§816.41. Hydrologic-balance protection.

30 C.F.R. § 816.41

(a)
General. All surface mining and reclamation activities shall be conducted to minimize disturbance of the hydrologic balance within the permit and adjacent areas, to prevent material damage to the hydrologic balance outside the permit area, to assure the protection or replacement of water rights, and to support approved postmining land uses in accordance with the terms and conditions of the approved permit and the performance standards of this part. The regulatory authority may require additional preventative, remedial, or monitoring measures to assure that material damage to the hydrologic balance outside the permit area is prevented. Mining and reclamation practices that minimize water pollution and changes in flow shall be used in preference to water treatment.
(b)
Ground-water protection. In order to protect the hydrologic balance, surface mining activities shall be conducted according to the plan approved under § 780.21(h) of this chapter and the following:
(1)
Ground-water quality shall be protected by handling earth materials and runoff in a manner that minimizes acidic, toxic, or other harmful infiltration to ground-water systems and by managing excavations and other disturbances to prevent or control the discharge of pollutants into the ground water.
(2)
Ground-water quantity shall be protected by handling earth materials and runoff in a manner that will restore the approximate premining recharge capacity of the reclaimed area as a whole, excluding coal mine waste disposal areas and fills, so as to allow the movement of water to the ground-water system.
(c)
Ground-water monitoring.
(1)
Ground-water monitoring shall be conducted according to the ground-water monitoring plan approved under § 780.21(i) of this chapter. The regulatory authority may require additional monitoring when necessary.
(2)
Ground-water monitoring data shall be submitted every 3 months to the regulatory authority or more frequently as prescribed by the regulatory authority. Monitoring reports shall include analytical results from each sample taken during the reporting period. When the analysis of any ground-water sample indicates noncompliance with the permit conditions, then the operator shall promptly notify the regulatory authority and immediately take the actions provided for in §§ 773.17(e) and 780.21(h) of this chapter.
(3)
Ground-water monitoring shall proceed through mining and continue during reclamation until bond release. Consistent with the procedures of § 774.13 of this chapter, the regulatory authority may modify the monitoring requirements, including the parameters covered and the sampling frequency, if the operator demonstrates, using the monitoring data obtained under this paragraph, that—
(i)
The operation has minimized disturbance to the hydrologic balance in the permit and adjacent areas and prevented material damage to the hydrologic balance outside the permit area; water quantity and quality are suitable to support approved postmining land uses; and the water rights of other users have been protected or replaced; or
(ii)
Monitoring is no longer necessary to achieve the purposes set forth in the monitoring plan approved under § 780.21(i) of this chapter.
(4)
Equipment, structures, and other devices used in conjunction with monitoring the quality and quantity of ground water onsite and offsite shall be properly installed, maintained, and operated and shall be removed by the operator when no longer needed.
(d)
Surface-water protection. In order to protect the hydrologic balance, surface mining activities shall be conducted according to the plan approved under § 780.21(h) of this chapter, and the following:
(1)
Surface-water quality shall be protected by handling earth materials, ground-water discharges, and runoff in a manner that minimizes the formation of acidic or toxic drainage; prevents, to the extent possible using the best technology currently available, additional contribution of suspended solids to streamflow outside the permit area; and otherwise prevents water pollution. If drainage control, restabilization and revegetation of disturbed areas, diversion of runoff, mulching, or other reclamation and remedial practices are not adequate to meet the requirements of this section and § 816.42, the operator shall use and maintain the necessary water-treatment facilities or water quality controls.
(2)
Surface-water quality and flow rates shall be protected by handling earth materials and runoff in accordance with the steps outlined in the plan approved under § 780.21(h) of this chapter.
(e)
Surface-water monitoring.
(1)
Surface-water monitoring shall be conducted according to the surface-water monitoring plan approved under § 780.21(j) of this chapter. The regulatory authority may require additional monitoring when necessary.
(2)
Surface-water monitoring data shall be submitted every 3 months to the regulatory authority or more frequently as prescribed by the regulatory authority. Monitoring reports shall include analytical results from each sample taken during the reporting period. When the analysis of any surface-water sample indicates noncompliance with the permit conditions, the operator shall promptly notify the regulatory authority and immediately take the actions provided for in §§ 773.17(e) and 780.21(h) of this chapter. The reporting requirements of this paragraph do not exempt the operator from meeting any National Pollutant Discharge Elimination System (NPDES) reporting requirements.
(3)
Surface-water monitoring shall proceed through mining and continue during reclamation until bond release. Consistent with § 774.13 of this chapter, the regulatory authority may modify the monitoring requirements, except those required by the NPDES permitting authority, including the parameters covered and sampling frequency if the operator demonstrates, using the monitoring data obtained under this paragraph, that—
(i)
The operation has minimized disturbance to the hydrologic balance in the permit and adjacent areas and prevented material damage to the hydrologic balance outside the permit area; water quantity and quality are suitable to support approved postmining land uses; and the water rights of other users have been protected or replaced; or
(ii)
Monitoring is no longer necessary to achieve the purposes set forth in the monitoring plan approved under § 780.21(j) of this chapter.
(4)
Equipment, structures, and other devices used in conjunction with monitoring the quality and quantity of surface water onsite and offsite shall be properly installed, maintained, and operated and shall be removed by the operator when no longer needed.
(f)
Acid- and toxic-forming materials.
(1)
Drainage from acid- and toxic-forming materials into surface water and ground water shall be avoided by—
(i)
Identifying and burying and/or treating, when necessary, materials which may adversely affect water quality, or be detrimental to vegetation or to public health and safety if not buried and/or treated, and
(ii)
Storing materials in a manner that will protect surface water and ground water by preventing erosion, the formation of polluted runoff, and the infiltration of polluted water. Storage shall be limited to the period until burial and/or treatment first become feasible, and so long as storage will not result in any risk of water pollution or other environmental damage.
(2)
Storage, burial or treatment practices shall be consistent with other material handling and disposal provisions of this chapter.
(g)
Transfer of wells. Before final release of bond, exploratory or monitoring wells shall be sealed in a safe and environmentally sound manner in accordance with §§ 816.13 to 816.15. With the prior approval of the regulatory authority, wells may be transferred to another party for further use. At a minimum, the conditions of such transfer shall comply with State and local law and the permittee shall remain responsible for the proper management of the well until bond release in accordance with §§ 816.13 to 816.15.
(h)
Water rights and replacement. Any person who conducts surface mining activities shall replace the water supply of an owner of interest in real property who obtains all or part of his or her supply of water for domestic, agricultural, industrial, or other legitimate use from an underground or surface source, where the water supply has been adversely impacted by contamination, diminution, or interruption proximately resulting from the surface mining activities. Baseline hydrologic information required in §§ 780.21 and 780.22 of this chapter shall be used to determine the extent of the impact of mining upon ground water and surface water.
(i)
Discharges into an underground mine.
(1)
Discharges into an underground mine are prohibited, unless specifically approved by the regulatory authority after a demonstration that the discharge will—
(i)
Minimize disturbance to the hydrologic balance on the permit area, prevent material damage outside the permit area and otherwise eliminate public hazards resulting from surface mining activities;
(ii)
Not result in a violation of applicable water quality standards or effluent limitations;
(iii)
Be at a known rate and quality which shall meet the effluent limitations of § 816.42 for pH and total suspended solids, except that the pH and total suspended-solids limitations may be exceeded, if approved by the regulatory authority; and
(iv)
Meet with the approval of the Mine Safety and Health Administration.
(2)
Discharges shall be limited to the following:
(i)
Water;
(ii)
Coal processing waste;
(iii)
Fly ash from a coal-fired facility;
(iv)
Sludge from an acid-mine-drainage treatment facility;
(v)
Flue-gas desulfurization sludge;
(vi)
Inert materials used for stabilizing underground mines; and
(vii)
Underground mine development wastes.
Notes, amendments, and revision history

Amendments

[48 FR 43990, Sept. 26, 1983, as amended at 81 FR 93392, Dec. 20, 2016; 82 FR 54979, Nov. 17, 2017]

Authority

Authority: 30 U.S.C. 1201 et seq.; and sec 115 of Pub. L. 98-146.

Source

Source: 44 FR 15395, Mar. 13, 1979, unless otherwise noted.

Amendments

[48 FR 43990, Sept. 26, 1983, as amended at 81 FR 93392, Dec. 20, 2016; 82 FR 54979, Nov. 17, 2017]

§816.42. Hydrologic balance: Water quality standards and effluent limitations.

30 C.F.R. § 816.42

Discharges of water from areas disturbed by surface mining activities shall be made in compliance with all applicable State and Federal water quality laws and regulations and with the effluent limitations for coal mining promulgated by the U.S. Environmental Protection Agency set forth in 40 CFR part 434.
Notes, amendments, and revision history

Amendments

[47 FR 47222, Oct. 22, 1982, as amended at 48 FR 44051, Sept. 26, 1983; 81 FR 93392, Dec. 20, 2016; 82 FR 54979, Nov. 17, 2017]

Authority

Authority: 30 U.S.C. 1201 et seq.; and sec 115 of Pub. L. 98-146.

Source

Source: 44 FR 15395, Mar. 13, 1979, unless otherwise noted.

Amendments

[47 FR 47222, Oct. 22, 1982, as amended at 48 FR 44051, Sept. 26, 1983; 81 FR 93392, Dec. 20, 2016; 82 FR 54979, Nov. 17, 2017]

§816.43. Diversions.

30 C.F.R. § 816.43

(a)
General requirements.
(1)
With the approval of the regulatory authority, any flow from mined areas abandoned before May 3, 1978, and any flow from undisturbed areas or reclaimed areas, after meeting the criteria of § 816.46 for siltation structure removal, may be diverted from disturbed areas by means of temporary or permanent diversions. All diversions shall be designed to minimize adverse impacts to the hydrologic balance within the permit and adjacent areas, to prevent material damage outside the permit area and to assure the safety of the public. Diversions shall not be used to divert water into underground mines without approval of the regulatory authority under § 816.41(i).
(2)
The diversion and its appurtenant structures shall be designed, located, constructed, maintained and used to—
(i)
Be stable;
(ii)
Provide protection against flooding and resultant damage to life and property;
(iii)
Prevent, to the extent possible using the best technology currently available, additional contributions of suspended solids to streamflow outside the permit area; and
(iv)
Comply with all applicable local, State, and Federal laws and regulations.
(3)
Temporary diversions shall be removed promptly when no longer needed to achieve the purpose for which they were authorized. The land disturbed by the removal process shall be restored in accordance with this part. Before diversions are removed, downstream water-treatment facilities previously protected by the diversion shall be modified or removed, as necessary, to prevent overtopping or failure of the facilities. This requirement shall not relieve the operator from maintaining water-treatment facilities as otherwise required. A permanent diversion or a stream channel reclaimed after the removal of a temporary diversion shall be designed and constructed so as to restore or approximate the premining characteristics of the original stream channel including the natural riparian vegetation to promote the recovery and the enhancement of the aquatic habitat.
(4)
The regulatory authority may specify design criteria for diversions to meet the requirements of this section.
(b)
Diversion of perennial and intermittent streams.
(1)
Diversion of perennial and intermittent streams within the permit area may be approved by the regulatory authority after making the finding relating to stream buffer zones that the diversion will not adversely affect the water quantity and quality and related environmental resources of the stream.
(2)
The design capacity of channels for temporary and permanent stream channel diversions shall be at least equal to the capacity of the unmodified stream channel immediately upstream and downstream from the diversion.
(3)
The requirements of paragraph (a)(2)(ii) of this section shall be met when the temporary and permanent diversions for perennial and intermittent streams are designed so that the combination of channel, bank and flood-plain configuration is adequate to pass safely the peak runoff of a 10-year, 6-hour precipitation event for a temporary diversion and a 100-year, 6-hour precipitation event for a permanent diversion.
(4)
The design and construction of all stream channel diversions of perennial and intermittent streams shall be certified by a qualified registered professional engineer as meeting the performance standards of this part and any design criteria set by the regulatory authority.
(c)
Diversion of miscellaneous flows.
(1)
Miscellaneous flows, which consist of all flows except for perennial and intermittent streams, may be diverted away from disturbed areas if required or approved by the regulatory authority. Miscellaneous flows shall include ground-water discharges and ephemeral streams.
(2)
The design, location, construction, maintenance, and removal of diversions of miscellaneous flows shall meet all of the performance standards set forth in paragraph (a) of this section:
(3)
The requirements of paragraph (a)(2)(ii) of this section shall be met when the temporary and permanent diversions for miscellaneous flows are designed so that the combination of channel, bank and flood-plain configuration is adequate to pass safely the peak runoff of a 2-year, 6-hour precipitation event for a temporary diversion and a 10-year, 6-hour precipitation event for a permanent diversion.
Notes, amendments, and revision history

