US Codex
C.F.R.
Browse by date
Notes

§2702.4. Response to request; processing; determinations. — Inbound Citations

29 C.F.R. § 2702.4

Cited by 8 regulations in release Current.

Citations to §2702.4(a)(1)

  • (1) Except in circumstances described in paragraph (b)(2) or (3) of this section, upon receipt of a request, a Commission FOIA officer will reach a determination to grant, deny, or partially grant the request within 20 business days after receipt by the Commission's FOIA Office.
    (2) In unusual circumstances, it may not be possible for the agency to reach a determination within 20 business days. When additional time is needed to respond to the initial request, the Commission shall notify the requester in writing within the 20 business day period, describe the circumstances causing the delay, and indicate the anticipated date for a substantive response that may not exceed 10 additional business days, except as provided in paragraph (b)(2)(i) of this section.
    (i) Unusual circumstances that may warrant delay include:
    (A) The need to search for and collect the requested records from facilities that are separate from the office processing the request;
    (B) The need to search for, collect, and appropriately examine a voluminous amount of separate and distinct records that are requested in a single request;
    (C) The need for consultation, which shall be conducted with all practicable speed, with another agency having a substantial interest in the determination of the request, or among two or more components of the agency having substantial subject matter interest in the request; and
    (ii) With respect to a request for which a written notice has extended the time limit by 10 additional business days, if the Commission determines that it cannot make a response determination within that additional 10 business day period, the requester will be notified and provided an opportunity to limit the scope of the request so that it may be processed within the extended time limit, or an opportunity to arrange an alternative time frame for processing the request or a modified request. See § 2702.10 for fee adjustments applicable to processing time delays.
    (3) While it is recommended that a request for expedited services be submitted with the initial § 2702.3(a) request, such request may be made at any time. A person may request expedited processing of a § 2702.3(a) request for records in cases where the requester can demonstrate a compelling need for said records. Requesters will be notified of the determination in accordance with paragraph (d)(4) of this section. A demonstration of compelling need by a person making a request for expedited processing shall be made by a statement certified by such person to be true and correct to the best of his or her knowledge and belief. For purposes of this paragraph (b)(3), a “compelling need” means:
    (i) That a failure to obtain the requested records on an expedited basis could reasonably be expected to pose an imminent threat to the life or physical safety of an individual; or
    (ii) The information is urgently needed by a person primarily engaged in disseminating information in order to inform the public concerning actual or alleged Federal Government activity; or
    (iii) The records are necessary to assist with meeting an impending deadline set by a Commission Judge or the Commission in a pending case to which the requester is a party.

Citations to §2702.4(a)(2)

  • (1) Except in circumstances described in paragraph (b)(2) or (3) of this section, upon receipt of a request, a Commission FOIA officer will reach a determination to grant, deny, or partially grant the request within 20 business days after receipt by the Commission's FOIA Office.
    (2) In unusual circumstances, it may not be possible for the agency to reach a determination within 20 business days. When additional time is needed to respond to the initial request, the Commission shall notify the requester in writing within the 20 business day period, describe the circumstances causing the delay, and indicate the anticipated date for a substantive response that may not exceed 10 additional business days, except as provided in paragraph (b)(2)(i) of this section.
    (i) Unusual circumstances that may warrant delay include:
    (A) The need to search for and collect the requested records from facilities that are separate from the office processing the request;
    (B) The need to search for, collect, and appropriately examine a voluminous amount of separate and distinct records that are requested in a single request;
    (C) The need for consultation, which shall be conducted with all practicable speed, with another agency having a substantial interest in the determination of the request, or among two or more components of the agency having substantial subject matter interest in the request; and
    (ii) With respect to a request for which a written notice has extended the time limit by 10 additional business days, if the Commission determines that it cannot make a response determination within that additional 10 business day period, the requester will be notified and provided an opportunity to limit the scope of the request so that it may be processed within the extended time limit, or an opportunity to arrange an alternative time frame for processing the request or a modified request. See § 2702.10 for fee adjustments applicable to processing time delays.
    (3) While it is recommended that a request for expedited services be submitted with the initial § 2702.3(a) request, such request may be made at any time. A person may request expedited processing of a § 2702.3(a) request for records in cases where the requester can demonstrate a compelling need for said records. Requesters will be notified of the determination in accordance with paragraph (d)(4) of this section. A demonstration of compelling need by a person making a request for expedited processing shall be made by a statement certified by such person to be true and correct to the best of his or her knowledge and belief. For purposes of this paragraph (b)(3), a “compelling need” means:
    (i) That a failure to obtain the requested records on an expedited basis could reasonably be expected to pose an imminent threat to the life or physical safety of an individual; or
    (ii) The information is urgently needed by a person primarily engaged in disseminating information in order to inform the public concerning actual or alleged Federal Government activity; or
    (iii) The records are necessary to assist with meeting an impending deadline set by a Commission Judge or the Commission in a pending case to which the requester is a party.

