§585.650. When may I begin conducting activities under my GAP?

30 C.F.R. § 585.650

After BOEM approves your GAP, you may begin conducting the approved activities that do not involve a project easement or the construction of facilities on the OCS that BOEM has deemed to be complex or significant.
Notes, amendments, and revision history

Source

Source: 89 FR 42748, May 15, 2024, unless otherwise noted.

Authority

Authority: 43 U.S.C. 1337.