§285.614. When may I begin conducting activities under my approved SAP? — Inbound Citations
30 C.F.R. § 285.614
Statutory Authority
Cited by 2 regulations in release Current.
Citations to §285.614(b)
-
(a) You must submit the following reports to BSEE before installing facilities described in your approved COP (30 CFR 585.632(a)) and, when required by 30 CFR part 585, in your approved SAP (30 CFR 585.614(b)) or GAP (30 CFR 585.651):(1) A Facility Design Report (FDR); and
-
You are required to use a Safety Management System (SMS) for activities conducted on the OCS to develop or operate a lease, from met buoy placement and site assessment work through decommissioning, and to provide your SMS to BSEE upon request. You must also submit a detailed description of the SMS with your COP (as provided in 30 CFR 585.627(d)) and, when required by this part, your SAP (as provided in § 285.614(b)) or GAP (as provided in § 285.651). Your SMS must address: