§250.431. What are the diverter design and installation requirements?
30 C.F.R. § 250.431
You must design and install your diverter system to:
Use diverter spool outlets and diverter lines that have a nominal diameter of at least 10 inches for surface wellhead configurations and at least 12 inches for floating drilling operations;
Use dual diverter lines arranged to provide for downwind diversion capability;
Use at least two diverter control stations. One station must be on the drilling floor. The other station must be in a readily accessible location away from the drilling floor;
Use only remote-controlled valves in the diverter lines. All valves in the diverter system must be full-opening. You may not install manual or butterfly valves in any part of the diverter system;
Minimize the number of turns (only one 90-degree turn allowed for each line for bottom-founded drilling units) in the diverter lines, maximize the radius of curvature of turns, and target all right angles and sharp turns;
Anchor and support the entire diverter system to prevent whipping and vibration; and
Protect all diverter-control instruments and lines from possible damage by thrown or falling objects.
Notes, amendments, and revision history
Authority
Authority: 30 U.S.C. 1751, 31 U.S.C. 9701, 33 U.S.C. 1321(j)(1)(C), 43 U.S.C. 1334.
Source
Source: 76 FR 64462, Oct. 18, 2011, unless otherwise noted.