§250.603. Emergency shutdown system.
30 C.F.R. § 250.603
When well-workover operations are conducted on a well with the tree removed, an emergency shutdown system (ESD) manually controlled station shall be installed near the driller's console or well-servicing unit operator's work station, except when there is no other hydrocarbon-producing well or other hydrocarbon flow on the platform.
Notes, amendments, and revision history
Authority
Authority: 30 U.S.C. 1751, 31 U.S.C. 9701, 33 U.S.C. 1321(j)(1)(C), 43 U.S.C. 1334.
Source
Source: 76 FR 64462, Oct. 18, 2011, unless otherwise noted.