Citations to §2702.4(a)(3)

  • (1) Except in circumstances described in paragraph (b)(2) or (3) of this section, upon receipt of a request, a Commission FOIA officer will reach a determination to grant, deny, or partially grant the request within 20 business days after receipt by the Commission's FOIA Office.
    (2) In unusual circumstances, it may not be possible for the agency to reach a determination within 20 business days. When additional time is needed to respond to the initial request, the Commission shall notify the requester in writing within the 20 business day period, describe the circumstances causing the delay, and indicate the anticipated date for a substantive response that may not exceed 10 additional business days, except as provided in paragraph (b)(2)(i) of this section.
    (i) Unusual circumstances that may warrant delay include:
    (A) The need to search for and collect the requested records from facilities that are separate from the office processing the request;
    (B) The need to search for, collect, and appropriately examine a voluminous amount of separate and distinct records that are requested in a single request;
    (C) The need for consultation, which shall be conducted with all practicable speed, with another agency having a substantial interest in the determination of the request, or among two or more components of the agency having substantial subject matter interest in the request; and
    (ii) With respect to a request for which a written notice has extended the time limit by 10 additional business days, if the Commission determines that it cannot make a response determination within that additional 10 business day period, the requester will be notified and provided an opportunity to limit the scope of the request so that it may be processed within the extended time limit, or an opportunity to arrange an alternative time frame for processing the request or a modified request. See § 2702.10 for fee adjustments applicable to processing time delays.
    (3) While it is recommended that a request for expedited services be submitted with the initial § 2702.3(a) request, such request may be made at any time. A person may request expedited processing of a § 2702.3(a) request for records in cases where the requester can demonstrate a compelling need for said records. Requesters will be notified of the determination in accordance with paragraph (d)(4) of this section. A demonstration of compelling need by a person making a request for expedited processing shall be made by a statement certified by such person to be true and correct to the best of his or her knowledge and belief. For purposes of this paragraph (b)(3), a “compelling need” means:
    (i) That a failure to obtain the requested records on an expedited basis could reasonably be expected to pose an imminent threat to the life or physical safety of an individual; or
    (ii) The information is urgently needed by a person primarily engaged in disseminating information in order to inform the public concerning actual or alleged Federal Government activity; or
    (iii) The records are necessary to assist with meeting an impending deadline set by a Commission Judge or the Commission in a pending case to which the requester is a party.

Citations to §2702.4(a)(4)

  • (1) Except in circumstances described in paragraph (b)(2) or (3) of this section, upon receipt of a request, a Commission FOIA officer will reach a determination to grant, deny, or partially grant the request within 20 business days after receipt by the Commission's FOIA Office.
    (2) In unusual circumstances, it may not be possible for the agency to reach a determination within 20 business days. When additional time is needed to respond to the initial request, the Commission shall notify the requester in writing within the 20 business day period, describe the circumstances causing the delay, and indicate the anticipated date for a substantive response that may not exceed 10 additional business days, except as provided in paragraph (b)(2)(i) of this section.
    (i) Unusual circumstances that may warrant delay include:
    (A) The need to search for and collect the requested records from facilities that are separate from the office processing the request;
    (B) The need to search for, collect, and appropriately examine a voluminous amount of separate and distinct records that are requested in a single request;
    (C) The need for consultation, which shall be conducted with all practicable speed, with another agency having a substantial interest in the determination of the request, or among two or more components of the agency having substantial subject matter interest in the request; and
    (ii) With respect to a request for which a written notice has extended the time limit by 10 additional business days, if the Commission determines that it cannot make a response determination within that additional 10 business day period, the requester will be notified and provided an opportunity to limit the scope of the request so that it may be processed within the extended time limit, or an opportunity to arrange an alternative time frame for processing the request or a modified request. See § 2702.10 for fee adjustments applicable to processing time delays.
    (3) While it is recommended that a request for expedited services be submitted with the initial § 2702.3(a) request, such request may be made at any time. A person may request expedited processing of a § 2702.3(a) request for records in cases where the requester can demonstrate a compelling need for said records. Requesters will be notified of the determination in accordance with paragraph (d)(4) of this section. A demonstration of compelling need by a person making a request for expedited processing shall be made by a statement certified by such person to be true and correct to the best of his or her knowledge and belief. For purposes of this paragraph (b)(3), a “compelling need” means:
    (i) That a failure to obtain the requested records on an expedited basis could reasonably be expected to pose an imminent threat to the life or physical safety of an individual; or
    (ii) The information is urgently needed by a person primarily engaged in disseminating information in order to inform the public concerning actual or alleged Federal Government activity; or
    (iii) The records are necessary to assist with meeting an impending deadline set by a Commission Judge or the Commission in a pending case to which the requester is a party.