Amendments

[48 FR 43991, Sept. 26, 1983, as amended at 73 FR 75882, Dec. 12, 2008; 79 FR 76231, Dec. 22, 2014; 81 FR 93392, Dec. 20, 2016; 82 FR 54979, Nov. 17, 2017]

Authority

Authority: 30 U.S.C. 1201 et seq.; and sec 115 of Pub. L. 98-146.

Source

Source: 44 FR 15395, Mar. 13, 1979, unless otherwise noted.

Amendments

[48 FR 43991, Sept. 26, 1983, as amended at 73 FR 75882, Dec. 12, 2008; 79 FR 76231, Dec. 22, 2014; 81 FR 93392, Dec. 20, 2016; 82 FR 54979, Nov. 17, 2017]

§816.45. Hydrologic balance: Sediment control measures.

30 C.F.R. § 816.45

(a)
Appropriate sediment control measures shall be designed, constructed, and maintained using the best technology currently available to:
(1)
Prevent, to the extent possible, additional contributions of sediment to streamflow or to runoff outside the permit area,
(2)
Meet the more stringent of applicable State or Federal effluent limitations,
(3)
Minimize erosion to the extent possible.
(b)
Sediment control measures include practices carried out within and adjacent to the disturbed area. The sedimentation storage capacity of practices in and downstream from the disturbed area shall reflect the degree to which successful mining and reclamation techniques are applied to reduce erosion and control sediment. Sediment control measures consist of the utilization of proper mining and reclamation methods and sediment control practices, singly or in combination. Sediment control methods include but are not limited to—
(1)
Disturbing the smallest practicable area at any one time during the mining operation through progressive backfilling, grading, and prompt revegetation as required in § 816.111(b);
(2)
Stabilizing the backfill material to promote a reduction in the rate and volume of runoff, in accordance with the requirements of § 816.102;
(3)
Retaining sediment within disturbed areas;
(4)
Diverting runoff away from disturbed areas;
(5)
Diverting runoff using protected channels or pipes through disturbed areas so as not to cause additional erosion;
(6)
Using straw dikes, riprap, check dams, mulches, vegetative sediment filters, dugout ponds, and other measures that reduce overland flow velocity, reduce runoff volume, or trap sediment; and
(7)
Treating with chemicals.
Notes, amendments, and revision history

Amendments

[44 FR 15395, Mar. 13, 1979, as amended at 48 FR 44780, Sept. 30, 1983; 81 FR 93392, Dec. 20, 2016; 82 FR 54979, Nov. 17, 2017]

Authority

Authority: 30 U.S.C. 1201 et seq.; and sec 115 of Pub. L. 98-146.

Source

Source: 44 FR 15395, Mar. 13, 1979, unless otherwise noted.

