, and subpart B (Operations) of part 127 for natural gas, respectively, of this chapter.(5) Minimum requirements for watch personnel on board the vessel during transfer operations, such as personnel necessary for checking mooring gear, monitoring communications, and maintaining propulsion and steering on standby.(8) The maximum relief valve settings, the maximum available working pressure, and hydraulic shock to the system without relief valves, or both.(9) Equipment necessary to discharge cargo to the port complex without harm to the environment or to persons involved in the cargo transfer, including piping, adapters, bolted flanges, and quick-disconnect coupling.
Citations to §150.15(l)(3)
-
(l) The procedures for cargo transfer must comply with the applicable requirements of parts 154 and 156 for oil, and subpart B (Operations) to part 127 for natural gas, respectively, of this chapter, including the requirements specified in paragraphs (l)(1) through (l)(10) of this section.(i) Pre-transfer conference;(ii) Inspection of transfer site and equipment such as hoses, connectors, closure devices, monitoring devices, and containment;(iii) Connecting and disconnecting transfer equipment, including a floating hose string for a single point mooring (SPM);(iv) Preparation of the Declaration of Inspection; and(2) The requirements for natural gas transfers in accordance with subpart B to part 127 of this chapter regarding:(i) Pre-transfer conference;(ii) Inspection of transfer site and equipment such as hoses, connectors, closure devices, leak monitoring devices, and containment;(iii) Connecting and disconnecting of transfer equipment, including to a floating hose string for a SPM;(iv) Line purging to test for leaks and to prepare for cool-down or heat-up phases as appropriate;(v) Preparation of the Declaration of Inspection; and(4) The duties, title, qualifications, and training of personnel of the deepwater port designated as the person in charge and responsible for managing cargo transfers, including ballasting operations if applicable to the deepwater port, in accordance with subpart D of part 154 for oil, and subpart B (Operations) of part 127 for natural gas, respectively, of this chapter.(5) Minimum requirements for watch personnel on board the vessel during transfer operations, such as personnel necessary for checking mooring gear, monitoring communications, and maintaining propulsion and steering on standby.(8) The maximum relief valve settings, the maximum available working pressure, and hydraulic shock to the system without relief valves, or both.(9) Equipment necessary to discharge cargo to the port complex without harm to the environment or to persons involved in the cargo transfer, including piping, adapters, bolted flanges, and quick-disconnect coupling.
Citations to §150.15(l)(4)
-
(l) The procedures for cargo transfer must comply with the applicable requirements of parts 154 and 156 for oil, and subpart B (Operations) to part 127 for natural gas, respectively, of this chapter, including the requirements specified in paragraphs (l)(1) through (l)(10) of this section.(i) Pre-transfer conference;(ii) Inspection of transfer site and equipment such as hoses, connectors, closure devices, monitoring devices, and containment;(iii) Connecting and disconnecting transfer equipment, including a floating hose string for a single point mooring (SPM);(iv) Preparation of the Declaration of Inspection; and(2) The requirements for natural gas transfers in accordance with subpart B to part 127 of this chapter regarding:(i) Pre-transfer conference;(ii) Inspection of transfer site and equipment such as hoses, connectors, closure devices, leak monitoring devices, and containment;(iii) Connecting and disconnecting of transfer equipment, including to a floating hose string for a SPM;(iv) Line purging to test for leaks and to prepare for cool-down or heat-up phases as appropriate;(v) Preparation of the Declaration of Inspection; and(4) The duties, title, qualifications, and training of personnel of the deepwater port designated as the person in charge and responsible for managing cargo transfers, including ballasting operations if applicable to the deepwater port, in accordance with subpart D of part 154 for oil, and subpart B (Operations) of part 127 for natural gas, respectively, of this chapter.(5) Minimum requirements for watch personnel on board the vessel during transfer operations, such as personnel necessary for checking mooring gear, monitoring communications, and maintaining propulsion and steering on standby.(8) The maximum relief valve settings, the maximum available working pressure, and hydraulic shock to the system without relief valves, or both.(9) Equipment necessary to discharge cargo to the port complex without harm to the environment or to persons involved in the cargo transfer, including piping, adapters, bolted flanges, and quick-disconnect coupling.
Citations to §150.15(l)(5)
-
(l) The procedures for cargo transfer must comply with the applicable requirements of parts 154 and 156 for oil, and subpart B (Operations) to part 127 for natural gas, respectively, of this chapter, including the requirements specified in paragraphs (l)(1) through (l)(10) of this section.(i) Pre-transfer conference;(ii) Inspection of transfer site and equipment such as hoses, connectors, closure devices, monitoring devices, and containment;(iii) Connecting and disconnecting transfer equipment, including a floating hose string for a single point mooring (SPM);(iv) Preparation of the Declaration of Inspection; and(2) The requirements for natural gas transfers in accordance with subpart B to part 127 of this chapter regarding:(i) Pre-transfer conference;(ii) Inspection of transfer site and equipment such as hoses, connectors, closure devices, leak monitoring devices, and containment;(iii) Connecting and disconnecting of transfer equipment, including to a floating hose string for a SPM;(iv) Line purging to test for leaks and to prepare for cool-down or heat-up phases as appropriate;(v) Preparation of the Declaration of Inspection; and(4) The duties, title, qualifications, and training of personnel of the deepwater port designated as the person in charge and responsible for managing cargo transfers, including ballasting operations if applicable to the deepwater port, in accordance with subpart D of part 154 for oil, and subpart B (Operations) of part 127 for natural gas, respectively, of this chapter.(5) Minimum requirements for watch personnel on board the vessel during transfer operations, such as personnel necessary for checking mooring gear, monitoring communications, and maintaining propulsion and steering on standby.(8) The maximum relief valve settings, the maximum available working pressure, and hydraulic shock to the system without relief valves, or both.(9) Equipment necessary to discharge cargo to the port complex without harm to the environment or to persons involved in the cargo transfer, including piping, adapters, bolted flanges, and quick-disconnect coupling.