Citations to §2702.4(a)(5)

  • (1) Except in circumstances described in paragraph (b)(2) or (3) of this section, upon receipt of a request, a Commission FOIA officer will reach a determination to grant, deny, or partially grant the request within 20 business days after receipt by the Commission's FOIA Office.
    (2) In unusual circumstances, it may not be possible for the agency to reach a determination within 20 business days. When additional time is needed to respond to the initial request, the Commission shall notify the requester in writing within the 20 business day period, describe the circumstances causing the delay, and indicate the anticipated date for a substantive response that may not exceed 10 additional business days, except as provided in paragraph (b)(2)(i) of this section.
    (i) Unusual circumstances that may warrant delay include:
    (A) The need to search for and collect the requested records from facilities that are separate from the office processing the request;
    (B) The need to search for, collect, and appropriately examine a voluminous amount of separate and distinct records that are requested in a single request;
    (C) The need for consultation, which shall be conducted with all practicable speed, with another agency having a substantial interest in the determination of the request, or among two or more components of the agency having substantial subject matter interest in the request; and
    (ii) With respect to a request for which a written notice has extended the time limit by 10 additional business days, if the Commission determines that it cannot make a response determination within that additional 10 business day period, the requester will be notified and provided an opportunity to limit the scope of the request so that it may be processed within the extended time limit, or an opportunity to arrange an alternative time frame for processing the request or a modified request. See § 2702.10 for fee adjustments applicable to processing time delays.
    (3) While it is recommended that a request for expedited services be submitted with the initial § 2702.3(a) request, such request may be made at any time. A person may request expedited processing of a § 2702.3(a) request for records in cases where the requester can demonstrate a compelling need for said records. Requesters will be notified of the determination in accordance with paragraph (d)(4) of this section. A demonstration of compelling need by a person making a request for expedited processing shall be made by a statement certified by such person to be true and correct to the best of his or her knowledge and belief. For purposes of this paragraph (b)(3), a “compelling need” means:
    (i) That a failure to obtain the requested records on an expedited basis could reasonably be expected to pose an imminent threat to the life or physical safety of an individual; or
    (ii) The information is urgently needed by a person primarily engaged in disseminating information in order to inform the public concerning actual or alleged Federal Government activity; or
    (iii) The records are necessary to assist with meeting an impending deadline set by a Commission Judge or the Commission in a pending case to which the requester is a party.

Citations to §2702.4(b)

  • (a) No fees shall be charged to any requester, including commercial use requesters, if the anticipated cost of processing and collecting the fee would be equal to or greater than the fee itself. Accordingly, the Commission has determined that fees of less than $20 shall be waived. If the Commission fails to comply with the time limits in § 2702.4(b), including the requirements related to the 10-day extension for unusual circumstances, search fees will not be assessed and, for requesters described in 30 U.S.C. 552(a)(4)(A)(ii)(II), duplication fees will not be assessed. See Commission's FOIA Guide for further information.

Citations to §2702.4(b)(3)

  • (b) If the requester desires expedited processing or a waiver or reduction of fees, such requests must be in writing and should be included in the initial request for information filed in accordance with paragraph (a) of this section. See §§ 2702.4(b)(3) and 2702.10 for additional requirements.
  • (c) The appeal must include a copy of the initial request to expedite, a copy of the determination denying the request, and a detailed explanation demonstrating a compelling need as stated in § 2702.4(b)(3). The Commission will provide expeditious consideration of administrative appeals of determinations on whether to provide expedited processing. Once a determination has been made to grant expedited processing, the Commission will process the request as soon as practicable.