(a) Whenever you interrupt operations, you must notify the District Manager. Before moving off the well, you must have two independent barriers installed, at least one of which must be a mechanical barrier, as approved by the District Manager. You must install the barriers at appropriate depths within a properly cemented casing string or liner. Before removing a subsea BOP stack or surface BOP stack on a mudline suspension well, you must conduct a negative pressure test in accordance with § 250.721.(1) The events that would cause you to interrupt operations and notify the District Manager include, but are not limited to, the following:(i) Evacuation of the rig crew;(ii) Inability to keep the rig on location;(iii) Repair to major rig or well-control equipment;(iv) Observed flow outside the well's casing (e.g., shallow water flow or bubbling); or(2) The District Manager may approve alternate procedures or barriers, in accordance with § 250.141, if you do not have time to install the required barriers or if special circumstances occur.(3) If you unlatch the BOP or LMRP:(i) Upon relatch of the BOP, you must test according to § 250.734(b)(2), or(ii) Upon relatch of the LMRP, you must test according to § 250.734(b)(3); and(iii) You must submit a revised permit with a written statement from an independent third party certifying that the previous certification under § 250.731(c) remains valid and receive District Manager approval before resuming operations.
-
(3) Perform a pressure test after the repairs are made or additional casing is installed and report the results to the District Manager as specified in § 250.721.
-
(ii) The inner riser for a dual riser configuration is subject to the requirements at § 250.721 for testing the casing or liner.