Amendments

[44 FR 15395, Mar. 13, 1979, as amended at 48 FR 44780, Sept. 30, 1983; 81 FR 93392, Dec. 20, 2016; 82 FR 54979, Nov. 17, 2017]

§816.46. Hydrologic balance: Siltation structures.

30 C.F.R. § 816.46

(a)
For the purpose of this section only, disturbed areas shall not include those areas—
(1)
In which the only surface mining activities include diversion ditches, siltation structures, or roads that are designed constructed and maintained in accordance with this part; and
(2)
For which the upstream area is not otherwise disturbed by the operator.
(b)
General requirements.
(1)
Additional contributions of suspended solids sediment to streamflow or runoff outside the permit area shall be prevented to the extent possible using the best technology currently available.
(2)
Siltation structures for an area shall be constructed before beginning any surface mining activities in that area, and upon construction shall be certified by a qualified registered professional engineer, or in any State which authorizes land surveyors to prepare and certify plans in accordance with § 780.25(a) of this chapter a qualified registered professional land surveyor, to be constructed as designed and as approved in the reclamation plan.
(3)
Any siltation structure which impounds water shall be designed, constructed and maintained in accordance with § 816.49 of this chapter.
(4)
Siltation structures shall be maintained until removal is authorized by the regulatory authority and the disturbed area has been stabilized and revegetated. In no case shall the structure be removed sooner than 2 years after the last augmented seeding.
(5)
When siltation structure is removed, the land on which the siltation structure was located shall be regraded and revegetated in accordance with the reclamation plan and §§ 816.111 through 816.116 of this chapter. Sedimentation ponds approved by the regulatory authority for retention as permanent impoundments may be exempted from this requirement.
(c)
Sedimentation ponds.
(1)
When used, sedimentation ponds shall—
(i)
Be used individually or in series;
(ii)
Be located as near as possible to the disturbed area and out of perennial streams unless approved by the regulatory authority, and
(iii)
Be designed, constructed, and maintained to—
(A)
Provide adequate sediment storage volume;
(B)
Provide adequate detention time to allow the effluent from the ponds to meet State and Federal effluent limitations;
(C)
Contain or treat the 10-year, 24-hour precipitation event (“design event”) unless a lesser design event is approved by the regulatory authority based on terrain, climate, other site-specific conditions and on a demonstration by the operator that the effluent limitations of § 816.42 will be met;
(D)
Provide a nonclogging dewatering device adequate to maintain the detention time required under paragraph (c)(1)(iii)(B) of this section;
(E)
Minimize, to the extent possible, short circuiting;
(F)
Provide periodic sediment removal sufficient to maintain adequate volume for the design event;
(G)
Ensure against excessive settlement;
(H)
Be free of sod, large roots, frozen soil, and acid- or toxic-forming coal-processing waste; and
(I)
Be compacted properly.
(2)
Spillways. A sedimentation pond shall include either a combination of principal and emergency spillways or single spillway configured as specified in § 816.49(a)(9).
(d)
Other treatment facilities.
(1)
Other treatment facilities shall be designed to treat the 10-year, 24-hour precipitation event unless a lesser design event is approved by the regulatory authority based on terrain, climate, other site-specific conditions and a demonstration by the operator that the effluent limitations of § 816.42 will be met.
(2)
Other treatment facilities shall be designed in accordance with the applicable requirements of paragraph (c) of this section.
(e)
Exemptions. Exemptions to the requirements of this section may be granted if—
(1)
The disturbed drainage area within the total disturbed area is small; and
(2)
The operator demonstrates that siltation structures and alternate sediment control measures are not necessary for drainage from the disturbed area to meet the effluent limitations under § 816.42 and the applicable State and Federal water quality standards for the receiving waters.
Notes, amendments, and revision history

Amendments

[48 FR 44051, Sept. 26, 1983, as amended at 53 FR 43605, Oct. 27, 1988; 59 FR 53029, Oct. 20, 1994; 75 FR 60275, Sept. 29, 2010; 79 FR 76231, Dec. 22, 2014; 81 FR 93392, Dec. 20, 2016; 82 FR 54979, Nov. 17, 2017; 90 FR 54577, Nov. 28, 2025]

Authority

Authority: 30 U.S.C. 1201 et seq.; and sec 115 of Pub. L. 98-146.