Citations to §150.15(l)(6)
-
(l) The procedures for cargo transfer must comply with the applicable requirements of parts 154 and 156 for oil, and subpart B (Operations) to part 127 for natural gas, respectively, of this chapter, including the requirements specified in paragraphs (l)(1) through (l)(10) of this section.(i) Pre-transfer conference;(ii) Inspection of transfer site and equipment such as hoses, connectors, closure devices, monitoring devices, and containment;(iii) Connecting and disconnecting transfer equipment, including a floating hose string for a single point mooring (SPM);(iv) Preparation of the Declaration of Inspection; and(2) The requirements for natural gas transfers in accordance with subpart B to part 127 of this chapter regarding:(i) Pre-transfer conference;(ii) Inspection of transfer site and equipment such as hoses, connectors, closure devices, leak monitoring devices, and containment;(iii) Connecting and disconnecting of transfer equipment, including to a floating hose string for a SPM;(iv) Line purging to test for leaks and to prepare for cool-down or heat-up phases as appropriate;(v) Preparation of the Declaration of Inspection; and(4) The duties, title, qualifications, and training of personnel of the deepwater port designated as the person in charge and responsible for managing cargo transfers, including ballasting operations if applicable to the deepwater port, in accordance with subpart D of part 154 for oil, and subpart B (Operations) of part 127 for natural gas, respectively, of this chapter.(5) Minimum requirements for watch personnel on board the vessel during transfer operations, such as personnel necessary for checking mooring gear, monitoring communications, and maintaining propulsion and steering on standby.(8) The maximum relief valve settings, the maximum available working pressure, and hydraulic shock to the system without relief valves, or both.(9) Equipment necessary to discharge cargo to the port complex without harm to the environment or to persons involved in the cargo transfer, including piping, adapters, bolted flanges, and quick-disconnect coupling.
Citations to §150.15(l)(7)
-
(l) The procedures for cargo transfer must comply with the applicable requirements of parts 154 and 156 for oil, and subpart B (Operations) to part 127 for natural gas, respectively, of this chapter, including the requirements specified in paragraphs (l)(1) through (l)(10) of this section.(i) Pre-transfer conference;(ii) Inspection of transfer site and equipment such as hoses, connectors, closure devices, monitoring devices, and containment;(iii) Connecting and disconnecting transfer equipment, including a floating hose string for a single point mooring (SPM);(iv) Preparation of the Declaration of Inspection; and(2) The requirements for natural gas transfers in accordance with subpart B to part 127 of this chapter regarding:(i) Pre-transfer conference;(ii) Inspection of transfer site and equipment such as hoses, connectors, closure devices, leak monitoring devices, and containment;(iii) Connecting and disconnecting of transfer equipment, including to a floating hose string for a SPM;(iv) Line purging to test for leaks and to prepare for cool-down or heat-up phases as appropriate;(v) Preparation of the Declaration of Inspection; and(4) The duties, title, qualifications, and training of personnel of the deepwater port designated as the person in charge and responsible for managing cargo transfers, including ballasting operations if applicable to the deepwater port, in accordance with subpart D of part 154 for oil, and subpart B (Operations) of part 127 for natural gas, respectively, of this chapter.(5) Minimum requirements for watch personnel on board the vessel during transfer operations, such as personnel necessary for checking mooring gear, monitoring communications, and maintaining propulsion and steering on standby.(8) The maximum relief valve settings, the maximum available working pressure, and hydraulic shock to the system without relief valves, or both.(9) Equipment necessary to discharge cargo to the port complex without harm to the environment or to persons involved in the cargo transfer, including piping, adapters, bolted flanges, and quick-disconnect coupling.
