§582.4. Opportunities for review and comment. — Inbound Citations

30 C.F.R. § 582.4

Cited by 3 regulations in release Current.

Citations to §582.4(b)

  • (2) Within 30 days following the completion of an environmental assessment or other NEPA document prepared pursuant to the regulations implementing NEPA or within 30 days following the comment period provided in § 582.4(b) of this part, the Director shall:
    (i) Approve any Delineation Plan which is consistent with the criteria in paragraph (b)(1) of this section;
    (ii) Require the lessee to modify any Delineation Plan that is inconsistent with the criteria in paragraph (b)(1) of this section; or
    (iii) Disapprove a Delineation Plan when it is determined that an activity proposed in the plan would probably cause serious harm or damage to life (including fish and other aquatic life); to property; to natural resources of the OCS including mineral deposits (in areas leased or not leased); or to the marine, coastal, or human environment, and the proposed activity cannot be modified to avoid the conditions.

Citations to §582.4(c)

  • (2) Within 60 days following the release of a final EIS prepared pursuant to NEPA or within 60 days following the comment period provided in § 582.4(c) of this part, the Director shall:
    (i) Approve any Testing Plan which is consistent with the criteria in paragraph (c)(1) of this section;
    (ii) Require the lessee to modify any Testing Plan which is inconsistent with the criteria in paragraph (c)(1) of this section; or
    (iii) Disapprove any Testing Plan when the Director determines the existence of exceptional geological conditions in the lease area, exceptional resource values in the marine or coastal environment, or other exceptional circumstances and that (A) implementation of the activities described in the plan would probably cause serious harm and damage to life (including fish and other aquatic life), to property, to any mineral deposit (in areas leased or not leased), to the National security or defense, or to the marine, coastal, or human environments; (B) that the threat of harm or damage will not disappear or decrease to an acceptable extent within a reasonable period of time; and (C) the advantages of disapproving the Testing Plan outweigh the advantages of development and production of the OCS mineral resources.

Citations to §582.4(d)

  • (2) Within 60 days following the release of a final EIS prepared pursuant to NEPA or within 60 days following the comment period provided in § 582.4(d) of this part, the Director shall:
    (i) Approve any Mining Plan which is consistent with the criteria in paragraph (d)(1) of this section;
    (ii) Require the lessee to modify any Mining Plan which is inconsistent with the criteria in paragraph (d)(1) of this section; or
    (iii) Disapprove any Mining Plan when the Director determines the existence of exceptional geological conditions in the lease area, exceptional resource values in the marine or coastal environment, or other exceptional circumstances, and that:
    (A) Implementation of the activities described in the plan would probably cause serious harm and damage to life (including fish and other aquatic life), to property, to any mineral deposit (in areas leased or not leased), to the National security or defense, or to the marine, coastal, or human environments;
    (B) That the threat of harm or damage will not disappear or decrease to an acceptable extent within a reasonable period of time; and
    (C) The advantages of disapproving the Mining Plan outweigh the advantages of development and production of the OCS mineral resources.