Source

Source: 44 FR 15395, Mar. 13, 1979, unless otherwise noted.

Amendments

[48 FR 44051, Sept. 26, 1983, as amended at 53 FR 43605, Oct. 27, 1988; 59 FR 53029, Oct. 20, 1994; 75 FR 60275, Sept. 29, 2010; 79 FR 76231, Dec. 22, 2014; 81 FR 93392, Dec. 20, 2016; 82 FR 54979, Nov. 17, 2017; 90 FR 54577, Nov. 28, 2025]

§816.47. Hydrologic balance: Discharge structures.

30 C.F.R. § 816.47

Discharge from sedimentation ponds, permanent and temporary impoundments, coal processing waste dams and embankments, and diversions shall be controlled, by energy dissipators, riprap channels, and other devices, where necessary, to reduce erosion, to prevent deepening or enlargement of stream channels, and to minimize disturbance of the hydrologic balance. Discharge structures shall be designed according to standard engineering-design procedures.
Notes, amendments, and revision history

Amendments

[44 FR 15395, Mar. 13, 1979, as amended at 81 FR 93392, Dec. 20, 2016; 82 FR 54979, Nov. 17, 2017]

Authority

Authority: 30 U.S.C. 1201 et seq.; and sec 115 of Pub. L. 98-146.

Source

Source: 44 FR 15395, Mar. 13, 1979, unless otherwise noted.

Amendments

[44 FR 15395, Mar. 13, 1979, as amended at 81 FR 93392, Dec. 20, 2016; 82 FR 54979, Nov. 17, 2017]

§816.49. Impoundments.

