US Codex
C.F.R.
Browse by date
Notes

§37.565. May I use a hybrid instrument that provides fixed support for only a portion of a project?

32 C.F.R. § 37.565

Yes, for a research project that is to be carried out by a number of participants, you may award a TIA that provides for some participants to perform under fixed-support arrangements and others to perform under expenditure-based arrangements. This approach may be useful, for example, if a commercial firm that is a participant will not accept an agreement with all of the post-award requirements of an expenditure-based award. Before using a fixed-support arrangement for that firm's portion of the project, you must judge that it meets the criteria in § 37.305.
Notes, amendments, and revision history

Authority

Authority: 5 U.S.C. 301 and 10 U.S.C. 113.

Source

Source: 68 FR 47160, Aug. 7, 2003, unless otherwise noted.