§75.519-1. Main power circuits; disconnecting switches; locations.
30 C.F.R. § 75.519-1
Section 75.519 requires (a) that a disconnecting switch be installed on the surface at a point within 500 feet of the place where the main power circuit enters the underground area of a mine, and (b) that, in an instance on which a main power circuit enters the underground area through a shaft or borehole, a disconnecting switch be installed underground within 500 feet of the bottom of the shaft or borehole.
Notes, amendments, and revision history
Authority
Authority: 30 U.S.C. 811, 813(h), 957.
Source
Source: 35 FR 17890, Nov. 20, 1970, unless otherwise noted.