Citations to §150.15(l)(8)
-
(l) The procedures for cargo transfer must comply with the applicable requirements of parts 154 and 156 for oil, and subpart B (Operations) to part 127 for natural gas, respectively, of this chapter, including the requirements specified in paragraphs (l)(1) through (l)(10) of this section.(i) Pre-transfer conference;(ii) Inspection of transfer site and equipment such as hoses, connectors, closure devices, monitoring devices, and containment;(iii) Connecting and disconnecting transfer equipment, including a floating hose string for a single point mooring (SPM);(iv) Preparation of the Declaration of Inspection; and(2) The requirements for natural gas transfers in accordance with subpart B to part 127 of this chapter regarding:(i) Pre-transfer conference;(ii) Inspection of transfer site and equipment such as hoses, connectors, closure devices, leak monitoring devices, and containment;(iii) Connecting and disconnecting of transfer equipment, including to a floating hose string for a SPM;(iv) Line purging to test for leaks and to prepare for cool-down or heat-up phases as appropriate;(v) Preparation of the Declaration of Inspection; and(4) The duties, title, qualifications, and training of personnel of the deepwater port designated as the person in charge and responsible for managing cargo transfers, including ballasting operations if applicable to the deepwater port, in accordance with subpart D of part 154 for oil, and subpart B (Operations) of part 127 for natural gas, respectively, of this chapter.(5) Minimum requirements for watch personnel on board the vessel during transfer operations, such as personnel necessary for checking mooring gear, monitoring communications, and maintaining propulsion and steering on standby.(8) The maximum relief valve settings, the maximum available working pressure, and hydraulic shock to the system without relief valves, or both.(9) Equipment necessary to discharge cargo to the port complex without harm to the environment or to persons involved in the cargo transfer, including piping, adapters, bolted flanges, and quick-disconnect coupling.
Citations to §150.15(l)(9)
-
(l) The procedures for cargo transfer must comply with the applicable requirements of parts 154 and 156 for oil, and subpart B (Operations) to part 127 for natural gas, respectively, of this chapter, including the requirements specified in paragraphs (l)(1) through (l)(10) of this section.(i) Pre-transfer conference;(ii) Inspection of transfer site and equipment such as hoses, connectors, closure devices, monitoring devices, and containment;(iii) Connecting and disconnecting transfer equipment, including a floating hose string for a single point mooring (SPM);(iv) Preparation of the Declaration of Inspection; and(2) The requirements for natural gas transfers in accordance with subpart B to part 127 of this chapter regarding:(i) Pre-transfer conference;(ii) Inspection of transfer site and equipment such as hoses, connectors, closure devices, leak monitoring devices, and containment;(iii) Connecting and disconnecting of transfer equipment, including to a floating hose string for a SPM;(iv) Line purging to test for leaks and to prepare for cool-down or heat-up phases as appropriate;(v) Preparation of the Declaration of Inspection; and(4) The duties, title, qualifications, and training of personnel of the deepwater port designated as the person in charge and responsible for managing cargo transfers, including ballasting operations if applicable to the deepwater port, in accordance with subpart D of part 154 for oil, and subpart B (Operations) of part 127 for natural gas, respectively, of this chapter.(5) Minimum requirements for watch personnel on board the vessel during transfer operations, such as personnel necessary for checking mooring gear, monitoring communications, and maintaining propulsion and steering on standby.(8) The maximum relief valve settings, the maximum available working pressure, and hydraulic shock to the system without relief valves, or both.(9) Equipment necessary to discharge cargo to the port complex without harm to the environment or to persons involved in the cargo transfer, including piping, adapters, bolted flanges, and quick-disconnect coupling.
Citations to §150.15(l)(10)
-
(l) The procedures for cargo transfer must comply with the applicable requirements of parts 154 and 156 for oil, and subpart B (Operations) to part 127 for natural gas, respectively, of this chapter, including the requirements specified in paragraphs (l)(1) through (l)(10) of this section.(i) Pre-transfer conference;(ii) Inspection of transfer site and equipment such as hoses, connectors, closure devices, monitoring devices, and containment;(iii) Connecting and disconnecting transfer equipment, including a floating hose string for a single point mooring (SPM);(iv) Preparation of the Declaration of Inspection; and(2) The requirements for natural gas transfers in accordance with subpart B to part 127 of this chapter regarding:(i) Pre-transfer conference;(ii) Inspection of transfer site and equipment such as hoses, connectors, closure devices, leak monitoring devices, and containment;(iii) Connecting and disconnecting of transfer equipment, including to a floating hose string for a SPM;(iv) Line purging to test for leaks and to prepare for cool-down or heat-up phases as appropriate;(v) Preparation of the Declaration of Inspection; and(4) The duties, title, qualifications, and training of personnel of the deepwater port designated as the person in charge and responsible for managing cargo transfers, including ballasting operations if applicable to the deepwater port, in accordance with subpart D of part 154 for oil, and subpart B (Operations) of part 127 for natural gas, respectively, of this chapter.(5) Minimum requirements for watch personnel on board the vessel during transfer operations, such as personnel necessary for checking mooring gear, monitoring communications, and maintaining propulsion and steering on standby.(8) The maximum relief valve settings, the maximum available working pressure, and hydraulic shock to the system without relief valves, or both.(9) Equipment necessary to discharge cargo to the port complex without harm to the environment or to persons involved in the cargo transfer, including piping, adapters, bolted flanges, and quick-disconnect coupling.
Citations to §150.15(w)
-
(a) Each deepwater port operator must ensure that all deepwater port personnel are provided with information and training on recognized hazardous conditions in their workplace, including, but not limited to, electrical, mechanical, and chemical hazards. Specific required training topics are outlined in § 150.15(w) of this part.