30 C.F.R. § 816.49

(a)
General requirements. The requirements of this paragraph apply to both temporary and permanent impoundments.
(1)
Impoundments meeting the Class B or C criteria for dams in the U.S. Department of Agriculture, Soil Conservation Service Technical Release No. 60 (210-VI-TR60, Oct. 1985), “Earth Dams and Reservoirs,” 1985 shall comply with “Minimum Emergency Spillway Hydrologic Criteria” table in TR-60 and the requirements of this section. The technical release is hereby incorporated by reference. This incorporation by reference was approved by the Director of the Federal Register in accordance with 5 U.S.C. 552(a) and 1 CFR part 51. Copies may be obtained from the National Technical Information Service (NTIS), 5285 Port Royal Road, Springfield, Virginia 22161, order No. PB 87-157509/AS. Copies can be inspected at the OSM Headquarters Office, Office of Surface Mining Reclamation and Enforcement, Administrative Record, 1951 Constitution Avenue NW., Washington, DC, or at the National Archives and Records Administration (NARA). For information on the availability of this material at NARA, call 202-741-6030, or go to: http://www.archives.gov/federal_register/code_of_federal_regulations/ibr_locations.html.
(2)
An impoundment meeting the size or other criteria of § 77.216(a) of this title shall comply with the requirements of § 77.216 of this title and this section.
(3)
Design certification. The design of impoundments shall be certified in accordance with § 780.25(a) of this chapter as designed to meet the requirements of this part using current, prudent, engineering practices and any design criteria established by the regulatory authority. The qualified, registered, professional engineer or qualified, registered, professional, land surveyor shall be experienced in the design and construction of impoundments.
(4)
Stability.
(i)
An impoundment meeting the Class B or C criteria for dams in TR-60, or the size or other criteria of § 77.216(a) of this title shall have a minimum static safety factor of 1.5 for a normal pool with steady state seepage saturation conditions, and a seismic safety factor of at least 1.2.
(ii)
Impoundments not included in paragraph (a)(4)(i) of this section, except for a coal mine waste impounding structure, shall have a minimum static safety factor of 1.3 for a normal pool with steady state seepage saturation conditions or meet the requirements of § 780.25(c)(3).
(5)
Freeboard. Impoundments shall have adequate freeboard to resist overtopping by waves and by sudden increases in storage volume. Impoundments meeting the Class B or C criteria for dams in TR-60 shall comply with the freeboard hydrograph criteria in the “Minimum Emergency Spillway Hydrologic Criteria” table in TR-60.
(6)
Foundation.
(i)
Foundations and abutments for an impounding structure shall be stable during all phases of construction and operation and shall be designed based on adequate and accurate information on the foundation conditions. For an impoundment meeting the Class B or C criteria for dams in TR-60, or the size or other criteria of § 77.216(a) of this title, foundation investigation, as well as any necessary laboratory testing of foundation material, shall be performed to determine the design requirements for foundation stability.
(ii)
All vegetative and organic materials shall be removed and foundations excavated and prepared to resist failure. Cutoff trenches shall be installed if necessary to ensure stability.
(7)
Slope protection shall be provided to protect against surface erosion at the site and protect against sudden drawdown.
(8)
Faces of embankments and surrounding areas shall be vegetated, except that faces where water is impounded may be riprapped or otherwise stabilized in accordance with accepted design practices.
(9)
Spillways. An impoundment shall include either a combination of principal and emergency spillways or a single spillway configured as specified in paragraph (a)(9)(i) of this section, designed and constructed to safely pass the applicable design precipitation event specified in paragraph (a)(9)(ii) of this section, except as set forth in paragraph (c)(2) of this section.
(i)
The regulatory authority may approve a single open-channel spillway that is:
(A)
Of nonerodible construction and designed to carry sustained flows; or
(B)
Earth- or grass-lined and designed to carry short-term, infrequent flows at non-erosive velocities where sustained flows are not expected.
(ii)
Except as specified in paragraph (c)(2) of this section, the required design precipitation event for an impoundment meeting the spillway requirements of paragraph (a)(9) of this section is:
(A)
For an impoundment meeting the Class B or C criteria for dams in TR-60, the emergency spillway hydrograph criteria in the “Minimum Emergency Spillway Hydrologic Criteria” table in TR-60, or greater event as specified by the regulatory authority.
(B)
For an impoundment meeting or exceeding the size or other criteria of § 77.216(a) of this title, a 100-year 6-hour event, or greater event as specified by the regulatory authority.
(C)
For an impoundment not included in paragraph (a)(9)(ii) (A) and (B) of this section, a 25-year 6-hour or greater event as specified by the regulatory authority.
(10)
The vertical portion of any remaining highwall shall be located far enough below the low-water line along the full extent of highwall to provide adequate safety and access for the proposed water users.
(11)
Inspections. Except as provided in paragraph (a)(11)(iv) of this section, a qualified registered professional engineer or other qualified professional specialist under the direction of a professional engineer, shall inspect each impoundment as provided in paragraph (a)(11)(i) of this section. The professional engineer or specialist shall be experienced in the construction of impoundments.
