US Codex
C.F.R.
Browse by date
Notes

§37.815. May the Government withhold payments? — Inbound Citations

32 C.F.R. § 37.815

Cited by 1 regulation in release Current.

Citations to 32 U.S.C. § 37.815 as a whole

  • (e) You must choose the payment method and tell the recipient how, when, and where to submit payment requests, as discussed in §§ 37.805 through 37.815. Your payment method must take into account sound cash management practices by avoiding unwarranted cash advances. For an expenditure-based TIA, your payment provision must require the return of interest should excess cash balances occur, in accordance with § 37.820. For any TIA using the milestone payment method described in § 37.805(c), you must include language notifying the recipient that post-award administrators may adjust amounts of future milestone payments if a project's expenditures fall too far below the projections that were the basis for setting the amounts (see § 37.575(c) and § 37.1105(c)).