§250.195. What notification does BSEE require on the production status of wells?
30 C.F.R. § 250.195
You must notify the appropriate BSEE District Manager when you successfully complete or recomplete a well for production. You must:
Notify the District Manager within 5 working days of placing the well in a production status. You must confirm oral notification by telefax or e-mail within those 5 working days.
Provide the following information in your notification—
Lessee or operator name;
Well number, lease number, and OCS area and block designations;
Date you placed the well on production (indicate whether or not this is first production on the lease);
Type of production; and
Measured depth of the production interval.
Notes, amendments, and revision history
Authority
Authority: 30 U.S.C. 1751, 31 U.S.C. 9701, 33 U.S.C. 1321(j)(1)(C), 43 U.S.C. 1334.
Source
Source: 76 FR 64462, Oct. 18, 2011, unless otherwise noted.