(i)
Inspections shall be made regularly during construction, upon completion of construction, and at least yearly until removal of the structure or release of the performance bond.
(ii)
The qualified registered professional engineer, or qualified registered professional land surveyor as specified in paragraph (a)(11)(iv) of this section, shall promptly after each inspection required in paragraph (a)(11)(i) of this section provide to the regulatory authority a certified report that the impoundment has been constructed and/or maintained as designed and in accordance with the approved plan and this chapter. The report shall include discussion of any appearance of instability, structural weakness or other hazardous condition, depth and elevation of any impounded waters, existing storage capacity, any existing or required monitoring procedures and instrumentation, and any other aspects of the structure affecting stability.
(iii)
A copy of the report shall be retained at or near the minesite.
(iv)
In any State which authorizes land surveyors to prepare and certify plans in accordance with § 780.25(a) of this chapter, a qualified registered professional land surveyor may inspect any temporary or permanent impoundment that does not meet the SCS Class B or C criteria for dams in TR-60, or the size or other criteria of § 77.216(a) of this title and certify and submit the report required by paragraph (a)(11)(ii) of this section, except that all coal mine waste impounding structures covered by § 816.84 of this chapter shall be certified by a qualified registered professional engineer. The professional land surveyor shall be experienced in the construction of impoundments.
(12)
Impoundments meeting the SCS Class B or C criteria for dams in TR-60, or the size or other criteria of § 77.216 of this title must be examined in accordance with § 77.216-3 of this title. Impoundments not meeting the SCS Class B or C criteria for dams in TR-60, or subject to § 77.216 of this title, shall be examined at least quarterly. A qualified person designated by the operator shall examine impoundments for the appearance of structural weakness and other hazardous conditions.
(13)
Emergency procedures. If any examination or inspection discloses that a potential hazard exists, the person who examined the impoundment shall promptly inform the regulatory authority of the finding and of the emergency procedures formulated for public protection and remedial action. If adequate procedures cannot be formulated or implemented, the regulatory authority shall be notified immediately. The regulatory authority shall then notify the appropriate agencies that other emergency procedures are required to protect the public.
(b)
Permanent impoundments. A permanent impoundment of water may be created, if authorized by the regulatory authority in the approved permit based upon the following demonstration:
(1)
The size and configuration of such impoundment will be adequate for its intended purposes.
(2)
The quality of impounded water will be suitable on a permanent basis for its intended use and, after reclamation, will meet applicable State and Federal water quality standards, and discharges from the impoundment will meet applicable effluent limitations and will not degrade the quality of receiving water below applicable State and Federal water quality standards.
(3)
The water level will be sufficiently stable and be capable of supporting the intended use.
(4)
Final grading will provide for adequate safety and access for proposed water users.
(5)
The impoundment will not result in the diminution of the quality and quantity of water utilized by adjacent or surrounding landowners for agricultural, industrial, recreational, or domestic uses.
(6)
The impoundment will be suitable for the approved postmining land use.
(c)
Temporary impoundments.
(1)
The regulatory authority may authorize the construction of temporary impoundments as part of a surface coal mining operation.
(2)
In lieu of meeting the requirements in paragraph (a)(9)(i) of this section, the regulatory authority may approve an impoundment that relies primarily on storage to control the runoff from the design precipitation event when it is demonstrated by the operator and certified by a qualified registered professional engineer or qualified registered professional land surveyor in accordance with § 780.25(a) of this chapter that the impoundment will safely control the design precipitation event, the water from which shall be safely removed in accordance with current, prudent, engineering practices. Such an impoundment shall be located where failure would not be expected to cause loss of life or serious property damage, except where:
(i)
Impoundments meeting the SCS Class B or C criteria for dams in TR-60, or the size or other criteria of § 77.216(a) of this title shall be designed to control the precipitation of the probable maximum precipitation of a 6-hour event, or greater event specified by the regulatory authority.
(ii)
Impoundments not included in paragraph (c)(2)(i) of this section shall be designed to control the precipitation of the 100-year 6-hour event, or greater event specified by the regulatory authority.
Notes, amendments, and revision history

Amendments

[48 FR 44004, Sept. 26, 1983, as amended at 50 FR 16200, Apr. 24, 1985; 53 FR 43605, Oct. 27, 1988; 59 FR 53029, 53030, Oct. 20, 1994; 66 FR 14317, Mar. 12, 2001; 81 FR 93392, Dec. 20, 2016; 82 FR 54979, Nov. 17, 2017]

Authority

Authority: 30 U.S.C. 1201 et seq.; and sec 115 of Pub. L. 98-146.

Source

Source: 44 FR 15395, Mar. 13, 1979, unless otherwise noted.

Amendments

[48 FR 44004, Sept. 26, 1983, as amended at 50 FR 16200, Apr. 24, 1985; 53 FR 43605, Oct. 27, 1988; 59 FR 53029, 53030, Oct. 20, 1994; 66 FR 14317, Mar. 12, 2001; 81 FR 93392, Dec. 20, 2016; 82 FR 54979, Nov. 17, 2017]