§250.433. What are the diverter actuation and testing requirements?
30 C.F.R. § 250.433
When you install the diverter system, you must actuate the diverter sealing element, diverter valves, and diverter-control systems and control stations. You must also flow-test the vent lines.
For drilling operations with a surface wellhead configuration, you must actuate the diverter system at least once every 24-hour period after the initial test. After you have nippled up on conductor casing, you must pressure-test the diverter-sealing element and diverter valves to a minimum of 200 psi. While the diverter is installed, you must conduct subsequent pressure tests within 7 days after the previous test.
For floating drilling operations with a subsea BOP stack, you must actuate the diverter system within 7 days after the previous actuation. For subsequent testing, you may partially actuate the diverter element and a flow test is not required.
You must alternate actuations and tests between control stations.
Notes, amendments, and revision history
Amendments
[76 FR 64462, Oct. 18, 2011, as amended at 84 FR 21975, May 15, 2019]
Authority
Authority: 30 U.S.C. 1751, 31 U.S.C. 9701, 33 U.S.C. 1321(j)(1)(C), 43 U.S.C. 1334.
Source
Source: 76 FR 64462, Oct. 18, 2011, unless otherwise noted.
Amendments
[76 FR 64462, Oct. 18, 2011, as amended at 84 FR 21975, May 15, 2019]