§285.905. When must I submit my decommissioning application? — Inbound Citations
30 C.F.R. § 285.905
Statutory Authority
Cited by 5 regulations in release Current.
Citations to 30 C.F.R. § 285.905 as a whole
-
-
(a) The decommissioning notice is distinct from your decommissioning application and may only be submitted following approval of your decommissioning application, as described in §§ 285.905 through 285.907. You must submit a decommissioning notice at least 60 days before you plan to begin decommissioning activities.
-
(a) In your decommissioning application that you submit to BSEE in accordance with 30 CFR 285.905 and 285.906, you may request that certain facilities authorized in your lease or grant remain in place for activities authorized in this part, elsewhere in this subchapter, or by other applicable Federal laws.
-
(e) You must decommission your site assessment facilities as set forth in 30 CFR part 285, subpart I, upon the termination of your lease. You must submit your decommissioning application as required in 30 CFR 285.905 and 285.906.
-
Upon completion of your approved activities under your GAP, you must decommission your project as set forth in 30 CFR part 285, subpart I. You must submit your decommissioning application as provided in 30 CFR 285.905 and 285.906.